Show Job Controls
Bid Cobra

COMAL SH0046 (6322-29-001)

Items: 48

County: COMAL
Length: N/A
Highway: SH0046
District: SAN ANTONIO
Control Number: 6322-29-001
DBE Goal: N/A
Project: RMC - 632229001
Guaranty: N/A
Time: 730 CALENDAR DAYS
Engineer's Estimate: $2,145,530.00
Date: 01/04/2018 (8 years ago)
Contract Number: N/A
Type: GUARDRAL REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$2,145,530.00
$2,123,690.00
Over/Under Est: -1.02% -$21,840.00
$2,451,295.00
Over/Under Est: 14.25% $305,765.00
Amt Left: 15.43% $327,605.00
$2,771,327.30
Over/Under Est: 29.17% $625,797.30
Amt Left: 30.5% $647,637.30
Delta: -13.06% -$320,032.30

Bid Items & Bid Tabulations

48 Total 0 of 48
COMAL  |  SH0046  |  SAN ANTONIO  |  6322-29-001  |  01/04/2018  |  $2,145,530.00  |  RMC - 632229001  |  GUARDRAL REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
K-BAR SERVICES, INC.
SHORT-LINE CORPORATION
DBI SERVICES, LLC
RIPRAP (MOW STRIP)(4 IN)
CY 100.000 $100.000 $100.000 $100.000 $333.100
RETROFIT RAIL (TY T631)
LF 1,000.000 $50.000 $85.000 $50.000 $78.470
MOBILIZATION (CALLOUT)
EA 100.000 $100.000 $1.000 $1.000 $259.640
MOBILIZATION (EMERGENCY)
EA 100.000 $200.000 $1.000 $1,000.000 $450.110
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $20.000 $25.000 $24.000 $19.780
MTL W-BEAM GD FEN (STEEL POST)
LF 50.000 $1.000 $15.000 $35.000 $20.280
MTL THRIE-BEAM GD FEN (TIM POST)
LF 50.000 $50.000 $40.000 $50.000 $46.200
MTL THRIE-BEAM GD FEN (STEEL POST)
LF 50.000 $1.000 $40.000 $1.000 $37.920
TERMINAL ANCHOR SECTION
EA 4.000 $500.000 $350.000 $250.000 $620.450
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 3.000 $2,000.000 $2,000.000 $2,500.000 $1,898.900
MTL W-BEAM GD FEN ADJUSTMENT
LF 400.000 $1.000 $6.000 $2.000 $6.430
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 15.000 $1,050.000 $1,200.000 $1,200.000 $2,318.230
DOWNSTREAM ANCHOR TERMINAL ADJUSTMENT
EA 15.000 $500.000 $500.000 $100.000 $446.470
REMOVE METAL BEAM GUARD FENCE
LF 2,000.000 $1.000 $0.800 $1.000 $2.350
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $100.000 $500.000 $100.000 $241.100
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 15.000 $250.000 $400.000 $100.000 $157.160
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $2,000.000 $2,000.000 $2,000.000 $2,972.800
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $500.000 $800.000 $500.000 $223.240
GDRAIL END TRT(INST)(WOOD POST)(TY III)
EA 10.000 $2,000.000 $2,000.000 $2,000.000 $2,397.580
CHAIN LINK FENCE (REPAIR) (6')
LF 500.000 $10.000 $10.000 $10.000 $17.260
CHAIN LINK FENCE (REMOVE)
LF 500.000 $1.000 $1.000 $5.000 $3.220
REPAIR RAIL ELEMENT (W - BEAM)
LF 35,000.000 $18.000 $20.500 $19.000 $14.500
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 85.000 $30.000 $2.000 $50.000 $49.690
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 50.000 $50.000 $5.000 $50.000 $50.690
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 1,000.000 $25.000 $20.000 $25.000 $22.220
REM / REPL TIMBER/STL POST W/O CONC FND
EA 2,500.000 $40.000 $35.000 $40.000 $35.980
REM / REPL TIMBER / STL POST W/CONC FND
EA 100.000 $1.000 $15.000 $1.000 $49.780
REALIGN POSTS
EA 600.000 $1.000 $1.000 $45.000 $26.790
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 7,500.000 $20.000 $10.000 $19.000 $21.400
REPLACE SINGLE GDRAIL TERMINAL POST
EA 1,000.000 $50.000 $20.000 $50.000 $46.610
REPAIR OF TERMINAL ANCHORS POSTS
EA 20.000 $1.000 $1.000 $1.000 $14.080
REPLACE TERMINAL ANCHOR POSTS
EA 50.000 $1.000 $1.000 $1.000 $44.200
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 300.000 $2,000.000 $2,300.000 $2,500.000 $2,744.120
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 250.000 $500.000 $100.000 $500.000 $893.800
REM & RESET SGT IMPACT HEAD
EA 150.000 $50.000 $50.000 $50.000 $160.730
REPAIR STEEL POST WITH BASE PLATE
EA 20.000 $1.000 $100.000 $1.000 $188.580
REPLACE POSTS (TL-3)
EA 2,500.000 $55.000 $60.000 $75.000 $89.830
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 50.000 $100.000 $100.000 $1.000 $388.470
REPAIR CONCRETE FOUNDATION (TL-3)
EA 40.000 $1.000 $200.000 $20.000 $185.810
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 75.000 $300.000 $500.000 $250.000 $919.710
REPLACE CABLE (TL-3)
LF 20,000.000 $1.500 $0.500 $0.500 $4.070
POST AND CABLE FENCE (REMOVAL)
LF 100.000 $10.000 $5.000 $1.000 $5.120
POST AND CABLE FENCE (REMV CONC ANCHOR)
EA 5.000 $100.000 $200.000 $1.000 $365.940
POST AND CABLE FENCE(REMV / REPL POSTS)
EA 40.000 $50.000 $50.000 $50.000 $345.990
POST AND CABLE FENCE(RMV/REPL CNC ANCH)
EA 5.000 $100.000 $500.000 $100.000 $360.090
POST AND CABLE FENCE (REMV/ REPL CABLE)
LF 75.000 $10.000 $10.000 $10.000 $332.490
REPAIR (VIA -SAND FILL PLASTIC BARRELS)
EA 100.000 $200.000 $200.000 $300.000 $339.070
REPAIR (STL POST W/ DOUBLED W-BEAMS-T6)
LF 1,000.000 $50.000 $40.000 $50.000 $43.810
Totals: $2,145,530.000 $2,123,690.000 $2,451,295.000 $2,771,327.300