Job Info for 2451-02-013

County: CULBERSON Highway: RM 652 Date: 11/04/2020 (4 years ago) Engineer's Estimate: $49,437,215 Control Number: 2451-02-013
Project: C 2451-2-13 District: EL PASO Time: 480 WORKING DAYS Type: FULL DEPTH REHAB
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $49,437,214.80
DAN WILLIAMS COMPANY   $49,745,889.15 1
0.62% | $308,674.35
J.D. ABRAMS, L.P.   $51,986,898.43 2
5.16% | $2,549,683.63
4.5% | $2,241,009.28

Bid Items

Items: 102, 0 filtered
CULBERSON RM 652  |  EL PASO  |  2451-02-013  |  11/04/2020  |  $49,437,215  |  C 2451-2-13  |  FULL DEPTH REHAB  |  480 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DAN WILLIAMS COMPANY J.D. ABRAMS, L.P.
100 6002 PREPARING ROW STA 646.000 $900.000 $1,500.000 $7,500.000
105 6044 REMOVING STAB BASE AND ASPH PAV (10") SY 256,802.000 $6.000 $4.000 $6.000
110 6001 EXCAVATION (ROADWAY) CY 118,218.000 $20.000 $20.000 $17.500
132 6002 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 166,395.000 $26.000 $40.000 $28.800
134 6005 BACKFILL TY A CY 43,564.000 $35.000 $34.500 $45.000
150 6002 BLADING HR 110.000 $175.000 $105.000 $95.800
216 6001 PROOF ROLLING HR 110.000 $135.000 $60.000 $56.610
247 6391 FL BS (RDWY DEL)(TY A GR 5) TON 220,050.000 $48.000 $35.000 $23.130
310 6005 PRIME COAT (AE-P) GAL 51,571.000 $4.500 $7.000 $2.500
314 6009 EMULS ASPH (EROSN CONT)(MULTI) GAL 11,649.000 $5.000 $6.500 $3.500
316 6001 ASPH (MULTI OPTION) GAL 195,969.000 $4.000 $4.000 $3.270
316 6224 AGGR(TY-PB GR-4 SAC-B) CY 2,902.000 $125.000 $200.000 $200.000
340 6106 D-GR HMA(SQ) TY-D PG64-22 TON 2,367.000 $160.000 $135.000 $250.000
354 6051 PLANE ASPH CONC PAV (0" TO 1 1/2") SY 49.000 $2.500 $50.000 $44.900
400 6002 STRUCT EXCAV (BOX) CY 8,142.000 $20.000 $1.000 $1.000
401 6001 FLOWABLE BACKFILL CY 2,104.000 $175.000 $300.000 $270.110
402 6001 TRENCH EXCAVATION PROTECTION LF 953.000 $4.500 $6.500 $1.250
403 6001 TEMPORARY SPL SHORING SF 24,178.000 $50.000 $22.000 $37.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 10,029.000 $120.000 $120.000 $118.990
432 6041 RIPRAP (SPECIAL) CY 19.000 $150.000 $300.000 $156.030
459 6014 GABION MATTRESSES (GALV) (24 IN) SY 26,454.000 $150.000 $135.000 $135.000
462 6002 CONC BOX CULV (3 FT X 3 FT) LF 230.000 $240.000 $300.000 $303.910
462 6003 CONC BOX CULV (4 FT X 2 FT) LF 112.000 $250.000 $290.000 $304.550
462 6014 CONC BOX CULV (7 FT X 3 FT) LF 1,454.000 $425.000 $490.000 $527.660
462 6032 CONC BOX CULV (10 FT X 8 FT) LF 312.000 $1,200.000 $1,000.000 $1,387.430
462 6043 CONC BOX CULV (12 FT X 10 FT) LF 536.000 $1,300.000 $1,200.000 $1,773.680
464 6008 RC PIPE (CL III)(36 IN) LF 1,185.000 $125.000 $150.000 $216.520
464 6018 RC PIPE (CL IV)(24 IN) LF 970.000 $130.000 $110.000 $127.830
466 6054 HEADWALL (CH - FW - 45) (DIA= 36 IN) EA 2.000 $6,000.000 $9,500.000 $8,698.360
466 6176 WINGWALL (PW - 1) (HW=15 FT) EA 2.000 $40,000.000 $130,000.000 $101,742.720
466 6186 WINGWALL (PW - 2) (HW=11 FT) EA 4.000 $22,000.000 $45,000.000 $32,268.560
466 6187 WINGWALL (PW - 2) (HW=12 FT) EA 4.000 $34,000.000 $50,000.000 $42,276.640
466 6188 WINGWALL (PW - 2) (HW=13 FT) EA 2.000 $35,000.000 $95,000.000 $73,422.240
466 6195 WINGWALL (PW - 2) (HW=6 FT) EA 12.000 $15,000.000 $25,000.000 $13,198.670
466 6196 WINGWALL (PW - 2) (HW=7 FT) EA 4.000 $17,000.000 $22,000.000 $12,573.550
466 6198 WINGWALL (PW - 2) (HW=9 FT) EA 2.000 $19,000.000 $35,000.000 $31,187.810
467 6148 SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C) EA 4.000 $8,000.000 $6,500.000 $1,481.150
467 6253 SET (TY I)(S= 7 FT)(HW= 6 FT)(3:1) (C) EA 4.000 $12,000.000 $9,000.000 $3,207.440
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 46.000 $2,250.000 $1,700.000 $1,728.610
467 6448 SET (TY II) (36 IN) (RCP) (3: 1) (C) EA 30.000 $2,400.000 $3,000.000 $2,202.230
496 6001 REMOV STR (BOX CULVERT) EA 12.000 $12,000.000 $5,500.000 $4,627.220
496 6005 REMOV STR (WINGWALL) EA 54.000 $1,300.000 $1,400.000 $1,460.080
496 6007 REMOV STR (PIPE) LF 1,140.000 $35.000 $15.000 $30.520
500 6001 MOBILIZATION LS 1.000 $3,000,000.000 $4,500,000.000 $4,985,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 24.000 $20,000.000 $15,000.000 $9,511.570
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 5,772.000 $20.000 $30.000 $6.290
506 6024 CONSTRUCTION EXITS (REMOVE) SY 5,772.000 $8.000 $6.000 $0.880
