PREPARING ROW
|
STA
|
11.000
|
$3,000.000
|
$7,700.000
|
$10,000.000
|
$6,480.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
3,391.000
|
$14.000
|
$7.250
|
$9.000
|
$22.440
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
13,044.000
|
$15.000
|
$18.100
|
$18.000
|
$24.540
|
|
|
BLADING
|
HR
|
50.000
|
$100.000
|
$67.000
|
$90.000
|
$102.600
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
SY
|
16,733.000
|
$2.000
|
$0.170
|
$0.200
|
$0.200
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
4,184.000
|
$2.000
|
$0.210
|
$0.300
|
$0.300
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
4,184.000
|
$2.000
|
$0.210
|
$0.300
|
$0.300
|
|
|
VEGETATIVE WATERING
|
MG
|
261.000
|
$45.000
|
$28.000
|
$15.000
|
$9.990
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
2,247.000
|
$75.000
|
$67.400
|
$83.000
|
$90.510
|
|
|
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
|
TON
|
165.000
|
$175.000
|
$165.250
|
$150.000
|
$210.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
10,466.000
|
$5.000
|
$3.900
|
$4.000
|
$3.990
|
|
|
ASPH (RC-250)
|
GAL
|
1,934.000
|
$5.000
|
$4.100
|
$6.300
|
$7.620
|
|
|
AGGR(TY-E GR-5 SAC-B)
|
CY
|
70.000
|
$135.000
|
$186.000
|
$250.000
|
$200.270
|
|
|
AGGR(TY-PE GR-3 SAC-B)
|
CY
|
114.000
|
$115.000
|
$155.000
|
$197.000
|
$183.590
|
|
|
AGGR(TY-PE GR-4 SAC-B)
|
CY
|
109.000
|
$115.000
|
$135.000
|
$159.000
|
$185.820
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
8,633.000
|
$5.000
|
$3.100
|
$3.500
|
$7.710
|
|
|
D-GR HMA TY-B PG70-22
|
TON
|
2,360.000
|
$95.000
|
$90.900
|
$93.000
|
$98.700
|
|
|
D-GR HMA TY-D SAC-B PG70-22
|
TON
|
1,134.000
|
$105.000
|
$107.400
|
$102.000
|
$103.950
|
|
|
D-GR HMA TY-D PG70-22
|
TON
|
1,329.000
|
$95.000
|
$106.100
|
$102.000
|
$103.950
|
|
|
TACK COAT
|
GAL
|
1,333.000
|
$4.000
|
$2.500
|
$3.500
|
$3.830
|
|
|
CEM STABIL BKFL
|
CY
|
153.000
|
$80.000
|
$142.000
|
$165.000
|
$180.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
500.000
|
$25.000
|
$38.000
|
$25.000
|
$40.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,502.000
|
$220.000
|
$309.000
|
$260.000
|
$301.490
|
|
|
CL C CONC (ABUT)
|
CY
|
59.600
|
$1,000.000
|
$765.000
|
$1,100.000
|
$1,000.000
|
|
|
CL C CONC (CAP)
|
CY
|
85.600
|
$1,200.000
|
$856.000
|
$1,000.000
|
$1,000.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
27.200
|
$1,200.000
|
$1,445.000
|
$1,500.000
|
$1,000.000
|
|
|
CL C CONC (RAC-R)
|
CY
|
7.000
|
$1,500.000
|
$445.000
|
$1,900.000
|
$1,000.000
|
|
|
REINF CONC SLAB
|
SF
|
16,377.000
|
$18.000
|
$17.850
|
$20.000
|
$22.000
|
|
|
PRESTR CONC GIRDER (TX40)
|
LF
|
2,121.000
|
$160.000
|
$150.000
|
$175.000
|
$140.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
45.000
|
$400.000
|
$500.000
|
$450.000
|
$400.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
251.000
|
$150.000
|
$138.000
|
$150.000
|
$157.500
|
|
|
RAIL (TY T552)
|
LF
|
818.000
|
$120.000
|
$75.700
|
$75.000
|
$72.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
136.000
|
$95.000
|
$135.000
|
$100.000
|
$110.000
|
|
|
CONC BOX CULVERT (10FT X 11 FT)(EXTEND)
|
LF
|
48.000
|
$1,100.000
|
$965.000
|
$1,700.000
|
$1,200.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
38.000
|
$90.000
|
$50.000
|
$74.000
|
$85.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
92.000
|
$100.000
|
$55.000
|
$80.000
|
$100.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
104.000
|
$110.000
|
$65.000
|
$85.000
|
$140.000
|
|
|
WINGWALL (FW - 0) (HW=13 FT)
|
EA
|
1.000
|
$35,000.000
|
$21,650.000
|
$32,000.000
|
$25,000.000
|
|
|
WINGWALL (FW - 0) (HW=14 FT)
|
EA
|
1.000
|
$40,000.000
|
$24,650.000
|
$48,000.000
|
$30,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,500.000
|
$1,240.000
|
$1,500.000
|
$1,800.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,600.000
|
$1,100.000
|
$1,800.000
|
$2,200.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,800.000
|
$2,850.000
|
$2,900.000
|
$4,200.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$70,000.000
