CROCKETT US 190 (2279-02-023)

Items: 77

County: CROCKETT
Length: 0.0000 MILES
Highway: US 190
District: SAN ANGELO
Control Number: 2279-02-023
DBE Goal: 6.5%
Project: BR 2B24(487)
Guaranty: $100,000.00
Time: 298 WORKING DAYS
Engineer's Estimate: $6,809,082.18
Date: 09/05/2024 (1 year ago)
Contract Number: 9243029
Type: BRIDGE REPLACEMENT
Project ID: A00188549
Project Description: REPLACEMENT OF BRIDGE AT LIVE OAK DRAW
Mail/Deliver Bids To: N/A
JESUS GARCIA9
RANDY BAIZA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$6,809,082.18
1
$5,673,708.11
Over/Under Est: -16.67% -$1,135,374.07
$6,571,416.74
Over/Under Est: -3.49% -$237,665.44
Amt Left: 15.82% $897,708.63
$6,771,299.75
Over/Under Est: -0.55% -$37,782.43
Amt Left: 19.35% $1,097,591.64
Delta: -3.04% -$199,883.01
Over/Under Est: 13.87% $944,448.56
Amt Left: 36.66% $2,079,822.63
Delta: -14.51% -$982,230.99
$9,091,292.00
Over/Under Est: 33.52% $2,282,209.82
Amt Left: 60.24% $3,417,583.89
Delta: -17.25% -$1,337,761.26
Subcontractor Percentage Amount
KINGZ INDUSTRIAL LLC 2.67% $151,488.01
DIIBS SPECIALISTS, LLC 1.43% $81,134.03
BAG REINFORCING LLC 0.96% $54,467.60
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 0.91% $51,630.74
Total: 5.97% $338,720.38

Bid Items & Bid Tabulations

77 Total 0 of 77
CROCKETT  |  US 190  |  SAN ANGELO  |  2279-02-023  |  09/05/2024  |  $6,809,082.18  |  BR 2B24(487)  |  BRIDGE REPL  |  298 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RELMCO, INC.
REECE ALBERT, INC.
C. E. BARKER, LTD.
PROJECT ALLIED RESOURCES, LLC
FNF CONSTRUCTION, INC.
PREPARING ROW
STA 15.700 $2,500.000 $11,500.000 $15,211.910 $40,000.000 $4,280.000 $6,000.000
PREP ROW (TREE REMOVE) (0"-12" DIA)
EA 267.000 $500.000 $300.000 $117.430 $59.730 $18.200 $300.000
PREP ROW (TREE REMOVE) (12"-24" DIA)
EA 46.000 $1,500.000 $800.000 $33.040 $89.590 $48.700 $750.000
PREP ROW (TREE REMOVE) (24"-36" DIA)
EA 10.000 $2,500.000 $1,000.000 $165.780 $244.880 $207.000 $1,200.000
PREP ROW (TREE REMOVE) (36"-48" DIA)
EA 2.000 $5,000.000 $2,500.000 $863.450 $519.620 $487.000 $1,500.000
REMOV CONC (RIPRAP)
SY 782.000 $45.000 $25.000 $10.830 $35.510 $35.300 $70.000
RMV (11"-15") TRT/UNTRT BASE & ASPH PAV
SY 4,235.000 $12.000 $12.000 $9.340 $30.100 $18.100 $17.000
EXCAV (ROADWAY)
CY 7,783.000 $35.000 $15.000 $6.110 $35.840 $32.300 $1.500
EMBANK (FNL)(DC)(TY B)
CY 13,877.000 $20.000 $25.000 $19.950 $50.170 $40.600 $2.000
DRILL SEED (PERM_RURAL_CLAY)
SY 3,978.000 $1.000 $1.320 $1.660 $3.340 $1.030 $2.000
DRILL SEED (TEMP_WARM_COOL)
SY 3,978.000 $1.000 $1.340 $1.690 $0.560 $0.910 $2.000
SOIL RET BLKT(SL_MOD_CLAY_LONG)
SY 1,750.000 $3.000 $4.390 $5.510 $5.200 $3.620 $6.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 2,096.000 $100.000 $100.000 $115.340 $66.550 $125.000 $120.000
PRIME COAT (MC-30)
GAL 1,077.000 $9.000 $8.000 $8.340 $17.920 $25.400 $18.000
ASPH (AC-20-5TR)
GAL 4,366.000 $7.000 $7.000 $6.790 $27.470 $8.400 $8.000
AGGR (TY-PB, GR-3)(SAC-B)
CY 49.000 $210.000 $250.000 $638.950 $238.910 $392.000 $530.000
