COMAL CS (0915-17-067)
Items: 71
County: COMAL
Length: N/A
Highway: CS
District: SAN ANTONIO
Control Number: 0915-17-067
DBE Goal: N/A
Project: BR 2019(908)
Guaranty: N/A
Time: 213 WORKING DAYS
Engineer's Estimate: $1,790,990.35
Date: 05/07/2019 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (11)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,790,990.35 | |||
| $1,589,567.35 |
-11.25%
-$201,423.00
|
|||
| $1,665,915.12 |
-6.98%
-$125,075.23
|
4.8%
$76,347.77
|
||
| $1,764,002.85 |
-1.51%
-$26,987.50
|
10.97%
$174,435.50
|
-5.89%
-$98,087.73
|
|
| $1,841,184.57 |
2.8%
$50,194.22
|
15.83%
$251,617.22
|
-4.38%
-$77,181.72
|
|
| $1,862,795.55 |
4.01%
$71,805.20
|
17.19%
$273,228.20
|
-1.17%
-$21,610.98
|
|
| $2,032,908.94 |
13.51%
$241,918.59
|
27.89%
$443,341.59
|
-9.13%
-$170,113.39
|
|
| $2,084,871.15 |
16.41%
$293,880.80
|
31.16%
$495,303.80
|
-2.56%
-$51,962.21
|
|
| $2,131,912.30 |
19.04%
$340,921.95
|
34.12%
$542,344.95
|
-2.26%
-$47,041.15
|
|
| $2,132,890.60 |
19.09%
$341,900.25
|
34.18%
$543,323.25
|
-0.05%
-$978.30
|
|
| $2,559,578.00 |
42.91%
$768,587.65
|
61.02%
$970,010.65
|
-20.01%
-$426,687.40
|
|
| $3,222,116.50 |
79.91%
$1,431,126.15
|
102.7%
$1,632,549.15
|
-25.88%
-$662,538.50
|
E
Engineer's Estimate
$1,790,990.35
1
Awarded
$1,589,567.35
Over/Under Est:
-11.25%
-$201,423.00
$1,665,915.12
Over/Under Est:
-6.98%
-$125,075.23
Amt Left:
4.8%
$76,347.77
$1,764,002.85
Over/Under Est:
-1.51%
-$26,987.50
Amt Left:
10.97%
$174,435.50
Delta:
-5.89%
-$98,087.73
$1,841,184.57
Over/Under Est:
2.8%
$50,194.22
Amt Left:
15.83%
$251,617.22
Delta:
-4.38%
-$77,181.72
$1,862,795.55
Over/Under Est:
4.01%
$71,805.20
Amt Left:
17.19%
$273,228.20
Delta:
-1.17%
-$21,610.98
$2,032,908.94
Over/Under Est:
13.51%
$241,918.59
Amt Left:
27.89%
$443,341.59
Delta:
-9.13%
-$170,113.39
$2,084,871.15
Over/Under Est:
16.41%
$293,880.80
Amt Left:
31.16%
$495,303.80
Delta:
-2.56%
-$51,962.21
$2,131,912.30
Over/Under Est:
19.04%
$340,921.95
Amt Left:
34.12%
$542,344.95
Delta:
-2.26%
-$47,041.15
$2,132,890.60
Over/Under Est:
19.09%
$341,900.25
Amt Left:
34.18%
$543,323.25
Delta:
-0.05%
-$978.30
$2,559,578.00
Over/Under Est:
42.91%
$768,587.65
Amt Left:
61.02%
$970,010.65
Delta:
-20.01%
-$426,687.40
$3,222,116.50
Over/Under Est:
79.91%
$1,431,126.15
Amt Left:
102.7%
$1,632,549.15
Delta:
-25.88%
-$662,538.50
Bid Items & Bid Tabulations
71
Total
0 of 71