CORYELL IH 14 (0231-02-066)

Items: 65

County: CORYELL
Length: N/A
Highway: IH 14
District: WACO
Control Number: 0231-02-066
DBE Goal: N/A
Project: C 231-2-66
Guaranty: N/A
Time: 147 WORKING DAYS
Engineer's Estimate: $10,266,461.20
Date: 02/01/2023 (3 years ago)
Contract Number: N/A
Type: MILL AND INLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$10,266,461.20
$9,294,253.44
Over/Under Est: -9.47% -$972,207.76
Over/Under Est: -8.56% -$879,102.93
Amt Left: 1% $93,104.83
Over/Under Est: -3.72% -$381,611.68
Amt Left: 6.35% $590,596.08
Delta: -5.30% -$497,491.25

Bid Items & Bid Tabulations

65 Total 0 of 65
CORYELL  |  IH 14  |  WACO  |  0231-02-066  |  02/01/2023  |  $10,266,461.20  |  C 231-2-66  |  MILL AND INLAY  |  147 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
BIG CREEK CONSTRUCTION, LTD.
LONE STAR PAVING COMPANY
REMOVING CONCRETE(MOW STRIP)
LF 3,579.000 $10.000 $10.000 $15.000 $12.000
BACKFILL (TY B)
STA 290.300 $220.000 $85.400 $225.000 $410.000
BLADING
STA 290.300 $270.000 $51.000 $100.000 $72.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 34,561.000 $0.500 $0.500 $0.370 $1.650
VEGETATIVE WATERING
MG 280.620 $20.000 $46.000 $25.000 $11.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 665.000 $50.000 $78.000 $150.000 $200.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 18,096.000 $60.000 $50.000 $65.000 $55.000
PLANE ASPH CONC PAV(MICRO)(0"-3")
SY 361,909.000 $3.000 $3.100 $2.000 $1.900
PAV JT UNDERSEAL (24")
LF 320.000 $20.000 $29.380 $40.000 $29.400
RIPRAP (MOW STRIP)(4 IN)
CY 453.000 $525.000 $575.000 $650.000 $650.000
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 320.000 $60.000 $31.230 $35.000 $31.250
CLEANING AND SEALING JOINTS (CL 3)
LF 1,371.000 $45.000 $31.230 $35.000 $31.250
CLEANING EXISTING JOINTS
LF 1,271.000 $20.000 $9.500 $10.000 $9.500
HEADER TYPE EXPANSION JOINT
CF 178.000 $400.000 $391.730 $400.000 $391.750
JOINT SEALANT
LF 1,620.000 $20.000 $12.000 $15.000 $12.000
MOBILIZATION
LS 1.000 $785,000.000 $579,000.000 $622,000.000 $470,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $10,000.000 $1,220.000 $7,500.000 $30,000.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 75,085.000 $0.200 $0.160 $0.150 $0.220
MTL W-BEAM GD FEN (STEEL POST)
LF 4,925.000 $40.000 $28.600 $30.000 $28.600
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 11.000 $2,800.000 $2,713.390 $2,500.000 $2,714.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 24.000 $1,400.000 $1,366.380 $1,000.000 $1,367.000
REMOVE METAL BEAM GUARD FENCE
LF 2,325.000 $2.750 $3.000 $3.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $400.000 $274.900 $250.000 $275.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 3.000 $200.000 $91.630 $250.000 $91.650
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 10.000 $300.000 $183.320 $250.000 $183.350
GUARDRAIL END TREATMENT (INSTALL)
EA 30.000 $3,500.000 $3,342.400 $3,000.000 $3,345.000
GUARDRAIL END TREATMENT (REMOVE)
EA 16.000 $290.000 $274.890 $250.000 $275.000
REPLACE EXISTING ALUMINUM SIGNS(TY G)
SF 901.200 $30.000 $41.510 $50.000 $47.500
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 4,111.800 $45.000 $34.160 $50.000 $53.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 29.000 $720.000 $700.000 $1,000.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $850.000 $850.000 $1,200.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 3.000 $1,250.000 $1,000.000 $1,500.000 $2,000.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 23.000 $450.000 $550.000 $600.000 $750.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 2.000 $2,400.000 $2,814.240 $5,000.000 $3,400.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 4.000 $2,800.000 $2,880.240 $5,000.000 $3,500.000
REMOVE SM RD SN SUP&AM
EA 60.000 $140.000 $200.000 $150.000 $250.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND
EA 117.000 $55.000 $39.000 $65.000 $39.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
EA 94.000 $30.000 $41.480 $26.000 $41.500
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
EA 25.000 $30.000 $13.670 $25.000 $13.700
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 44,520.000 $0.400 $1.650 $0.500 $0.250
WK ZN PAV MRK NON-REMOV (W)6"(DOT)
LF 138.000 $0.450 $0.650 $3.000 $0.600
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 116,066.000 $0.300 $0.600 $0.400 $0.250
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 27,904.000 $0.500 $0.900 $0.750 $0.400
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 8,662.000 $1.900 $1.500 $4.000 $1.600
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 93,502.000 $0.400 $0.600 $0.400 $0.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 23,304.000 $1.700 $0.960 $1.250 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 4,675.000 $1.500 $0.960 $1.250 $1.500
WK ZN PAV MRK NON-REMOV (W)12"(DOT)
LF 1,317.000 $1.000 $1.500 $4.000 $1.000
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 69.000 $1.500 $2.000 $1.000 $1.060
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 9,900.000 $1.500 $1.000 $1.000 $1.600
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 4,331.000 $3.750 $2.100 $4.000 $6.710
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 22,260.000 $0.700 $0.750 $0.800 $0.700
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 46,779.000 $0.700 $0.710 $0.700 $0.610
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 46,751.000 $0.700 $0.710 $0.700 $0.610
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 1,317.000 $6.000 $1.800 $4.000 $2.500
PREFAB PAV MRK TY C (W) (ARROW)
EA 7.000 $220.000 $300.000 $200.000 $304.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 2.000 $400.000 $435.000 $300.000 $437.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 30.000 $250.000 $300.000 $70.000 $403.000
PREFAB PAV MRK TY C (W) (WORD)
EA 7.000 $260.000 $400.000 $300.000 $340.000
REFL PAV MRKR TY II-C-R
EA 1,881.000 $5.000 $6.750 $4.000 $7.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 35,359.000 $150.000 $135.000 $135.000 $155.000
BONDING COURSE
GAL 43,430.000 $3.000 $5.350 $4.500 $3.150
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $7,500.000 $10,800.000 $10,000.000 $7,500.000
TMA (STATIONARY)
DAY 189.000 $250.000 $280.000 $225.000 $200.000
TMA (MOBILE OPERATION)
HR 700.000 $70.000 $20.000 $30.000 $34.000
Totals: $10,266,461.200 $9,294,253.450 $9,387,358.270 $9,884,849.520