Bid Cobra

CROSBY CR (0905-21-004)

Items: 39

County: CROSBY
Length: N/A
Highway: CR
District: LUBBOCK
Control Number: 0905-21-004
DBE Goal: N/A
Project: BR 2019(810)
Guaranty: N/A
Time: 213 WORKING DAYS
Engineer's Estimate: $1,362,930.50
Date: 08/04/2021 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$1,362,930.50
$1,322,304.00
Over/Under Est: -2.98% -$40,626.50
Over/Under Est: 3.45% $47,004.91
Amt Left: 6.63% $87,631.41
Over/Under Est: 5.83% $79,473.42
Amt Left: 9.08% $120,099.92
Delta: -2.30% -$32,468.51

Bid Items & Bid Tabulations

39 Total 0 of 39
CROSBY  |  CR  |  LUBBOCK  |  0905-21-004  |  08/04/2021  |  $1,362,930.50  |  BR 2019(810)  |  BRIDGE REPL  |  213 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EARTH BUILDERS, L.P.
INTEGRITY SERVICES, LLC
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
PREPARING ROW
STA 14.000 $1,150.000 $2,500.000 $1,000.000 $912.760
EXCAVATION (ROADWAY)
CY 625.000 $20.000 $20.000 $20.000 $38.370
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 750.000 $12.000 $30.000 $16.000 $61.360
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 3,240.000 $0.750 $1.000 $1.008 $1.520
PROOF ROLLING
HR 20.000 $110.000 $100.000 $130.000 $258.240
FL BS (CMP IN PL)(TY D GR 4)(8")
SY 3,600.000 $15.000 $25.000 $19.900 $25.440
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 423.000 $10.000 $10.000 $12.000 $15.300
CEM STABIL BKFL
CY 44.000 $250.000 $300.000 $230.000 $402.410
TEMPORARY SPL SHORING (COFFERDAM)
SF 2,688.000 $20.000 $8.000 $30.000 $35.960
APPROACH SLAB
CY 94.000 $650.000 $800.000 $686.960 $825.110
RAIL (TY T223)
LF 370.000 $125.000 $150.000 $130.000 $216.490
GABION MATTRESSES (GALV)(9 IN)
SY 167.000 $200.000 $150.000 $180.000 $255.380
GABIONS (3' X 3')(GALV)
CY 227.000 $250.000 $250.000 $200.000 $349.400
CONC BOX CULV (10 FT X 5 FT)
LF 165.000 $1,200.000 $1,150.000 $1,093.890 $965.520
CONC BOX CULV (10 FT X 10 FT)
LF 143.000 $2,000.000 $1,400.000 $1,701.870 $1,110.970
WINGWALL (PW - 1) (HW=11 FT)
EA 2.000 $60,000.000 $70,000.000 $51,000.000 $45,392.600
WINGWALL (PW - 1) (HW=6 FT)
EA 2.000 $16,000.000 $26,000.000 $35,000.000 $36,084.500
CLEAN EXIST CULVERTS
EA 2.000 $2,800.000 $2,500.000 $2,500.000 $2,538.820
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $22,500.000 $25,000.000 $20,160.000 $32,951.360
MOBILIZATION
LS 1.000 $81,000.000 $145,000.000 $161,744.390 $144,200.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $5,500.000 $1,500.000 $1,500.000 $539.310
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 470.000 $60.000 $50.000 $75.000 $70.990
ROCK FILTER DAMS (REMOVE)
LF 470.000 $15.000 $10.000 $15.000 $15.630
TEMP SEDMT CONT FENCE (INSTALL)
LF 720.000 $3.000 $5.000 $3.640 $5.980
TEMP SEDMT CONT FENCE (REMOVE)
LF 720.000 $0.900 $1.000 $1.680 $2.740
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 160.000 $6.000 $10.000 $6.720 $15.180
BIODEG EROSN CONT LOGS (REMOVE)
LF 160.000 $2.000 $1.000 $1.120 $9.620
MTL W-BEAM GD FEN (STEEL POST)
LF 487.500 $35.000 $40.000 $33.600 $35.720
MTL BEAM GD FEN TRANS (TL2)
EA 8.000 $1,400.000 $1,500.000 $1,512.000 $1,698.550
SHORT RADIUS
LF 14.000 $40.000 $50.000 $67.200 $249.170
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,500.000 $1,250.000 $1,400.000 $3,938.390
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $3,150.000 $2,500.000 $3,164.000 $3,098.340
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $800.000 $1,000.000 $1,120.000 $928.550
REMOVE SM RD SN SUP&AM
EA 4.000 $200.000 $100.000 $112.000 $368.550
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 12.000 $50.000 $50.000 $16.800 $139.180
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 36.000 $50.000 $50.000 $22.400 $61.730
LITTER REMOVAL
CYC 4.000 $5,000.000 $250.000 $1,500.000 $50.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $200.000 $250.000 $350.000 $528.220
TMA (STATIONARY)
DAY 213.000 $200.000 $50.000 $350.000 $153.760
Totals: $1,362,930.500 $1,322,304.000 $1,409,935.410 $1,442,403.920