County: COOKE Highway: FM 373 Date: 04/05/2024 (7 months ago) Engineer's Estimate: $1,098,368 Control Number: 0823-01-038
Project: C 823-1-38 District: WICHITA FALLS Time: 34 WORKING DAYS Type: SURFACING/ROADWAY RESTORATION
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,098,368.33
EUROVIA ATLANTIC COAST LLC   $903,763.84 1
-17.72% | -$194,604.49
JAGOE-PUBLIC COMPANY   $977,137.25 2
-11.04% | -$121,231.08
8.12% | $73,373.41
PEACHTREE CONSTRUCTION, LTD.   $1,067,731.80 3
-2.79% | -$30,636.53
18.14% | $163,967.96
9.27% | $90,594.55
A. L. HELMCAMP, INC.   $1,183,402.40 4
7.74% | $85,034.07
30.94% | $279,638.56
10.83% | $115,670.60
Subcontractor Percentage Amount
TRP CONSTRUCTION GROUP, LLC 2.33% $21,057.70
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.44% $3,976.56
Total: 2.77% $25,034.26

Bid Items

Items: 21, 0 filtered
COOKE FM 373  |  WICHITA FALLS  |  0823-01-038  |  04/05/2024  |  $1,098,368  |  C 823-1-38  |  SURF/ROADWAY RESTOR  |  34 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate EUROVIA ATLANTIC COAST LLC JAGOE-PUBLIC COMPANY PEACHTREE CONSTRUCTION, LTD. A. L. HELMCAMP, INC.
351 6013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") SY 5,109.000 $70.000 $40.500 $50.000 $53.650 $67.000
354 6045 PLANE ASPH CONC PAV (2") SY 25,191.000 $5.280 $3.350 $3.000 $2.750 $3.800
500 6001 MOBILIZATION LS 1.000 $107,501.870 $47,000.000 $90,000.000 $80,000.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $18,000.000 $26,000.000 $20,000.000 $15,000.000 $25,000.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 1,090.000 $2.810 $5.000 $1.000 $4.000 $1.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 150.000 $1.800 $1.100 $2.500 $1.400 $1.150
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 140.000 $4.690 $4.700 $5.000 $6.000 $5.000
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 6,865.000 $1.150 $0.730 $1.750 $0.950 $0.750
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 13,356.000 $1.150 $0.730 $1.750 $0.950 $0.750
668 6067 PREFAB PAV MRK TY C (W) (6") (LNDP) LF 275.000 $15.500 $4.950 $6.000 $6.250 $5.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 2.000 $293.000 $292.000 $300.000 $375.000 $300.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 2.000 $315.250 $386.000 $325.000 $500.000 $400.000
668 6091 PREFAB PAV MRK TY C (W) (18")(YLD TRI) EA 14.000 $51.000 $69.000 $80.000 $89.000 $70.000
672 6007 REFL PAV MRKR TY I-C EA 16.000 $10.680 $5.000 $7.000 $6.500 $5.200
672 6009 REFL PAV MRKR TY II-A-A EA 320.000 $7.720 $5.000 $7.000 $6.500 $5.200
678 6006 PAV SURF PREP FOR MRK (12") LF 86.000 $1.050 $0.360 $3.500 $0.500 $0.400
678 6008 PAV SURF PREP FOR MRK (24") LF 195.000 $1.250 $0.610 $4.500 $0.800 $0.650
3076 6024 D-GR HMA TY-C SAC-A PG70-22 TON 2,864.000 $140.000 $151.000 $162.000 $190.000 $195.000
3084 6001 BONDING COURSE GAL 1,044.000 $4.000 $4.500 $1.000 $5.250 $8.000
6185 6002 TMA (STATIONARY) DAY 25.000 $438.000 $550.000 $150.000 $300.000 $200.000
6185 6005 TMA (MOBILE OPERATION) DAY 30.000 $391.000 $1,200.000 $75.000 $850.000 $25.000
Totals: $1,098,368.33 $903,763.84 $977,137.25 $1,067,731.80 $1,183,402.40