Job Info for 0253-03-073

County: COMAL Highway: US 281 Date: 02/06/2020 (4 years ago) Engineer's Estimate: $1,468,369 Control Number: 0253-03-073
Project: NH 2020(556) District: SAN ANTONIO Time: 178 WORKING DAYS Type: LANDSCAPE PLANTING AND IRRIGATION
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,468,369.00
APEX LANDSCAPE & IRRIGATION, LLC   $1,299,000.00 1
-11.53% | -$169,369.00
ENCINO LANDSCAPE, INC.   $1,336,290.50 2
-8.99% | -$132,078.50
2.87% | $37,290.50
CENTRAL NORTH CONSTRUCTION, LLC   $1,377,327.34 3
-6.2% | -$91,041.66
6.03% | $78,327.34
3.07% | $41,036.84
3LW CIVIL LLC   $1,489,882.80 4
1.47% | $21,513.80
14.69% | $190,882.80
8.17% | $112,555.46
TIGHT LINE CONSTRUCTION, LLC   $1,504,113.50 5
2.43% | $35,744.50
15.79% | $205,113.50
0.96% | $14,230.70
ALTUS CONSTRUCTION LLC   $1,840,751.77 6
25.36% | $372,382.77
41.71% | $541,751.77
22.38% | $336,638.27

Bid Items

Items: 17, 0 filtered
COMAL US 281  |  SAN ANTONIO  |  0253-03-073  |  02/06/2020  |  $1,468,369  |  NH 2020(556)  |  LANDSCAPE PLANTING AND IRRIGATION  |  178 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate APEX LANDSCAPE & IRRIGATION, LLC ENCINO LANDSCAPE, INC. CENTRAL NORTH CONSTRUCTION, LLC 3LW CIVIL LLC TIGHT LINE CONSTRUCTION, LLC ALTUS CONSTRUCTION LLC
161 6012 GENERAL USE COMPOST CY 5,892.000 $35.000 $20.000 $30.000 $18.000 $25.350 $26.000 $22.490
169 6006 SOIL RETENTION BLANKETS (CL 2) (TY F) SY 90.000 $2.000 $16.000 $10.000 $10.000 $5.200 $15.000 $1.070
170 6001 IRRIGATION SYSTEM LS 1.000 $154,000.000 $102,998.750 $100,000.000 $273,000.000 $122,412.984 $175,000.000 $160,787.650
180 6001 WILDFLOWER SEEDING AC 2.285 $1,000.000 $2,400.000 $1,500.000 $1,285.000 $1,300.000 $2,500.000 $6,029.540
192 6004 PLANT MATERIAL (5-GAL) EA 1,830.000 $30.000 $25.000 $30.000 $19.000 $24.395 $30.000 $20.100
192 6005 PLANT MATERIAL (15-GAL) EA 1,877.000 $125.000 $125.000 $130.000 $95.000 $81.870 $120.000 $147.390
192 6006 PLANT MATERIAL (30-GAL) EA 1,131.000 $225.000 $225.000 $250.000 $180.000 $205.156 $225.000 $247.880
192 6013 MULCH SY 56,094.000 $3.000 $2.500 $3.000 $1.980 $5.016 $3.000 $3.630
192 6063 PLANT BED PREP (TYPE I) SY 52,901.000 $2.000 $2.250 $1.000 $4.000 $0.274 $2.000 $0.390
192 6064 PLANT BED PREP (TYPE II) SY 220.000 $2.000 $5.000 $3.000 $15.000 $0.549 $2.000 $0.390
193 6001 PLANT MAINTENANCE MO 36.000 $2,500.000 $2,000.000 $1,500.000 $1,860.000 $7,200.000 $2,500.000 $10,049.230
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 36.000 $750.000 $1,000.000 $1,000.000 $1,600.000 $708.000 $2,500.000 $2,679.790
500 6001 MOBILIZATION LS 1.000 $130,250.000 $125,000.000 $130,000.000 $100,000.000 $150,811.540 $155,000.000 $174,186.620
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 11.000 $3,250.000 $3,415.000 $2,000.000 $1,585.000 $4,192.060 $2,000.000 $6,699.490
506 6034 CONSTRUCTION PERIMETER FENCE LF 160.000 $3.000 $20.000 $10.000 $10.000 $3.950 $1.000 $6.320
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 510.000 $3.000 $1.000 $10.000 $5.500 $5.250 $5.000 $5.800
6185 6002 TMA (STATIONARY) DAY 10.000 $215.000 $175.000 $300.000 $540.000 $342.000 $1.000 $535.960
Totals: $1,468,369.00 $1,299,000.00 $1,336,290.50 $1,377,327.35 $1,489,882.82 $1,504,113.50 $1,840,751.78