Job Info for 0374-08-021

County: CULBERSON Highway: US 62 Date: 08/07/2018 (6 years ago) Engineer's Estimate: $1,332,176 Control Number: 0374-08-021
Project: C 374-8-21 District: EL PASO Time: 100 WORKING DAYS Type: COUNTERMEASURE FOR BRIDGE SCOUR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,332,176.00
DAN WILLIAMS COMPANY   $1,434,496.00 1
7.68% | $102,320.00
DCI CONTRACTING, INC.   $1,468,164.93 2
10.21% | $135,988.93
2.35% | $33,668.93
EARTH BUILDERS, L.P.   $1,527,588.00 3
14.67% | $195,412.00
6.49% | $93,092.00
4.05% | $59,423.07
LESNA CONSTRUCTION, INC.   $1,572,789.00 4
18.06% | $240,613.00
9.64% | $138,293.00
2.96% | $45,201.00
GILVIN-TERRILL, LTD.   $1,806,643.90 5
35.62% | $474,467.90
25.94% | $372,147.90
14.87% | $233,854.90

Bid Items

Items: 20, 0 filtered
CULBERSON US 62  |  EL PASO  |  0374-08-021  |  08/07/2018  |  $1,332,176  |  C 374-8-21  |  COUNTERMEASURE FOR BRIDGE SCOUR  |  100 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate DAN WILLIAMS COMPANY DCI CONTRACTING, INC. EARTH BUILDERS, L.P. LESNA CONSTRUCTION, INC. GILVIN-TERRILL, LTD.
100 6002 PREPARING ROW STA 6.000 $5,550.000 $23,000.000 $4,166.680 $10,000.000 $1,250.000 $2,000.000
401 6001 FLOWABLE BACKFILL CY 4.000 $500.000 $1,000.000 $2,093.750 $2,000.000 $400.000 $500.000
407 6019 SHEET PILING (PZC - 18) SF 19,077.000 $40.000 $38.000 $42.390 $40.000 $62.000 $58.700
432 6002 RIPRAP (CONC)(5 IN) CY 57.000 $600.000 $900.000 $1,085.550 $1,000.000 $550.000 $1,500.000
432 6046 RIPRAP (MOW STRIP)(5 IN) CY 22.000 $590.000 $900.000 $1,193.200 $800.000 $650.000 $1,500.000
459 6007 GABION MATTRESSES (GALV)(12 IN) SY 582.000 $100.000 $150.000 $135.350 $200.000 $90.000 $150.000
459 6008 GABION MATTRESSES (GALV)(18 IN) SY 582.000 $175.000 $180.000 $182.380 $300.000 $130.000 $175.000
459 6009 GABIONS (3' X 3')(GALV) CY 98.000 $310.000 $300.000 $427.330 $500.000 $190.000 $300.000
500 6001 MOBILIZATION LS 1.000 $121,100.000 $140,000.000 $200,000.000 $150,000.000 $95,000.000 $180,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $20,000.000 $10,000.000 $5,000.000 $10,000.000 $6,500.000 $11,130.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 311.000 $60.000 $40.000 $34.990 $50.000 $30.000 $25.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 311.000 $20.000 $10.000 $8.700 $10.000 $10.000 $5.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 794.000 $3.000 $4.000 $4.840 $5.000 $4.000 $5.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 794.000 $1.000 $2.000 $1.450 $2.000 $1.000 $2.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 794.000 $10.000 $9.000 $7.380 $10.000 $5.000 $5.000
540 6024 MTL W-BEAM GD FEN (TIM POST)(TY IV) LF 175.000 $30.000 $50.000 $50.000 $30.000 $35.000 $30.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 1.000 $2,560.000 $1,000.000 $2,500.000 $5,000.000 $2,500.000 $3,500.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 1.000 $260.000 $4,500.000 $500.000 $500.000 $700.000 $500.000
6158 6001 TMSP RADAR SPEED CONTROL MONITOR EA 2.000 $9,810.000 $15,000.000 $6,250.000 $10,000.000 $10,000.000 $5,000.000
6185 6002 TMA (STATIONARY) DAY 38.000 $300.000 $350.000 $986.850 $500.000 $300.000 $1,632.000
Totals: $1,332,176.00 $1,434,496.00 $1,468,164.93 $1,527,588.00 $1,572,789.00 $1,806,643.90