County: CROCKETT Highway: IH 10 Date: 08/04/2022 (2 years ago) Engineer's Estimate: $1,421,600 Control Number: 0140-13-025
Project: STP 2022(878)HES District: SAN ANGELO Time: 147 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
HCS
Pay Estimate
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,421,600.00
SCR CIVIL CONSTRUCTION, LLC   $1,714,801.50 1
20.62% | $293,201.50
HJC FARMS, INC.   $1,842,990.00 2
29.64% | $421,390.00
7.48% | $128,188.50
MASSANA CONSTRUCTION INC.   $1,846,669.97 3
29.9% | $425,069.97
7.69% | $131,868.47
0.20% | $3,679.97
GRATIOT CONSTRUCTION, LTD.   $1,869,177.00 4
31.48% | $447,577.00
9% | $154,375.50
1.22% | $22,507.03

Bid Items

Items: 17, 0 filtered
CROCKETT IH 10  |  SAN ANGELO  |  0140-13-025  |  08/04/2022  |  $1,421,600  |  STP 2022(878)HES  |  HAZARD ELIM & SAFETY  |  147 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SCR CIVIL CONSTRUCTION, LLC HJC FARMS, INC. MASSANA CONSTRUCTION INC. GRATIOT CONSTRUCTION, LTD.
150 6002 BLADING HR 85.000 $100.000 $250.000 $150.000 $81.000 $120.000
164 6036 DRILL SEEDING (PERM) (RURAL) (CLAY) AC 16.000 $800.000 $3,500.000 $750.000 $2,000.000 $1,400.000
164 6042 DRILL SEEDING (TEMP) (WARM) AC 8.000 $550.000 $1,000.000 $750.000 $2,000.000 $1,000.000
164 6044 DRILL SEEDING (TEMP) (COOL) AC 8.000 $580.000 $1,000.000 $750.000 $2,000.000 $800.000
330 6002 LRA PAV TY-I GR-A TON 49.000 $270.000 $560.000 $175.000 $175.000 $265.000
432 6006 RIPRAP (CONC)(CL B) CY 1,656.000 $450.000 $538.000 $550.000 $560.000 $625.000
500 6001 MOBILIZATION LS 1.000 $120,000.000 $94,000.000 $175,000.000 $168,085.970 $185,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $10,000.000 $7,500.000 $5,000.000 $20,000.000 $12,000.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 546.000 $40.000 $38.000 $27.000 $45.000 $5.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 546.000 $15.000 $11.000 $8.000 $9.000 $1.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 600.000 $9.500 $9.000 $6.000 $8.000 $5.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 600.000 $1.500 $1.250 $1.000 $1.000 $1.000
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 32,670.000 $10.000 $13.850 $16.500 $14.000 $13.000
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 14.000 $1,750.000 $2,500.000 $5,000.000 $4,000.000 $5,900.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 2.000 $750.000 $2,400.000 $1,000.000 $950.000 $3.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 300.000 $150.000 $50.000 $100.000 $17.000 $20.000
6185 6002 TMA (STATIONARY) DAY 150.000 $190.000 $210.000 $150.000 $110.000 $60.000
Totals: $1,421,600.00 $1,714,801.50 $1,842,990.00 $1,846,669.97 $1,869,177.00