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 4,180.000 $4.000 $3.000 $6.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 4,180.000 $2.000 $1.000 $1.460
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 24.000 $6,000.000 $5,000.000 $10,000.000
510 6004 ONE-WAY TRAFFIC CONTROL (PORT TRAF SIG) DAY 960.000 $300.000 $120.000 $42.460
512 6005 PORT CTB (FUR & INST)(F-SHAPE)(TY 1) LF 10,620.000 $75.000 $65.000 $82.710
512 6029 PORT CTB (MOVE)(F-SHAPE)(TY 1) LF 107,520.000 $6.000 $1.750 $4.000
512 6041 PORT CTB (STKPL)(F-SHAPE)(TY 1) LF 10,620.000 $8.000 $2.500 $4.000
530 6004 DRIVEWAYS (CONC) SY 489.000 $85.000 $100.000 $100.000
530 6005 DRIVEWAYS (ACP) SY 5,053.000 $70.000 $75.000 $50.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 128,520.000 $0.200 $0.100 $0.100
533 6004 RUMBLE STRIPS (CENTERLINE) ASPHALT LF 64,355.000 $0.200 $0.100 $0.110
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 14,800.000 $30.000 $18.000 $35.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 475.000 $36.000 $20.000 $32.000
540 6033 MTL BM GD FEN (LONG SPAN SYSTEM) EA 18.000 $1,450.000 $1,000.000 $2,200.000
540 6035 MTL BM GD FEN TRANS (31"-28") EA 4.000 $625.000 $500.000 $13,000.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 870.000 $4.500 $2.000 $32.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 66.000 $3,000.000 $3,000.000 $4,500.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 200.000 $2,000.000 $600.000 $1,500.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 26.000 $1,000.000 $700.000 $281.110
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 26.000 $12,000.000 $8,000.000 $8,243.860
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 64.000 $700.000 $650.000 $672.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 12.000 $750.000 $850.000 $887.250
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 1.000 $900.000 $850.000 $892.500
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 5.000 $800.000 $950.000 $966.000
644 6076 REMOVE SM RD SN SUP&AM EA 35.000 $120.000 $100.000 $105.000
658 6011 INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI) EA 292.000 $60.000 $80.000 $84.000
658 6047 INSTL OM ASSM (OM-2Y)(WC)GND EA 125.000 $65.000 $80.000 $84.000
658 6060 REMOVE DELIN & OBJECT MARKER ASSMS EA 218.000 $30.000 $70.000 $73.500
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 258,120.000 $0.220 $0.150 $0.150
662 6050 WK ZN PAV MRK REMOV (REFL) TY II-A-A EA 1,300.000 $3.500 $5.350 $5.620
662 6063 WK ZN PAV MRK REMOV (W)4"(SLD) LF 5,200.000 $1.400 $1.150 $1.210
662 6075 WK ZN PAV MRK REMOV (W)24"(SLD) LF 624.000 $2.950 $4.500 $4.730
662 6095 WK ZN PAV MRK REMOV (Y)4"(SLD) LF 99,840.000 $1.350 $1.150 $1.210
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 6,455.000 $1.500 $2.000 $0.460
662 6110 WK ZN PAV MRK SHT TERM (TAB)TY Y EA 6,455.000 $1.500 $2.000 $0.470
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 12.000 $6.000 $4.850 $5.100
666 6170 REFL PAV MRK TY II (W) 4" (SLD) LF 126,931.000 $0.250 $0.100 $0.090
666 6205 REFL PAV MRK TY II (Y) 4" (BRK) LF 14,250.000 $0.250 $0.120 $0.110
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 40,570.000 $0.250 $0.100 $0.090
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 126,931.000 $0.600 $0.600 $0.620
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 14,250.000 $0.600 $0.600 $0.630
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 40,570.000 $0.600 $0.600 $0.620
672 6009 REFL PAV MRKR TY II-A-A EA 1,229.000 $3.750 $3.500 $3.500
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 64,530.000 $1.000 $0.350 $0.350
700 6001 POTHOLE REPAIR (STANDARD) SY 650.000 $125.000 $55.000 $106.000
2005 6001 FILTER FABRIC (TY 2) SY 25.000 $43.000 $6.000 $10.000
3075 6001 GEOGRID BASE REINFORCEMENT SY 98,318.000 $3.000 $1.750 $3.000
3077 6022 SP MIXES SP-C SAC-A PG70-22 TON 34,727.000 $100.000 $130.000 $121.000
3077 6075 TACK COAT GAL 47,306.000 $4.000 $5.000 $2.250
3088 6001 CEMENT TON 2,581.000 $200.000 $180.000 $200.000
3088 6002 ASPHALT BINDER (PG 64-22) TON 4,729.000 $450.000 $475.000 $690.000
3088 6005 FOAMED ASPHALT TREAT (10")(DC) SY 360,333.000 $4.000 $4.250 $4.500
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $20,000.000 $15,000.000 $1.000
6185 6002 TMA (STATIONARY) DAY 1,920.000 $150.000 $210.000 $135.000
6185 6005 TMA (MOBILE OPERATION) DAY 104.000 $150.000 $375.000 $455.000
Totals: $49,437,214.80 $49,745,889.15 $51,986,898.43