Show Job Controls
Bid Cobra

COMAL US 281 (0253-03-074)

Items: 21

County: COMAL
Length: N/A
Highway: US 281
District: SAN ANTONIO
Control Number: 0253-03-074
DBE Goal: N/A
Project: NH 2021(019)
Guaranty: N/A
Time: 165 WORKING DAYS
Engineer's Estimate: $1,140,497.90
Date: 10/02/2020 (5 years ago)
Contract Number: N/A
Type: LANDSCAPE PLANTING AND IRRIGATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,140,497.90
$1,048,990.00
Over/Under Est: -8.02% -$91,507.90
$1,107,976.10
Over/Under Est: -2.85% -$32,521.80
Amt Left: 5.62% $58,986.10
$1,200,476.00
Over/Under Est: 5.26% $59,978.10
Amt Left: 14.44% $151,486.00
Delta: -8.35% -$92,499.90
Over/Under Est: 43.51% $496,204.10
Amt Left: 56.03% $587,712.00
Delta: -36.34% -$436,226.00
Subcontractor Percentage Amount
TX DOWN UNDER CONSTRUCTION LLC 0.88% $9,231.11
Total: 0.88% $9,231.11

Bid Items & Bid Tabulations

21 Total 0 of 21
COMAL  |  US 281  |  SAN ANTONIO  |  0253-03-074  |  10/02/2020  |  $1,140,497.90  |  NH 2021(019)  |  LANDSCAPE PLANTING AND IRRIGATION  |  165 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
APEX LANDSCAPE & IRRIGATION, LLC
LEGACY ENERGY SERVICES
ENCINO LANDSCAPE, INC.
TIGHT LINE CONSTRUCTION, LLC
GENERAL USE COMPOST
CY 4,635.000 $30.000 $20.000 $15.000 $30.000 $30.000
IRRIGATION SYSTEM
LS 1.000 $133,000.000 $116,500.000 $215,000.000 $150,000.000 $200,000.000
WILDFLOWER SEEDING
AC 1.450 $1,700.000 $3,000.000 $1,500.000 $3,000.000 $5,000.000
PLANT MATERIAL (5-GAL)
EA 1,691.000 $30.000 $25.000 $35.000 $30.000 $40.000
PLANT MATERIAL (15-GAL)
EA 1,104.000 $125.000 $120.000 $120.000 $125.000 $150.000
PLANT MATERIAL (30-GAL)
EA 931.000 $225.000 $225.000 $230.000 $225.000 $275.000
MULCH
SY 42,110.000 $3.000 $2.500 $1.650 $3.000 $5.000
PLANT BED PREP (TYPE I)
SY 41,110.000 $2.000 $2.250 $2.750 $2.000 $5.000
PLANT BED PREP (TYPE II)
SY 1,000.000 $2.000 $2.000 $1.000 $3.000 $5.000
PLANT MAINTENANCE
MO 36.000 $2,000.000 $2,000.000 $1,100.000 $2,000.000 $2,500.000
PLANT REPLACEMENT (5-GAL)
EA 38.000 $25.000 $0.100 $1.000 $30.000 $40.000
IRRIGATION SYSTEM OPER AND MAINT
MO 36.000 $1,000.000 $1,000.000 $900.000 $1,000.000 $1,500.000
PLANT REPLACEMENT (15 GAL)
EA 29.000 $115.000 $0.100 $1.000 $100.000 $150.000
PLANT REPLACEMENT (30 GAL)
EA 28.000 $190.000 $0.100 $1.000 $200.000 $300.000
MOBILIZATION
LS 1.000 $82,250.000 $99,703.000 $75,000.000 $110,000.000 $180,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $3,000.000 $2,000.000 $1,350.000 $2,000.000 $2,500.000
CONSTRUCTION EXITS (INSTALL) (TY 3)
SY 777.800 $23.000 $25.000 $70.000 $50.000 $10.000
CONSTRUCTION EXITS (REMOVE)
SY 777.800 $7.500 $5.000 $20.000 $10.000 $5.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 300.000 $4.000 $1.200 $2.500 $10.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 300.000 $1.000 $0.100 $2.000 $0.010 $2.000
TMA (STATIONARY)
DAY 10.000 $215.000 $0.100 $0.010 $1.000 $150.000
Totals: $1,140,497.900 $1,048,990.000 $1,107,976.100 $1,200,476.000 $1,636,702.000