Bid Cobra

CORYELL FM 217 (0833-01-009)

Items: 22

County: CORYELL
Length: N/A
Highway: FM 217
District: WACO
Control Number: 0833-01-009
DBE Goal: N/A
Project: F 2024(015)
Guaranty: N/A
Time: 60 WORKING DAYS
Engineer's Estimate: $8,721,664.38
Date: 09/06/2023 (2 years ago)
Contract Number: N/A
Type: SEAL COAT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$8,721,664.38
$7,582,811.52
Over/Under Est: -13.06% -$1,138,852.86
$8,357,678.91
Over/Under Est: -4.17% -$363,985.47
Amt Left: 10.22% $774,867.39
Over/Under Est: -1.84% -$160,334.44
Amt Left: 12.9% $978,518.42
Delta: -2.44% -$203,651.03
Over/Under Est: 1.01% $88,078.99
Amt Left: 16.18% $1,226,931.85
Delta: -2.90% -$248,413.43
Over/Under Est: 2.78% $242,563.95
Amt Left: 18.22% $1,381,416.81
Delta: -1.75% -$154,484.96
Subcontractor Percentage Amount
CENTERLINE TECHNOLOGIES, LLC 6.63% $502,302.18
BARRICADES PLUS, LLC 1.71% $129,553.05
RED SIXTEEN CONSTRUCTION, INC 0.00% $0.00
Total: 8.34% $631,855.23

Bid Items & Bid Tabulations

22 Total 0 of 22
CORYELL  |  FM 217  |  WACO  |  0833-01-009  |  09/06/2023  |  $8,721,664.38  |  F 2024(015)  |  SEAL COAT  |  60 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BRANNAN PAVING CO., LTD.
CK NEWBERRY, LLC
RONALD R. WAGNER & CO., LP
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
D. I. J. CONSTRUCTION, INC.
ASPH (TIER II)
GAL 1,011,693.000 $4.000 $3.330 $4.000 $4.175 $3.750 $4.150
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 18,749.000 $120.000 $115.270 $145.000 $139.130 $125.000 $155.000
MOBILIZATION
LS 1.000 $690,000.000 $1,299,000.000 $825,000.000 $1,118,598.300 $1,850,000.000 $875,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $8,800.000 $50,000.000 $5,000.000 $0.010 $50,000.000 $50,000.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 1,393,239.000 $0.500 $0.160 $0.190 $0.200 $0.160 $0.210
WK ZN PAV MRK NON-REMOV (W)8"(LNDP)
LF 115.000 $0.680 $1.000 $1.500 $1.000 $1.000 $2.200
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 1,400.000 $0.620 $0.300 $0.750 $1.000 $0.300 $1.100
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 3,514.000 $5.250 $5.000 $3.000 $3.000 $5.000 $3.300
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 126,379.000 $0.500 $0.170 $0.200 $0.250 $0.170 $0.210
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 899,979.000 $0.500 $0.170 $0.200 $0.200 $0.170 $0.200
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 155,707.000 $1.500 $0.150 $1.000 $0.010 $0.750 $0.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 3.000 $290.000 $250.000 $300.000 $225.000 $250.000 $385.000
PREFAB PAV MRK TY C (W) (WORD)
EA 23.000 $315.000 $300.000 $300.000 $275.000 $300.000 $430.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 6.000 $725.000 $750.000 $700.000 $655.000 $750.000 $850.000
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 8.000 $70.000 $25.000 $30.000 $100.000 $25.000 $55.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 43.000 $60.000 $35.000 $40.000 $100.000 $35.000 $55.000
REFL PAV MRKR TY I-C
EA 55.000 $7.450 $4.000 $5.000 $5.000 $4.000 $5.500
REFL PAV MRKR TY II-A-A
EA 18,621.000 $3.230 $3.750 $3.000 $4.500 $3.750 $4.500
CLEANING / SWEEPING (AGGREGATE REMOVAL)
MI 152.327 $300.000 $100.000 $200.000 $0.010 $0.010 $300.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 192.000 $175.000 $60.000 $10.000 $0.010 $10.000 $165.000
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 320.000 $15.000 $10.000 $20.000 $20.000 $10.000 $13.200
TMA (MOBILE OPERATION)
HR 960.000 $80.000 $1.000 $1.000 $0.010 $1.000 $10.000
Totals: $8,721,664.380 $7,582,811.520 $8,357,678.910 $8,561,329.948 $8,809,743.373 $8,964,228.330