Job Info for 0184-01-068

County: CORYELL Highway: SH 36 Date: 03/07/2023 (1 year ago) Engineer's Estimate: $260,435 Control Number: 0184-01-068
Project: C 184-1-68 District: WACO Time: 75 WORKING DAYS Type: LANDSCAPE IMPROVEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $260,435.00
CROSS PLUS CONSTRUCTION, LLC   $291,325.00 1
11.86% | $30,890.00
TIGHT LINE CONSTRUCTION, LLC   $430,701.00 2
65.38% | $170,266.00
47.84% | $139,376.00
Subcontractor Percentage Amount
CEN-TEX IRRIGATION SYSTEMS, INC. 3.26% $9,497.20
Total: 3.26% $9,497.20

Bid Items

Items: 21, 0 filtered
CORYELL SH 36  |  WACO  |  0184-01-068  |  03/07/2023  |  $260,435  |  C 184-1-68  |  LANDSCAPE IMPRV  |  75 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate CROSS PLUS CONSTRUCTION, LLC TIGHT LINE CONSTRUCTION, LLC
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 146.000 $25.000 $1.000 $10.000
168 6001 VEGETATIVE WATERING MG 146.000 $25.000 $50.000 $1.000
170 6003 IRRIGATION SYSTEM (TY II) LS 1.000 $20,000.000 $8,750.000 $55,000.000
192 6002 PLANT MATERIAL (1-GAL) EA 57.000 $25.000 $34.000 $20.000
192 6004 PLANT MATERIAL (5-GAL) EA 23.000 $35.000 $52.000 $50.000
192 6012 MULCH CY 25.000 $35.000 $55.000 $100.000
192 6024 PLANT MATERIAL (30 GAL) (TREE) EA 1.000 $250.000 $500.000 $650.000
192 6025 PLANT MATERIAL (45 GAL) (TREE) EA 29.000 $475.000 $800.000 $650.000
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 9.000 $400.000 $1,000.000 $1,200.000
423 6004 RETAINING WALL (CONC BLOCK) SF 1,660.000 $40.000 $40.000 $55.000
423 6006 RETAINING WALL (STONE) SF 2,340.000 $25.000 $35.000 $25.000
423 6015 RETAINING WALL (SPECIAL) SF 1,660.000 $25.000 $22.000 $55.000
432 6009 RIPRAP (CONC) (CL B) (4") CY 6.400 $250.000 $900.000 $3,000.000
432 6047 RIPRAP (MOW STRIP)(6 IN) CY 4.000 $570.000 $900.000 $2,000.000
500 6001 MOBILIZATION LS 1.000 $34,000.000 $25,000.000 $50,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $1,500.000 $2,000.000 $3,500.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 1.000 $50.000 $100.000 $1,500.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 1.000 $20.000 $50.000 $500.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 100.000 $3.500 $5.000 $10.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 100.000 $2.000 $2.000 $2.000
6185 6002 TMA (STATIONARY) DAY 5.000 $1.000 $1,578.000 $1.000
Totals: $260,435.00 $291,325.00 $430,701.00