PREPARING ROW
|
STA
|
362.000
|
$400.000
|
$200.000
|
$4,800.000
|
$324.000
|
|
|
REMOVING STAB BASE & ASPH PAV (4"-22")
|
SY
|
176,584.000
|
$2.000
|
$2.000
|
$1.050
|
$1.850
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
78,093.000
|
$9.000
|
$25.000
|
$14.100
|
$14.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
56,646.400
|
$10.500
|
$20.000
|
$28.500
|
$36.250
|
|
|
BACKFILL TY A
|
CY
|
39,908.700
|
$43.000
|
$20.000
|
$43.000
|
$69.000
|
|
|
BLADING
|
HR
|
62.000
|
$285.000
|
$120.000
|
$110.000
|
$295.000
|
|
|
PROOF ROLLING
|
HR
|
62.000
|
$120.000
|
$160.000
|
$92.000
|
$131.000
|
|
|
FL BS (RDWY DEL)(TY A GR 5)
|
TON
|
95,088.000
|
$50.000
|
$30.000
|
$18.500
|
$29.600
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
6,415.000
|
$4.000
|
$4.000
|
$2.200
|
$3.940
|
|
|
ASPH (AC-20-5TR)
|
GAL
|
35,205.000
|
$3.000
|
$4.000
|
$5.100
|
$4.300
|
|
|
ASPH (RC-250)
|
GAL
|
26,600.000
|
$4.000
|
$4.500
|
$5.100
|
$4.750
|
|
|
AGGR(TY-B GR-4 SAC-A)
|
CY
|
891.000
|
$60.000
|
$110.000
|
$155.000
|
$189.000
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
735.000
|
$75.000
|
$110.000
|
$83.000
|
$234.000
|
|
|
TOM (ASPHALT) PG 76-22
|
TON
|
582.700
|
$575.000
|
$900.000
|
$1,000.000
|
$994.000
|
|
|
TOM-C (AGGREGATE) SAC-A
|
TON
|
9,143.500
|
$62.000
|
$110.000
|
$82.000
|
$96.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
1,230.000
|
$275.000
|
$125.000
|
$250.000
|
$221.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
1,056.000
|
$6.100
|
$1.000
|
$24.500
|
$1.400
|
|
|
TEMPORARY SPL SHORING
|
SF
|
9,060.000
|
$13.000
|
$1.000
|
$5.000
|
$58.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
2,336.000
|
$156.940
|
$150.000
|
$129.000
|
$132.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(24 IN)
|
CY
|
646.000
|
$214.000
|
$150.000
|
$85.000
|
$209.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
2,363.000
|
$83.000
|
$100.000
|
$54.000
|
$88.000
|
|
|
CMP (GAL STL 30 IN)
|
LF
|
2,122.000
|
$74.000
|
$120.000
|
$67.000
|
$98.000
|
|
|
CMP (GAL STL 36 IN)
|
LF
|
404.000
|
$103.000
|
$140.000
|
$69.000
|
$108.000
|
|
|
CMP (GAL STL 48 IN)
|
LF
|
633.000
|
$104.000
|
$175.000
|
$95.000
|
$153.000
|
|
|
CONC BOX CULV (8 FT X 8 FT)
|
LF
|
53.000
|
$900.000
|
$1,500.000
|
$1,100.000
|
$1,600.000
|
|
|
CONC BOX CULV (10 FT X 7 FT)
|
LF
|
55.000
|
$800.000
|
$1,500.000
|
$1,300.000
|
$1,900.000
|
|
|
CONC BOX CULV (10 FT X 8 FT)
|
LF
|
271.000
|
$500.000
|
$1,500.000
|
$1,400.000
|
$1,475.000
|
|
|
WINGWALL (PW - 2) (HW=10 FT)
|
EA
|
2.000
|
$26,000.000
|
$31,000.000
|
$70,000.000
|
$30,500.000
|
|
|
WINGWALL (PW - 2) (HW=11 FT)
|
EA
|
4.000
|
$31,500.000
|
$32,000.000
|
$58,000.000
|
$38,500.000
|
|
|
WINGWALL (PW - 2) (HW=12 FT)
|
EA
|
2.000
|
$36,750.000
|
$33,000.000
|
$1.000
|
$43,000.000
|
|
|
WINGWALL (PW - 2) (HW=9 FT)
|
EA
|
2.000
|
$28,000.000
|
$30,000.000
|
$58,000.000
|
$24,000.000
|
|
|
SET (TY II) (24 IN) (CMP) (3: 1) (C)
|
EA
|
54.000
|
$1,121.000
|
$1,800.000
|
$2,700.000
|
$3,400.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
16.000
|
$4,410.000
|
$2,050.000
|
$2,400.000
|
$3,700.000
|
|
|
SET (TY II) (30 IN) (CMP) (3: 1) (C)
|
EA
|
60.000
|
$1,200.000
|
$1,950.000
|
$1,400.000
|
$4,300.000
|
|
|
SET (TY II) (36 IN) (CMP) (3: 1) (C)
|
EA
|
10.000
|
$2,500.000
|
$2,100.000
|
$1,400.000
|
$4,600.000
|
|
|
SET (TY II) (48 IN) (CMP) (3: 1) (C)
|
EA
|
18.000
|
$6,084.000
|
$4,350.000
|
$1,600.000
|
$7,200.000
|
|
|
REMOV STR (BOX CULVERT)
|
EA
|
4.000
|
$17,025.000
|
$8,900.000
|
$17,000.000
|
$10,900.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
116.000
|
$7,750.760
|
$185.000
|
$1,500.000
|
$411.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
58.000
|
$1,200.000
|
$185.000
|
$1,500.000
|
$825.000
|
|
|
REMOV STR (PIPE)
|
LF
|
3,096.000
|
$23.970
|
$25.000
|
$34.500
|
