COLORADO US 90 (0026-04-048)

Items: 45

County: COLORADO
Length: 5.5640 MILES
Highway: US 90
District: YOAKUM
Control Number: 0026-04-048
DBE Goal: 0.0%
Project: C 26-4-48
Guaranty: $61,000.00
Time: 270 WORKING DAYS
Engineer's Estimate: $3,046,350.50
Date: 09/06/2024 (1 year ago)
Contract Number: 9243218
Type: BICYCLE AND PEDESTRIAN IMPROVEMENTS
Project ID: A00183447
Project Description: INSTALL SIDEWALKS
Mail/Deliver Bids To: N/A
RYAN SIMPER
PAUL RODRIGUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$3,046,350.50
1
$2,778,932.59
Over/Under Est: -8.78% -$267,417.91
$2,994,307.48
Over/Under Est: -1.71% -$52,043.02
Amt Left: 7.75% $215,374.89
$3,041,973.60
Over/Under Est: -0.14% -$4,376.90
Amt Left: 9.47% $263,041.01
Delta: -1.59% -$47,666.12
Over/Under Est: 6.02% $183,446.62
Amt Left: 16.22% $450,864.53
Delta: -6.17% -$187,823.52
$3,414,866.00
Over/Under Est: 12.1% $368,515.50
Amt Left: 22.88% $635,933.41
Delta: -5.73% -$185,068.88
Subcontractor Percentage Amount
VACA UNDERGROUND UTILITIES INC 6.12% $170,070.67
RARE EARTH LANDSCAPE SOLUTIONS LLC 2.51% $69,751.21
AWP SAFETY 1.39% $38,627.16
D. I. J. CONSTRUCTION, INC. 1.14% $31,679.83
INTERSTATE BARRICADES & MARKINGS, INC. 0.65% $18,063.06
Total: 11.81% $328,191.93