AGGR (TY-PB, GR-4)(SAC-B)
CY 42.000 $230.000 $250.000 $745.440 $238.910 $389.000 $530.000
CEM STABIL BKFL
CY 126.000 $405.000 $245.000 $497.270 $226.960 $837.000 $650.000
TEMPORARY SPL SHORING
SF 132.000 $110.000 $100.000 $111.750 $46.590 $46.600 $300.000
DRILL SHAFT (36 IN)
LF 1,070.000 $525.000 $625.000 $729.280 $677.110 $789.000 $1,088.000
CL C CONC (ABUT)
CY 57.200 $1,815.000 $1,650.000 $2,258.080 $1,931.290 $2,380.000 $4,000.000
CL C CONC (CAP)
CY 85.700 $2,200.000 $1,545.000 $2,280.390 $2,035.740 $2,890.000 $4,500.000
CL C CONC (COLUMN)
CY 65.600 $2,200.000 $1,425.000 $2,003.030 $2,114.360 $3,250.000 $3,500.000
REINF CONC SLAB
SF 19,741.000 $40.000 $32.000 $49.210 $28.460 $43.300 $70.000
APPROACH SLAB
CY 72.200 $1,100.000 $950.000 $1,610.850 $974.690 $1,300.000 $2,000.000
PRESTR CONC GIRDER (TX40)
LF 2,704.000 $340.000 $205.000 $281.550 $229.460 $284.000 $400.000
RIPRAP (MOW STRIP)(4 IN)
CY 92.000 $750.000 $772.100 $1,015.410 $811.950 $1,240.000 $1,300.000
RIPRAP (STONE COMMON)(DRY)(8 IN)
CY 2,836.000 $275.000 $195.000 $171.210 $120.650 $223.000 $260.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 958.000 $320.000 $205.000 $275.090 $259.080 $250.000 $270.000
RAIL (TY SSTR)
LF 880.000 $150.000 $125.000 $194.560 $179.610 $284.000 $150.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 141.000 $305.000 $235.000 $393.130 $228.160 $402.000 $400.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $183,750.000 $250,000.000 $187,462.150 $157,977.600 $369,000.000 $500,000.000
MOBILIZATION
LS 1.000 $603,552.930 $550,000.000 $651,023.410 $670,000.000 $873,000.000 $909,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $10,000.000 $5,000.000 $2,848.400 $3,414.970 $5,040.000 $20,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $15,000.000 $6,175.350 $11,945.380 $12,200.000 $15,000.000
TMA (MOBILE OPERATION)
HR 40.000 $100.000 $90.000 $110.520 $83.620 $507.000 $400.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $35.000 $66.120 $83.040 $37.580 $63.000 $15.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $15.000 $22.040 $27.690 $14.360 $18.200 $5.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 2,635.000 $8.000 $7.000 $8.800 $12.040 $10.500 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,635.000 $2.500 $2.409 $3.030 $3.720 $3.020 $3.500
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 10.000 $5,000.000 $3,000.000 $2,624.870 $5,023.030 $5,550.000 $5,000.000
PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL)
LF 480.000 $80.000 $45.000 $45.840 $88.530 $34.300 $80.000
PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 480.000 $25.000 $25.000 $3.880 $27.870 $13.400 $10.000
PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 480.000 $40.000 $35.000 $54.790 $33.450 $11.700 $10.000
DRIVEWAYS (SURF TREAT)
SY 102.000 $60.000 $100.000 $148.560 $61.920 $174.000 $75.000
MTL W-BEAM GD FEN (STEEL POST)
LF 1,725.000 $50.000 $35.200 $44.210 $34.820 $35.500 $40.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $3,000.000 $2,640.000 $5,249.740 $3,135.660 $3,190.000 $4,000.000