$18.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,200,000.000
|
$2,000,000.000
|
$2,000,000.000
|
$2,426,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
18.000
|
$9,286.980
|
$25,000.000
|
$7,100.000
|
$15,000.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
4,050.000
|
$6.000
|
$3.000
|
$4.600
|
$9.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
4,050.000
|
$2.000
|
$1.000
|
$1.110
|
$2.250
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
18.000
|
$2,800.000
|
$6,000.000
|
$3,800.000
|
$6,900.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
8,490.000
|
$35.000
|
$80.000
|
$100.000
|
$108.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
55,560.000
|
$6.000
|
$3.500
|
$2.000
|
$5.150
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
8,490.000
|
$10.000
|
$3.500
|
$6.000
|
$14.200
|
|
|
DRIVEWAYS (CONC)
|
SY
|
286.000
|
$91.000
|
$110.000
|
$91.000
|
$136.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,418.000
|
$90.000
|
$40.000
|
$90.000
|
$60.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
10,768.000
|
$21.000
|
$30.000
|
$45.000
|
$41.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
LF
|
452.000
|
$25.000
|
$40.000
|
$45.000
|
$41.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
18.000
|
$3,000.000
|
$3,000.000
|
$4,725.000
|
$4,800.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
12.000
|
$8,000.000
|
$11,500.000
|
$7,500.000
|
$9,200.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
44.000
|
$1,900.000
|
$2,500.000
|
$2,500.000
|
$453.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
14.000
|
$850.000
|
$1,000.000
|
$1,000.000
|
$246.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
27.000
|
$800.000
|
$800.000
|
$840.000
|
$720.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
13.000
|
$75.000
|
$100.000
|
$68.500
|
$110.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 2(WC)GND(BR)
|
EA
|
27.000
|
$60.000
|
$50.000
|
$157.500
|
$69.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
70.000
|
$160.000
|
$40.000
|
$157.500
|
$83.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
44.000
|
$20.000
|
$30.000
|
$48.000
|
$16.500
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
72,280.000
|
$1.000
|
$0.920
|
$1.000
|
$1.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
54,210.000
|
$1.000
|
$1.000
|
$2.000
|
$2.790
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
71,876.000
|
$0.450
|
$0.420
|
$0.400
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
7,748.000
|
$0.350
|
$0.420
|
$0.400
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
24,776.000
|
$0.350
|
$0.420
|
$0.400
|
$0.500
|
|
RE PM W/RET REQ TY II (W) 4" (SLD)
|
LF
|
71,876.000
|
$0.250
|
$0.130
|
$0.150
|
$0.140
|
|
RE PM W/RET REQ TY II (Y) 4" (BRK)
|
LF
|
7,748.500
|
$1.000
|
$0.130
|
$0.150
|
$0.140
|
|
RE PM W/RET REQ TY II (Y) 4" (SLD)
|
LF
|
24,776.000
|
$0.400
|
$0.130
|
$0.150
|
$0.140
|
|
PLOWABLE REFL PAV MRKR TY I-C
|
EA
|
454.000
|
$65.000
|
$35.000
|
$18.800
|
$19.000
|
|
PLOWABLE REFL PAV MRKR TY II-A-A
|
EA
|
903.000
|
$65.000
|
$35.000
|
$18.500
|
$19.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
72,280.000
|
$0.500
|
$0.780
|
$0.800
|
$0.800
|
|
|
FILTER FABRIC (TY 2)
|
SY
|
943.700
|
$3.000
|
$43.910
|
$45.000
|
$88.000
|
|
|
EMULSION
|
GAL
|
978,066.100
|
$2.500
|
$2.750
|
$2.800
|
$3.000
|
|
|
CEMENT
|
TON
|
950.897
|
$200.000
|
$165.000
|
$205.000
|
$229.000
|
|
|
EMUL TRTMNT(MX EXST MTRL & NEW BASE)10"
|
SY
|
181,123.000
|
$4.000
|
$3.670
|
$5.850
|
$2.750
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$14,500.000
|
$15,000.000
|
$6,900.000
|
$25,370.000
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$17,000.000
|
$62,000.000
|
$40,000.000
|
$140,000.000
|
|
Totals: |
$20,544,702.410
|
$20,059,666.122
|
$21,503,376.790
|
$24,354,201.333
|