Bid Items & Bid Tabulations

45 Total 0 of 45
COLORADO  |  US 90  |  YOAKUM  |  0026-04-048  |  09/06/2024  |  $3,046,350.50  |  C 26-4-48  |  BICYCLE AND PEDESTRIAN IMPRVS  |  270 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
TI-ZACK CONCRETE, LLC
DIGG COMMERCIAL, LLC
PROJECT ALLIED RESOURCES, LLC
FNH CONSTRUCTION, LLC
PREPARING ROW(TREE)(12" TO 24" DIA)
EA 2.000 $3,000.000 $650.000 $2,508.000 $2,500.000 $3,020.000 $5,000.000
REMOVING CONC (DRIVEWAYS)
SY 2,547.000 $25.000 $25.000 $33.480 $25.000 $16.600 $20.000
REMOVING CONC (CURB)
LF 361.000 $14.000 $12.500 $11.050 $15.000 $6.300 $20.000
REMOVING CONC (CURB AND GUTTER)
LF 1,766.000 $23.000 $14.000 $9.040 $25.000 $7.800 $20.000
REMOVING CONC (MISC)
SY 86.000 $30.000 $50.000 $28.770 $77.000 $20.300 $20.000
EXCAVATION (ROADWAY)
CY 167.000 $11.000 $35.000 $47.780 $32.000 $36.500 $20.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 928.000 $27.000 $45.000 $8.600 $67.000 $63.000 $50.000
BLOCK SODDING
SY 10,744.000 $8.000 $7.150 $3.570 $9.000 $8.300 $6.000
VEGETATIVE WATERING
MG 90.500 $25.000 $0.010 $30.450 $120.000 $85.000 $50.000
DRILL SHAFT (RDWY ILL POLE) (24 IN)
LF 84.000 $230.000 $302.500 $235.120 $299.000 $320.000 $285.000
RIPRAP (CONC)(5 IN)
CY 19.000 $850.000 $650.000 $898.920 $788.000 $1,070.000 $650.000
RAIL (HANDRAIL)(TY F)
LF 34.000 $275.000 $270.000 $257.760 $210.000 $602.000 $185.000
MOBILIZATION
LS 1.000 $350,000.000 $189,500.000 $305,221.050 $250,000.000 $71,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 18.000 $4,000.000 $4,500.000 $1,575.000 $8,000.000 $5,900.000 $12,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,200.000 $4.000 $3.500 $0.110 $30.000 $6.400 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,200.000 $1.000 $1.000 $0.110 $2.000 $1.930 $2.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 600.000 $7.000 $0.010 $0.110 $30.000 $8.800 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 600.000 $2.000 $0.010 $0.110 $2.000 $2.780 $9.000
CONC CURB (TY II)
LF 4.000 $42.000 $35.000 $69.940 $120.000 $26.500 $55.000
CONC CURB & GUTTER (TY II)
LF 396.000 $45.000 $42.140 $69.940 $80.000 $55.000 $75.000
CONC CURB (TY C1)
LF 53.000 $300.000 $122.420 $213.500 $145.000 $111.000 $85.000
DRIVEWAYS (CONC)
SY 3,930.000 $120.000 $156.000 $120.510 $100.000 $153.000 $85.000
CONC SIDEWALKS (5")
SY 12,997.000 $100.000 $80.820 $118.830 $85.000 $102.000 $65.000
CONC SIDEWALKS (6")
SY 33.000 $120.000 $120.570 $128.310 $300.000 $118.000 $85.000
CURB RAMPS (TY 1)
SY 135.000 $200.000 $296.820 $128.310 $270.000 $190.000 $700.000
CURB RAMPS (TY 3)
SY 14.000 $200.000 $144.350 $128.310 $370.000 $190.000 $700.000
CURB RAMPS (TY 7)
SY 667.000 $180.000 $221.710 $128.310 $237.000 $190.000 $700.000
CURB RAMPS (TY 10)
SY 492.000 $190.000 $184.460 $128.050 $250.000 $190.000 $700.000
CONC SIDEWALKS (SPECIAL) (TYPE A)
SY 12.000 $550.000 $550.000 $1,348.380 $650.000 $12,500.000 $100.000
RELOCATE EXISTING MAILBOX
EA 4.000 $250.000 $291.500 $472.500 $520.000 $775.000 $1,500.000
CONDT (PVC) (SCH 80) (2")
LF 1,145.000 $33.000 $14.850 $15.400 $20.910 $22.500 $20.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 903.000 $45.000 $17.600 $24.570 $29.540 $31.700 $50.000
ELEC CONDR (NO.12) INSULATED
LF 3,516.000 $3.000 $2.200 $1.900 $1.360 $1.460 $3.000
ELEC CONDR (NO.10) INSULATED
LF 3,438.000 $2.000 $2.200 $1.970 $1.560 $1.670 $3.000
GROUND BOX TY A (122311)W/APRON
EA 13.000 $1,500.000 $1,540.000 $1,753.470 $1,772.150 $1,900.000 $1,500.000
ELC SRV TY D 120/240 060(NS)AL(E)SP(U)
EA 2.000 $5,000.000 $8,250.000 $7,218.650 $11,225.970 $12,100.000 $9,500.000
IN SM RD SN SUP&AM TYTWT(1)UA(P)
EA 2.000 $950.000 $522.500 $157.500 $762.000 $976.000 $1,500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 36.000 $700.000 $588.500 $157.500 $701.000 $944.000 $1,150.000
RELOCATE SM RD SN SUP&AM TY S80
EA 5.000 $800.000 $621.500 $157.500 $735.000 $1,090.000 $1,150.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 31.000 $450.000 $511.500 $157.500 $609.000 $813.000 $1,150.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 1,307.000 $22.000 $22.000 $17.220 $12.000 $39.200 $20.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $250.000 $385.000 $304.500 $276.000 $389.000 $250.000
ELIM EXT PAV MRK & MRKS (12")
LF 1,840.000 $2.250 $2.530 $3.150 $2.530 $7.300 $8.000
TMA (STATIONARY)
DAY 64.000 $230.000 $250.000 $1.050 $1,560.000 $633.000 $250.000
PEDESTRIAN ILLUMINATION
EA 14.000 $4,000.000 $5,500.000 $4,705.280 $6,162.850 $6,620.000 $10,000.000
Totals: $3,046,350.500 $2,778,932.595 $2,994,307.485 $3,041,973.600 $3,229,797.120 $3,414,866.000