Job Info for 0183-04-053

County: CORYELL Highway: SH 36 Date: 02/06/2020 (4 years ago) Engineer's Estimate: $3,097,761 Control Number: 0183-04-053
Project: STP 2020(565) District: WACO Time: 90 WORKING DAYS Type: ASPHALTIC CONCRETE OVERLAY

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,097,761.06
BIG CREEK CONSTRUCTION, LTD.   $2,987,724.20 1
-3.55% | -$110,036.86
KNIFE RIVER CORPORATION - SOUTH   $3,095,193.16 2
-0.08% | -$2,567.90
3.6% | $107,468.96
TEXAS MATERIALS GROUP, INC.   $3,188,713.12 3
2.94% | $90,952.06
6.73% | $200,988.92
3.02% | $93,519.96
LONE STAR PAVING COMPANY   $3,971,179.00 4
28.2% | $873,417.94
32.92% | $983,454.80
24.54% | $782,465.88

Bid Items

Items: 43, 0 filtered
CORYELL SH 36  |  WACO  |  0183-04-053  |  02/06/2020  |  $3,097,761  |  STP 2020(565)  |  ASPHIC CONC OVERLAY  |  90 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BIG CREEK CONSTRUCTION, LTD. KNIFE RIVER CORPORATION - SOUTH TEXAS MATERIALS GROUP, INC. LONE STAR PAVING COMPANY
104 6054 REMOVING CONCRETE(MOW STRIP) LF 2,600.000 $7.700 $12.000 $5.600 $4.350 $6.000
162 6008 ROLL SODDING SY 3,254.000 $4.000 $6.000 $8.500 $5.000 $6.000
168 6001 VEGETATIVE WATERING MG 26.800 $12.500 $25.000 $1.000 $44.400 $50.000
351 6006 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 20,000.000 $45.000 $35.000 $44.850 $44.150 $50.000
354 6041 PLANE ASPH CONC PAV (1.5") SY 163,952.000 $1.490 $1.000 $0.950 $0.950 $1.300
354 6046 PLANE ASPH CONC PAV (2 1/2"-3") SY 1,338.000 $3.000 $5.000 $10.150 $5.150 $6.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 6.000 $1,000.000 $750.000 $325.000 $500.000 $2,000.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 185.900 $438.000 $500.000 $555.000 $407.000 $407.000
438 6006 CLEANING AND SEALING JOINTS (CL 3) LF 236.000 $35.000 $60.000 $50.600 $48.830 $49.000
500 6001 MOBILIZATION LS 1.000 $275,000.000 $140,000.000 $90,978.000 $200,985.000 $130,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $5,000.000 $2,500.000 $2,355.000 $705.000 $35,500.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 200.000 $3.800 $7.000 $16.850 $5.000 $5.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 200.000 $0.750 $0.500 $8.000 $1.000 $1.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 67,063.000 $0.200 $0.200 $0.180 $0.100 $0.130
533 6002 RUMBLE STRIPS (CENTERLINE) LF 16,742.000 $0.200 $0.200 $0.340 $0.280 $0.130
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 2,597.000 $25.500 $27.000 $22.280 $21.250 $21.250
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 14.000 $1,928.000 $2,000.000 $2,892.000 $1,615.000 $1,615.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 1,870.000 $2.700 $2.000 $1.800 $1.750 $1.750
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 20.000 $2,724.000 $3,000.000 $2,565.000 $2,475.000 $2,475.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 8.000 $261.000 $250.000 $210.000 $225.000 $225.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 1,223.000 $0.980 $1.000 $1.000 $0.950 $1.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 5,328.000 $1.080 $1.000 $1.000 $0.950 $1.000
666 6030 REFL PAV MRK TY I (W)8"(DOT)(100MIL) LF 3,010.000 $1.400 $0.750 $0.730 $0.750 $0.700
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 9,601.000 $1.000 $0.700 $0.690 $0.650 $0.670
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 460.000 $5.630 $5.250 $5.200 $7.500 $5.000
666 6224 PAVEMENT SEALER 4" LF 1,380.000 $0.180 $0.300 $0.260 $2.950 $0.250
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 1,378.000 $0.390 $0.400 $0.390 $0.500 $0.380
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 56,927.000 $0.360 $0.350 $0.330 $0.310 $0.320
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 12,148.000 $0.400 $0.350 $0.350 $0.320 $0.340
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 90,313.000 $0.380 $0.350 $0.320 $0.310 $0.310
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 30.000 $210.130 $200.000 $200.000 $190.000 $193.000
668 6078 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 6.000 $344.980 $350.000 $357.000 $300.000 $344.000
668 6083 PREFAB PAV MRK TY C (W) (LNDP ARROW) EA 7.000 $575.000 $550.000 $565.000 $545.000 $544.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 2.000 $295.000 $225.000 $220.000 $255.000 $209.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 22.000 $37.000 $45.000 $45.000 $40.000 $43.000
672 6007 REFL PAV MRKR TY I-C EA 262.000 $4.000 $5.000 $4.150 $4.600 $4.000
672 6009 REFL PAV MRKR TY II-A-A EA 799.000 $3.880 $4.000 $3.100 $4.050 $3.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 1,380.000 $0.480 $2.000 $1.750 $5.000 $1.670
3076 6025 D-GR HMA TY-C SAC-B PG70-22 TON 18,185.000 $60.000 $75.000 $75.900 $81.000 $105.000
3084 6001 BONDING COURSE GAL 33,056.000 $2.700 $3.250 $2.100 $2.600 $2.800
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $9,329.030 $5,000.000 $2,500.000 $2,400.000 $8,000.000
6185 6002 TMA (STATIONARY) DAY 20.000 $195.000 $200.000 $420.000 $240.000 $250.000
6185 6003 TMA (MOBILE OPERATION) HR 480.000 $49.800 $60.000 $65.000 $10.000 $75.000
Totals: $3,097,761.06 $2,987,724.20 $3,095,193.16 $3,188,713.12 $3,971,179.00