Job Info for 1272-01-019

County: COMAL Highway: FM 1101 Date: 09/07/2018 (6 years ago) Engineer's Estimate: $259,933 Control Number: 1272-01-019
Project: STP 2019(046)HES District: SAN ANTONIO Time: 119 WORKING DAYS Type: PROFILE EDGELINE & CENTERLINE MARKINGS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $259,933.16
TRP CONSTRUCTION GROUP, LLC   $195,334.08 1
-24.85% | -$64,599.08
INTERSTATE BARRICADES & MARKINGS, INC.   $199,794.98 2
-23.14% | -$60,138.18
2.28% | $4,460.90
D. I. J. CONSTRUCTION, INC.   $201,735.38 3
-22.39% | -$58,197.78
3.28% | $6,401.30
0.97% | $1,940.40
STRIPE-A-ZONE, INC.   $219,535.07 4
-15.54% | -$40,398.09
12.39% | $24,200.99
8.82% | $17,799.69

Bid Items

Items: 12, 0 filtered
COMAL FM 1101  |  SAN ANTONIO  |  1272-01-019  |  09/07/2018  |  $259,933  |  STP 2019(046)HES  |  PROFILE EDGELINE & CENTERLINE MRK  |  119 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TRP CONSTRUCTION GROUP, LLC INTERSTATE BARRICADES & MARKINGS, INC. D. I. J. CONSTRUCTION, INC. STRIPE-A-ZONE, INC.
500 6001 MOBILIZATION LS 1.000 $19,393.570 $14,000.000 $7,500.000 $20,000.000 $30,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $3,500.000 $500.000 $1.000 $1.000 $1,500.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 53,272.000 $0.270 $0.170 $0.300 $0.230 $0.200
533 6002 RUMBLE STRIPS (CENTERLINE) LF 25,936.000 $0.210 $0.240 $0.300 $0.320 $0.270
666 6224 PAVEMENT SEALER 4" LF 35,586.000 $0.110 $0.160 $0.250 $0.100 $0.100
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 3,880.000 $0.560 $0.500 $0.650 $0.330 $0.850
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 31,706.000 $0.350 $0.400 $0.400 $0.310 $0.370
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 140,534.000 $0.580 $0.520 $0.530 $0.540 $0.505
666 6344 REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL) LF 3,337.000 $0.690 $0.600 $1.000 $0.600 $0.550
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 112,922.000 $0.590 $0.530 $0.530 $0.540 $0.505
672 6009 REFL PAV MRKR TY II-A-A EA 2,210.000 $3.700 $3.250 $3.000 $3.400 $5.750
6185 6002 TMA (STATIONARY) DAY 126.000 $162.000 $1.000 $1.000 $1.000 $2.000
Totals: $259,933.16 $195,334.08 $199,794.98 $201,735.38 $219,535.07