Job Info for 6322-18-001

County: COMAL Highway: FM3009 Date: 01/31/2018 (6 years ago) Engineer's Estimate: $204,893 Control Number: 6322-18-001
Project: RMC - 632218001 District: SAN ANTONIO Time: 30 W Type: DRAINAGE IMPROVEMENTS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $204,893.00
DAN WILLIAMS COMPANY   $165,000.00 1
-19.47% | -$39,893.00
CURRAN CONTRACTING COMPANY   $168,837.70 2
-17.6% | -$36,055.30
2.33% | $3,837.70
SHANNON-MONK, INC.   $185,421.14 3
-9.5% | -$19,471.86
12.38% | $20,421.14
9.82% | $16,583.44
HILL COUNTRY BRIDGE, INC.   $187,726.89 4
-8.38% | -$17,166.11
13.77% | $22,726.89
1.24% | $2,305.75
TMES LLC   $192,336.50 5
-6.13% | -$12,556.50
16.57% | $27,336.50
2.46% | $4,609.61
DENBOW COMPANY INC.   $199,855.00 6
-2.46% | -$5,038.00
21.12% | $34,855.00
3.91% | $7,518.50
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.   $207,591.20 7
1.32% | $2,698.20
25.81% | $42,591.20
3.87% | $7,736.20
FNH CONSTRUCTION, LLC   $236,861.00 8
15.6% | $31,968.00
43.55% | $71,861.00
14.10% | $29,269.80
ACME BRIDGE COMPANY, INC.   $245,180.40 9
19.66% | $40,287.40
48.59% | $80,180.40
3.51% | $8,319.40
CHAMPION INFRASTRUCTURE, LLC   $304,648.20 10
48.69% | $99,755.20
84.64% | $139,648.20
24.25% | $59,467.80

