CORYELL SH 36 (0183-04-053)

Items: 43

County: CORYELL
Length: N/A
Highway: SH 36
District: WACO
Control Number: 0183-04-053
DBE Goal: N/A
Project: STP 2020(565)
Guaranty: N/A
Time: 90 WORKING DAYS
Engineer's Estimate: $3,097,761.06
Date: 02/06/2020 (6 years ago)
Contract Number: N/A
Type: ASPHALTIC CONCRETE OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$3,097,761.06
$2,987,724.20
Over/Under Est: -3.55% -$110,036.86
Over/Under Est: -0.08% -$2,567.90
Amt Left: 3.6% $107,468.96
Over/Under Est: 2.94% $90,952.06
Amt Left: 6.73% $200,988.92
Delta: -3.02% -$93,519.96
Over/Under Est: 28.2% $873,417.94
Amt Left: 32.92% $983,454.80
Delta: -24.54% -$782,465.88

Bid Items & Bid Tabulations

43 Total 0 of 43
CORYELL  |  SH 36  |  WACO  |  0183-04-053  |  02/06/2020  |  $3,097,761.06  |  STP 2020(565)  |  ASPHIC CONC OVERLAY  |  90 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
TEXAS MATERIALS GROUP, INC.
LONE STAR PAVING COMPANY
REMOVING CONCRETE(MOW STRIP)
LF 2,600.000 $7.700 $12.000 $5.600 $4.350 $6.000
ROLL SODDING
SY 3,254.000 $4.000 $6.000 $8.500 $5.000 $6.000
VEGETATIVE WATERING
MG 26.800 $12.500 $25.000 $1.000 $44.400 $50.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
SY 20,000.000 $45.000 $35.000 $44.850 $44.150 $50.000
PLANE ASPH CONC PAV (1.5")
SY 163,952.000 $1.490 $1.000 $0.950 $0.950 $1.300
PLANE ASPH CONC PAV (2 1/2"-3")
SY 1,338.000 $3.000 $5.000 $10.150 $5.150 $6.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 6.000 $1,000.000 $750.000 $325.000 $500.000 $2,000.000
RIPRAP (MOW STRIP)(4 IN)
CY 185.900 $438.000 $500.000 $555.000 $407.000 $407.000
CLEANING AND SEALING JOINTS (CL 3)
LF 236.000 $35.000 $60.000 $50.600 $48.830 $49.000
MOBILIZATION
LS 1.000 $275,000.000 $140,000.000 $90,978.000 $200,985.000 $130,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $2,500.000 $2,355.000 $705.000 $35,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 200.000 $3.800 $7.000 $16.850 $5.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 200.000 $0.750 $0.500 $8.000 $1.000 $1.000
RUMBLE STRIPS (SHOULDER)
LF 67,063.000 $0.200 $0.200 $0.180 $0.100 $0.130
RUMBLE STRIPS (CENTERLINE)
LF 16,742.000 $0.200 $0.200 $0.340 $0.280 $0.130
MTL W-BEAM GD FEN (STEEL POST)
LF 2,597.000 $25.500 $27.000 $22.280 $21.250 $21.250
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 14.000 $1,928.000 $2,000.000 $2,892.000 $1,615.000 $1,615.000
REMOVE METAL BEAM GUARD FENCE
LF 1,870.000 $2.700 $2.000 $1.800 $1.750 $1.750
GUARDRAIL END TREATMENT (INSTALL)
EA 20.000 $2,724.000 $3,000.000 $2,565.000 $2,475.000 $2,475.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $261.000 $250.000 $210.000 $225.000 $225.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,223.000 $0.980 $1.000 $1.000 $0.950 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 5,328.000 $1.080 $1.000 $1.000 $0.950 $1.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 3,010.000 $1.400 $0.750 $0.730 $0.750 $0.700
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 9,601.000 $1.000 $0.700 $0.690 $0.650 $0.670
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 460.000 $5.630 $5.250 $5.200 $7.500 $5.000
PAVEMENT SEALER 4"
LF 1,380.000 $0.180 $0.300 $0.260 $2.950 $0.250
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,378.000 $0.390 $0.400 $0.390 $0.500 $0.380
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 56,927.000 $0.360 $0.350 $0.330 $0.310 $0.320
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 12,148.000 $0.400 $0.350 $0.350 $0.320 $0.340
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 90,313.000 $0.380 $0.350 $0.320 $0.310 $0.310
PREFAB PAV MRK TY C (W) (ARROW)
EA 30.000 $210.130 $200.000 $200.000 $190.000 $193.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 6.000 $344.980 $350.000 $357.000 $300.000 $344.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 7.000 $575.000 $550.000 $565.000 $545.000 $544.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $295.000 $225.000 $220.000 $255.000 $209.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 22.000 $37.000 $45.000 $45.000 $40.000 $43.000
REFL PAV MRKR TY I-C
EA 262.000 $4.000 $5.000 $4.150 $4.600 $4.000
REFL PAV MRKR TY II-A-A
EA 799.000 $3.880 $4.000 $3.100 $4.050 $3.000
ELIM EXT PAV MRK & MRKS (4")
LF 1,380.000 $0.480 $2.000 $1.750 $5.000 $1.670
D-GR HMA TY-C SAC-B PG70-22
TON 18,185.000 $60.000 $75.000 $75.900 $81.000 $105.000
BONDING COURSE
GAL 33,056.000 $2.700 $3.250 $2.100 $2.600 $2.800
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $9,329.030 $5,000.000 $2,500.000 $2,400.000 $8,000.000
TMA (STATIONARY)
DAY 20.000 $195.000 $200.000 $420.000 $240.000 $250.000
TMA (MOBILE OPERATION)
HR 480.000 $49.800 $60.000 $65.000 $10.000 $75.000
Totals: $3,097,761.060 $2,987,724.200 $3,095,193.160 $3,188,713.120 $3,971,179.000