Job Info for 6401-54-001

County: COLORADO Highway: SS0052 Date: 05/02/2024 (6 months ago) Changed Engineer's Estimate: $409,782 Control Number: 6401-54-001
Project: RMC - 640154001 District: YOAKUM Time: 30 W Type: ASPHALT PAVEMENT REPAIR
Bidder's List

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $409,782.00
HUNTER INDUSTRIES, LTD.   $468,903.40 1
14.43% | $59,121.40
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.   $528,664.17 2
29.01% | $118,882.17
12.74% | $59,760.77
LCR TOTAL TRANSPORT LLC   $530,097.40 3
29.36% | $120,315.40
13.05% | $61,194.00
0.27% | $1,433.23
FORDE CONSTRUCTION COMPANY, INC.   $598,800.80 4
46.13% | $189,018.80
27.7% | $129,897.40
12.96% | $68,703.40
TEXAS MATERIALS GROUP, INC.   $601,370.80 5
46.75% | $191,588.80
28.25% | $132,467.40
0.43% | $2,570.00

Bid Items

Items: 15, 0 filtered
COLORADO SS0052  |  YOAKUM  |  6401-54-001  |  05/02/2024  |  $409,782  |  RMC - 640154001  |  ASPH PAVMT REPAIR  |  30 W
Item code Description Unit Quantity Engineer's Estimate HUNTER INDUSTRIES, LTD. CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. LCR TOTAL TRANSPORT LLC FORDE CONSTRUCTION COMPANY, INC. TEXAS MATERIALS GROUP, INC.
316 6249 AGGR(TY-PE GR-4 SAC-B) CY 143.000 $120.000 $187.580 $190.250 $260.000 $390.000 $250.000
316 6400 ASPH (AC-15P OR AC-10-2TR OR CRS-2P) GAL 6,298.000 $4.500 $5.050 $5.600 $5.500 $6.000 $5.000
351 6002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 100.000 $75.000 $147.200 $148.000 $100.000 $200.000 $120.000
354 6037 PLANE CONC PAV(0" TO 2") SY 18,522.000 $2.000 $2.680 $4.300 $2.000 $3.700 $3.000
500 6001 MOBILIZATION LS 1.000 $36,500.000 $46,063.680 $25,000.000 $50,000.000 $59,000.000 $40,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $4,000.000 $3,000.000 $5,000.000 $16,700.000 $14,000.000 $2,100.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 404.000 $1.500 $1.630 $1.000 $3.000 $2.500 $1.750
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 30.000 $12.000 $25.000 $20.100 $25.000 $22.000 $22.000
672 6009 REFL PAV MRKR TY II-A-A EA 52.000 $4.000 $10.000 $10.000 $12.000 $9.000 $11.000
3076 6042 D-GR HMA TY-D SAC-B PG70-22 TON 2,038.000 $130.000 $129.300 $159.750 $148.000 $152.000 $200.000
6185 6002 TMA (STATIONARY) DAY 7.000 $250.000 $500.000 $125.000 $750.000 $230.000 $400.000
6185 6005 TMA (MOBILE OPERATION) DAY 2.000 $250.000 $1,000.000 $125.000 $750.000 $170.000 $660.000
6439 6008 HPPM-RIB W/RET REQ TYI(W)6"(SLD)100MIL LF 8,058.000 $0.750 $2.500 $0.930 $1.600 $1.500 $0.950
6439 6014 HPPM-RIB W/RET REQ TYI(Y)6"(BRK)100MIL LF 982.000 $0.750 $2.500 $0.930 $3.600 $3.400 $0.950
6439 6016 HPPM-RIB W/RET REQ TYI(Y)6"(SLD)100MIL LF 124.000 $0.750 $2.500 $0.930 $3.600 $3.400 $0.950
Totals: $409,782.00 $468,903.40 $528,664.17 $530,097.40 $598,800.80 $601,370.80