Show Job Controls
Bid Cobra

COLLIN FM0455 (6399-40-001)

Items: 24

County: COLLIN
Length: N/A
Highway: FM0455
District: DALLAS
Control Number: 6399-40-001
DBE Goal: N/A
Project: RMC - 639940001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $168,948.00
Date: 08/09/2022 (3 years ago)
Contract Number: N/A
Type: CULVERT EXTENSION & CROSS DRAINAGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (1)
E
Engineer's Estimate
$168,948.00
$265,824.00
Over/Under Est: 57.34% $96,876.00

Bid Items & Bid Tabulations

24 Total 0 of 24
COLLIN  |  FM0455  |  DALLAS  |  6399-40-001  |  08/09/2022  |  $168,948.00  |  RMC - 639940001  |  CULVERT EXTENSION & CROSS DRAINAGE  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TALBRAN ENTERPRISES LLC
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 167.000 $35.000 $33.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 765.000 $1.000 $1.000
VEGETATIVE WATERING
MG 53.000 $1.000 $1.000
CEM STABIL BKFL
CY 49.000 $300.000 $440.000
CUT & RESTORE ASPH PAVING
SY 64.000 $190.000 $352.000
FLOWABLE BACKFILL
CY 13.000 $600.000 $660.000
TRENCH EXCAVATION PROTECTION
LF 69.000 $10.000 $1.000
RIPRAP (STONE COMMON)(GROUT)(12 IN)
CY 129.000 $200.000 $418.000
RC PIPE (CL III)(36 IN)
LF 125.000 $190.000 $308.000
RC PIPE (CL III)(54 IN)
LF 8.000 $900.000 $1,100.000
HEADWALL (CH - PW - 0) (DIA= 54 IN)
EA 1.000 $8,000.000 $22,000.000
HEADWALL (CH - PW - S) (DIA= 36 IN)
EA 2.000 $7,400.000 $19,800.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 2.000 $5,900.000 $9,900.000
REMOV STR (SET)
EA 3.000 $350.000 $2,200.000
REMOV STR (HEADWALL)
EA 2.000 $1,000.000 $2,200.000
REMOV STR (PIPE)
LF 140.000 $40.000 $22.000
MOBILIZATION
LS 1.000 $21,515.000 $2,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $2,000.000 $500.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 6.000 $8.500 $60.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 44.000 $2.000 $5.000
REFL PAV MRK TY II (W) 24" (SLD)
LF 15.000 $10.000 $5.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 57.000 $2.000 $5.000
TREE TRIMMING / BRUSH REMOVAL(CHANNELS)
AC 0.128 $1,500.000 $22,000.000
TMA (STATIONARY)
DAY 33.000 $25.000 $100.000
Totals: $168,948.000 $265,824.000