Bid Items

Items: 33, 0 filtered
COMAL FM3009  |  SAN ANTONIO  |  6322-18-001  |  01/31/2018  |  $204,893  |  RMC - 632218001  |  DRAINAGE IMPRVS  |  30 W
Item code Description Unit Quantity Engineer's Estimate DAN WILLIAMS COMPANY CURRAN CONTRACTING COMPANY SHANNON-MONK, INC. HILL COUNTRY BRIDGE, INC. TMES LLC DENBOW COMPANY INC. DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC. FNH CONSTRUCTION, LLC ACME BRIDGE COMPANY, INC. CHAMPION INFRASTRUCTURE, LLC
104 6009 REMOVING CONC (RIPRAP) SY 181.000 $20.000 $15.000 $19.300 $18.000 $29.000 $17.240 $18.000 $28.000 $40.000 $17.700 $40.000
104 6015 REMOVING CONC (SIDEWALKS) SY 93.000 $25.000 $20.000 $24.300 $16.000 $22.500 $16.770 $18.000 $24.000 $40.000 $17.000 $60.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 110.000 $25.000 $25.000 $23.500 $16.000 $40.000 $20.060 $15.000 $24.000 $40.000 $26.600 $60.000
104 6021 REMOVING CONC (CURB) LF 87.000 $20.000 $5.000 $18.400 $10.000 $12.000 $6.460 $10.000 $9.000 $12.500 $15.700 $30.000
150 6002 BLADING HR 25.000 $117.000 $40.000 $158.950 $165.000 $177.000 $124.650 $177.000 $120.000 $150.000 $196.000 $150.000
158 6002 SPEC EXCAV WORK (BACKHOE) HR 25.000 $93.000 $23.000 $119.900 $140.000 $96.000 $144.320 $135.000 $120.000 $150.000 $89.100 $150.000
158 6003 SPEC EXCAV WORK (HYD EXCAVATOR) HR 25.000 $90.000 $45.000 $226.200 $165.000 $177.000 $172.520 $199.000 $120.000 $150.000 $135.000 $150.000
162 6002 BLOCK SODDING SY 259.000 $10.000 $8.500 $5.750 $10.000 $6.750 $10.310 $5.000 $14.000 $6.500 $8.200 $20.000
168 6001 VEGETATIVE WATERING MG 5.000 $100.000 $23.000 $34.700 $65.000 $68.000 $187.950 $36.000 $80.000 $2,500.000 $93.700 $250.000
400 6006 CUT & RESTORING PAV SY 63.000 $150.000 $75.000 $124.550 $120.000 $156.000 $136.610 $222.000 $200.000 $200.000 $158.000 $210.000
401 6001 FLOWABLE BACKFILL CY 65.920 $150.000 $135.000 $209.350 $142.000 $117.000 $150.110 $150.000 $135.000 $350.000 $205.000 $210.000
432 6001 RIPRAP (CONC)(4 IN) CY 27.000 $500.000 $510.000 $351.300 $643.000 $520.000 $450.590 $845.000 $505.000 $550.000 $614.000 $840.000
450 6051 RAIL (HANDRAIL)(TY E) LF 78.000 $150.000 $95.000 $117.850 $148.000 $130.000 $106.730 $159.000 $160.000 $210.000 $200.000 $300.000
464 6018 RC PIPE (CL IV)(24 IN) LF 322.000 $125.000 $85.000 $78.650 $110.000 $90.000 $87.930 $103.000 $80.000 $85.000 $110.000 $80.000
465 6233 INLET (COMP) (TY SIDEWALK BRIDGE) EA 2.000 $8,500.000 $8,000.000 $5,807.400 $6,500.000 $9,900.000 $9,988.010 $7,640.000 $8,000.000 $5,000.000 $14,500.000 $7,500.000
467 6394 SET (TY II) (24 IN) (RCP) (6: 1) (C) EA 1.000 $1,800.000 $1,700.000 $2,450.000 $3,850.000 $1,900.000 $1,360.650 $2,000.000 $4,500.000 $3,000.000 $2,850.000 $3,200.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 4.000 $1,800.000 $1,300.000 $2,450.000 $2,600.000 $1,160.000 $1,370.080 $1,670.000 $2,400.000 $3,000.000 $2,410.000 $3,600.000
496 6050 REMOV STR (DRIVEWAY CULVERT) EA 1.000 $800.000 $1,500.000 $1,236.050 $3,150.000 $1,320.000 $3,493.910 $910.000 $700.000 $500.000 $1,260.000 $4,500.000
500 6001 MOBILIZATION LS 1.000 $17,500.000 $15,000.000 $15,769.600 $17,895.000 $18,750.000 $29,780.930 $17,826.000 $20,000.000 $22,000.000 $22,200.000 $60,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $5,000.000 $9,500.000 $3,847.700 $3,200.000 $9,000.000 $6,558.430 $2,650.000 $11,000.000 $8,500.000 $9,190.000 $6,000.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 30.000 $36.000 $30.000 $49.700 $31.000 $28.000 $31.080 $42.000 $23.000 $30.000 $41.200 $40.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 30.000 $10.000 $8.000 $14.350 $6.500 $8.000 $15.530 $38.000 $9.000 $15.000 $27.400 $25.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 111.000 $28.000 $11.000 $14.900 $17.500 $12.000 $14.720 $14.000 $18.000 $45.000 $16.500 $20.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 111.000 $10.000 $5.000 $4.300 $6.500 $5.000 $8.310 $7.000 $18.000 $20.000 $12.300 $15.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 300.000 $4.500 $4.000 $3.050 $4.500 $3.000 $4.170 $3.000 $3.250 $4.000 $2.750 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 300.000 $2.750 $0.500 $1.900 $2.000 $0.550 $2.280 $0.500 $0.750 $2.000 $1.350 $2.000
506 6044 SANDBAGS FOR EROSION CONTROL (8") LF 47.000 $6.000 $8.900 $16.550 $6.500 $6.500 $18.220 $7.000 $12.000 $12.000 $11.000 $10.000
508 6001 CONSTRUCTING DETOURS SY 62.000 $75.000 $70.000 $18.250 $31.000 $23.000 $64.730 $60.000 $40.000 $42.000 $93.600 $120.000
529 6002 CONC CURB (TY II) LF 108.000 $35.000 $35.000 $39.300 $16.000 $34.500 $22.630 $27.000 $48.000 $35.000 $42.800 $40.000
530 6004 DRIVEWAYS (CONC) SY 134.000 $150.000 $75.000 $75.950 $65.000 $62.000 $84.020 $112.000 $96.000 $85.000 $131.000 $160.000
531 6003 CONC SIDEWALKS (6") SY 67.000 $85.000 $85.000 $80.500 $75.000 $90.000 $54.580 $98.000 $110.000 $65.000 $134.000 $160.000
531 6013 CURB RAMPS (TY 10) EA 1.000 $1,500.000 $1,500.000 $2,131.900 $2,510.000 $1,575.000 $1,074.910 $2,030.000 $2,150.000 $1,850.000 $3,420.000 $3,400.000
644 6070 RELOCATE SM RD SN SUP&AM TY S80 EA 2.000 $500.000 $800.000 $500.000 $750.000 $545.000 $266.060 $775.000 $450.000 $650.000 $617.000 $750.000
Totals: $204,893.00 $165,000.00 $168,837.70 $185,421.14 $187,726.89 $192,336.50 $199,855.00 $207,591.20 $236,861.00 $245,180.40 $304,648.20