Job Info for 6460-92-001

County: COLLIN Highway: US0075 Date: 06/06/2024 (5 months ago) Changed Engineer's Estimate: $818,083 Control Number: 6460-92-001
Project: RMC - 646092001 District: DALLAS Time: 70 W Type: FULL DEPTH CONCRETE REPAIR
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $818,082.61
O. TREVINO CONSTRUCTION, LLC   $650,985.00 1
-20.43% | -$167,097.61
GARRET SHIELDS INFRASTRUCTURE   $663,500.00 2
-18.9% | -$154,582.61
1.92% | $12,515.00
ICOS MANAGEMENT, LLC   $791,755.00 3
-3.22% | -$26,327.61
21.62% | $140,770.00
19.33% | $128,255.00
STX CIVIL   $849,450.00 4
3.83% | $31,367.39
30.49% | $198,465.00
7.29% | $57,695.00
FNH CONSTRUCTION, LLC   $1,068,750.00 5
30.64% | $250,667.39
64.17% | $417,765.00
25.82% | $219,300.00
ROY JORGENSEN ASSOCIATES, INC.   $1,239,820.00 6
51.55% | $421,737.39
90.45% | $588,835.00
16.01% | $171,070.00

Bid Items

Items: 12, 0 filtered
COLLIN US0075  |  DALLAS  |  6460-92-001  |  06/06/2024  |  $818,083  |  RMC - 646092001  |  FULL DEPTH CONC REPAIR  |  70 W
Item code Description Unit Quantity Engineer's Estimate O. TREVINO CONSTRUCTION, LLC GARRET SHIELDS INFRASTRUCTURE ICOS MANAGEMENT, LLC STX CIVIL FNH CONSTRUCTION, LLC ROY JORGENSEN ASSOCIATES, INC.
104 6021 REMOVING CONC (CURB) LF 300.000 $20.000 $13.000 $30.000 $32.000 $30.000 $30.000 $15.000
104 6022 REMOVING CONC (CURB AND GUTTER) LF 150.000 $25.000 $18.000 $30.000 $43.000 $30.000 $30.000 $25.000
361 6069 FULL-DEPTH REPAIR CPCD (11"-13") SY 100.000 $432.000 $486.500 $350.000 $428.000 $410.000 $650.000 $650.000
361 6084 FULL DEPTH REPAIR CPCD (8"-10" SY 1,600.000 $330.000 $275.000 $300.000 $334.000 $395.000 $450.000 $625.000
429 6004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) SF 50.000 $148.000 $200.000 $200.000 $428.000 $230.000 $500.000 $180.000
429 6006 CONC STR REPR(RAPID DECK REP(FULL DPT)) SF 50.000 $277.000 $225.000 $300.000 $535.000 $320.000 $400.000 $250.000
500 6001 MOBILIZATION LS 1.000 $67,548.110 $62,000.000 $40,000.000 $65,000.000 $67,000.000 $100,000.000 $70,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $4,000.000 $3,677.000 $5,000.000 $1.000 $3,500.000 $15,000.000 $8,000.000
529 6002 CONC CURB (TY II) LF 300.000 $253.670 $65.000 $40.000 $54.000 $45.000 $55.000 $50.000
529 6008 CONC CURB & GUTTER (TY II) LF 150.000 $92.670 $80.000 $40.000 $86.000 $60.000 $75.000 $80.000
720 6003 SPALLING REPAIR (POLYMERIC) (SEMIRIGID) GAL 100.000 $103.330 $100.000 $60.000 $370.000 $85.000 $50.000 $80.000
6185 6002 TMA (STATIONARY) DAY 70.000 $400.000 $180.000 $300.000 $275.000 $285.000 $250.000 $1.000
Totals: $818,082.61 $650,985.00 $663,500.00 $791,755.00 $849,450.00 $1,068,750.00 $1,239,820.00