REMOVE METAL BEAM GUARD FENCE
LF 400.000 $3.000 $2.750 $4.140 $5.970 $6.100 $10.000
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $150.000 $275.000 $690.750 $328.500 $335.000 $500.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $250.000 $275.000 $690.760 $328.500 $335.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $4,000.000 $3,410.000 $4,835.280 $4,300.340 $4,380.000 $5,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $300.000 $275.000 $690.750 $388.220 $395.000 $500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,000.000 $950.000 $1,516.780 $2,299.480 $2,340.000 $750.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,500.000 $330.000 $1,516.780 $1,702.220 $1,730.000 $750.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $15,000.000 $7,700.000 $10,841.960 $10,601.520 $10,800.000 $15,000.000
WIRE FENCE (TY C)
LF 1,250.000 $25.000 $35.750 $18.070 $38.820 $39.500 $40.000
GATE (TY 1)
EA 2.000 $5,000.000 $3,206.500 $5,180.660 $3,482.080 $3,550.000 $4,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $1,150.000 $385.000 $2,210.410 $1,791.810 $2,510.000 $2,000.000
REMOVE SM RD SN SUP&AM
EA 2.000 $200.000 $137.500 $224.320 $358.360 $998.000 $1,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
EA 10.000 $35.000 $25.300 $24.810 $59.730 $55.000 $300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 20.000 $35.000 $27.500 $31.710 $71.670 $59.000 $400.000
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 212.000 $7.500 $4.400 $5.530 $7.170 $8.100 $15.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 7,120.000 $1.500 $1.595 $2.000 $2.090 $1.820 $5.000
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 24.000 $15.000 $13.200 $16.580 $11.950 $9.600 $20.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 8,400.000 $1.500 $1.595 $2.000 $2.090 $1.820 $1.500
RE PM TY II (W) 6" (SLD)
LF 1,280.000 $0.450 $1.320 $1.660 $0.900 $2.980 $0.900
RE PM TY II (Y) 6" (BRK)
LF 1,130.000 $0.450 $1.430 $1.800 $0.900 $3.040 $1.000
RE PM TY II (Y) 6" (SLD)
LF 2,630.000 $0.450 $1.320 $1.660 $0.900 $2.980 $0.900
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 3,580.000 $0.750 $3.130 $3.940 $2.990 $4.010 $2.000
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 3,198.000 $0.750 $3.130 $3.940 $2.990 $4.010 $2.000
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 1,575.000 $0.750 $3.240 $4.080 $2.990 $4.060 $2.000
PRFB RUMBLE STRIP (BLK)(1 )(CENTERLINE)
LF 575.000 $10.000 $7.700 $9.670 $11.950 $7.700 $12.000
REFL PAV MRKR TY II-A-A
EA 119.000 $10.000 $9.900 $12.430 $8.960 $10.100 $8.000
ELIM EXT PM & MRKS (4")
LF 14,550.000 $2.000 $0.380 $0.480 $1.190 $0.830 $1.700
ELIM EXT PM & MRKS (24")
LF 246.000 $10.000 $5.770 $7.250 $4.780 $2.640 $8.000
PAV SURF PREP FOR MRK (6")
LF 5,040.000 $1.000 $0.050 $0.070 $0.300 $0.750 $0.750
POST AND CABLE FENCE (REMOVAL)
LF 736.000 $10.000 $10.000 $2.230 $5.970 $5.900 $10.000
Totals: $6,809,082.180 $5,673,708.115 $6,571,416.764 $6,771,299.780 $7,753,530.740 $9,091,292.000