|
$84,000.000
|
$85,000.000
|
$80,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$285,000.000
|
$325,000.000
|
$320,000.000
|
$366,703.250
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
13.000
|
$3,500.000
|
$2,550.000
|
$5,000.000
|
$5,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
50.000
|
$35.000
|
$31.400
|
$46.000
|
$46.100
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
50.000
|
$10.000
|
$18.000
|
$15.000
|
$15.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,454.000
|
$3.000
|
$3.500
|
$2.600
|
$2.600
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,454.000
|
$1.000
|
$1.200
|
$0.500
|
$0.500
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
780.000
|
$35.000
|
$16.400
|
$23.000
|
$20.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
570.000
|
$5.000
|
$9.100
|
$15.000
|
$20.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
780.000
|
$10.000
|
$14.800
|
$14.000
|
$20.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
390.000
|
$25.000
|
$18.600
|
$33.000
|
$39.420
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
6,044.000
|
$0.250
|
$0.900
|
$1.300
|
$1.310
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
3,022.000
|
$0.250
|
$1.400
|
$2.400
|
$2.080
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,075.000
|
$25.000
|
$23.000
|
$22.000
|
$21.630
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
10.000
|
$1,850.000
|
$2,355.000
|
$1,700.000
|
$2,019.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,185.000
|
$2.500
|
$4.150
|
$2.000
|
$2.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
4.000
|
$145.000
|
$130.000
|
$175.000
|
$175.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,800.000
|
$2,565.000
|
$2,900.000
|
$2,872.000
|
|
|
GUARDRAIL END TREATMENT (MOVE & RESET)
|
EA
|
4.000
|
$1,650.000
|
$1,035.000
|
$1,600.000
|
$1,600.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,500.000
|
$715.000
|
$1,500.000
|
$1,500.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$750.000
|
$470.000
|
$750.000
|
$750.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$8,500.000
|
$7,410.000
|
$7,300.000
|
$7,250.000
|
|
|
WIRE FENCE (TY A)
|
LF
|
339.000
|
$15.000
|
$29.000
|
$20.000
|
$20.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
3.000
|
$600.000
|
$670.000
|
$650.000
|
$649.130
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
2.000
|
$400.000
|
$670.000
|
$430.000
|
$426.630
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
5.000
|
$85.000
|
$155.000
|
$100.000
|
$150.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
58.000
|
$15.000
|
$15.500
|
$18.000
|
$18.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
4.000
|
$50.000
|
$105.000
|
$53.000
|
$52.950
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
14.000
|
$20.000
|
$105.000
|
$20.000
|
$20.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
67.000
|
$22.000
|
$15.500
|
$22.000
|
$21.950
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
9,175.000
|
$1.000
|
$0.650
|
$0.610
|
$0.600
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
11,954.000
|
$1.000
|
$0.650
|
$0.610
|
$0.600
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
600.000
|
$2.000
|
$2.850
|
$1.000
|
$1.780
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
6,044.000
|
$0.750
|
$0.950
|
$0.910
|
$0.900
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
540.000
|
$0.750
|
$1.000
|
$0.960
|
$0.950
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
3,740.000
|
$0.750
|
$0.950
|
$0.910
|
$0.900
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
76.000
|
$5.000
|
$7.750
|
$7.600
|
$7.500
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$8,500.000
|
$7,000.000
|
$7,500.000
|
$7,656.650
|
|
|
TMA (STATIONARY)
|
DAY
|
20.000
|
$300.000
|
$400.000
|
$250.000
|
$306.270
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
20.000
|
$400.000
|
$400.000
|
$250.000
|
$510.440
|
|
Totals: |
$3,319,910.000
|
$3,351,389.940
|
$3,585,315.730
|
$3,786,659.970
|