County: COLLIN Highway: US0075 Date: 06/03/2021 (3 years ago) Engineer's Estimate: $592,832 Control Number: 6377-10-001
Project: RMC - 637710001 District: DALLAS Time: 365 CALENDAR DAYS Type: REFLECTIVE PAVEMENT MARKINGS (LONG LINE)

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $592,832.00
STRIPE-A-ZONE, INC.   $432,199.00 1
-27.1% | -$160,633.00
PMI PAVEMENT MARKING, LLC   $579,440.00 2
-2.26% | -$13,392.00
34.07% | $147,241.00
STRIPING TECHNOLOGY, L.P.   $593,925.00 3
0.18% | $1,093.00
37.42% | $161,726.00
2.50% | $14,485.00
TOTAL HIGHWAY MAINTENANCE, LLC   $901,425.00 4
52.05% | $308,593.00
108.57% | $469,226.00
51.77% | $307,500.00
TRP CONSTRUCTION GROUP, LLC   $946,502.00 5
59.66% | $353,670.00
119% | $514,303.00
5.00% | $45,077.00

Bid Items

Items: 39, 0 filtered
COLLIN US0075  |  DALLAS  |  6377-10-001  |  06/03/2021  |  $592,832  |  RMC - 637710001  |  REFL PAVMT MRK (LONG LINE)  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPE-A-ZONE, INC. PMI PAVEMENT MARKING, LLC STRIPING TECHNOLOGY, L.P. TOTAL HIGHWAY MAINTENANCE, LLC TRP CONSTRUCTION GROUP, LLC
500 6001 MOBILIZATION LS 1.000 $43,400.000 $1.000 $7,000.000 $5,000.000 $80,000.000 $10,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $1,600.000 $1.000 $2,000.000 $5,000.000 $7,500.000 $2,200.000
666 6006 REFL PAV MRK TY I (W)4"(DOT)(100MIL) LF 1,000.000 $1.450 $1.000 $0.950 $1.000 $2.000 $4.000
666 6018 REFL PAV MRK TY I (W)6"(DOT)(100MIL) LF 1,000.000 $1.450 $1.000 $0.950 $1.000 $2.000 $4.000
666 6025 REFL PAV MRK TY I (W)8"(BRK)(060MIL) LF 1,000.000 $0.500 $0.750 $0.950 $1.000 $2.000 $4.000
666 6027 REFL PAV MRK TY I (W)8"(BRK)(100MIL) LF 1,000.000 $0.900 $0.750 $0.950 $1.000 $2.000 $4.000
666 6030 REFL PAV MRK TY I (W)8"(DOT)(100MIL) LF 1,000.000 $1.560 $0.850 $1.250 $1.000 $2.000 $4.000
666 6034 REFL PAV MRK TY I (W)8"(SLD)(060MIL) LF 1,000.000 $0.600 $0.650 $0.950 $1.000 $2.000 $4.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 1,000.000 $1.250 $1.000 $1.160 $1.000 $2.000 $4.000
666 6040 REFL PAV MRK TY I (W)12"(SLD)(060MIL) LF 1,000.000 $2.820 $3.750 $1.170 $3.000 $4.000 $15.000
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 500.000 $2.500 $4.000 $2.150 $3.000 $4.000 $20.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 500.000 $5.850 $6.250 $2.150 $5.000 $10.000 $30.000
666 6138 REFL PAV MRK TY I (Y)8"(SLD)(100MIL) LF 500.000 $1.000 $1.000 $1.850 $5.000 $2.000 $4.000
666 6141 REFL PAV MRK TY I (Y)12"(SLD)(100MIL) LF 500.000 $3.500 $4.000 $2.150 $3.000 $4.000 $20.000
666 6224 PAVEMENT SEALER 4" LF 341,000.000 $0.140 $0.160 $0.140 $0.130 $0.150 $0.200
666 6225 PAVEMENT SEALER 6" LF 126,000.000 $0.220 $0.180 $0.150 $0.200 $0.200 $0.250
666 6226 PAVEMENT SEALER 8" LF 3,500.000 $0.350 $0.200 $0.200 $0.300 $0.300 $0.300
666 6228 PAVEMENT SEALER 12" LF 2,000.000 $1.000 $0.350 $0.350 $1.250 $1.000 $0.600
666 6230 PAVEMENT SEALER 24" LF 500.000 $1.910 $0.600 $0.700 $3.000 $2.000 $1.200
666 6298 RE PM W/RET REQ TY I (W)4"(BRK)(060MIL) LF 11,500.000 $0.310 $0.260 $0.550 $0.250 $0.450 $0.310
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 1,000.000 $0.360 $0.320 $0.950 $0.320 $1.000 $0.450
666 6301 RE PM W/RET REQ TY I (W)4"(SLD)(060MIL) LF 5,700.000 $0.360 $0.220 $0.550 $0.250 $0.400 $0.310
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 171,000.000 $0.330 $0.300 $0.470 $0.270 $0.500 $0.450
666 6304 RE PM W/RET REQ TY I (W)6"(BRK)(060MIL) LF 8,500.000 $0.390 $0.340 $0.700 $0.550 $1.000 $0.600
666 6306 RE PM W/RET REQ TY I (W)6"(BRK)(100MIL) LF 126,000.000 $0.530 $0.420 $0.700 $0.600 $0.550 $0.600
666 6313 RE PM W/RET REQ TY I (Y)4"(SLD)(060MIL) LF 57,000.000 $0.250 $0.220 $0.500 $0.250 $0.360 $0.310
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 171,000.000 $0.320 $0.300 $0.470 $0.270 $0.500 $0.450
666 6350 REFL PAV MRK TY I (W)12"(DOT)(100MIL) LF 1,000.000 $2.370 $1.250 $2.450 $3.000 $4.000 $10.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 341,000.000 $0.370 $0.270 $0.300 $0.540 $0.500 $0.500
677 6002 ELIM EXT PAV MRK & MRKS (6") LF 126,000.000 $0.550 $0.340 $0.320 $0.580 $0.650 $0.600
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 3,500.000 $0.750 $0.750 $0.520 $0.700 $1.000 $1.000
677 6005 ELIM EXT PAV MRK & MRKS (12") LF 2,000.000 $1.260 $2.000 $0.700 $2.250 $2.000 $4.000
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 1,000.000 $2.750 $3.000 $1.450 $3.250 $4.000 $8.000
678 6001 PAV SURF PREP FOR MRK (4") LF 341,000.000 $0.050 $0.020 $0.060 $0.010 $0.100 $0.300
678 6002 PAV SURF PREP FOR MRK (6") LF 126,000.000 $0.090 $0.040 $0.080 $0.030 $0.200 $0.300
678 6004 PAV SURF PREP FOR MRK (8") LF 3,500.000 $0.200 $0.120 $0.280 $0.100 $0.300 $0.400
678 6006 PAV SURF PREP FOR MRK (12") LF 2,000.000 $0.400 $0.500 $0.480 $0.200 $0.500 $10.000
678 6008 PAV SURF PREP FOR MRK (24") LF 1,000.000 $0.340 $1.000 $0.950 $0.500 $1.000 $20.000
6185 6005 TMA (MOBILE OPERATION) DAY 300.000 $30.000 $1.000 $22.000 $20.000 $250.000 $100.000
Totals: $592,832.00 $432,199.00 $579,440.00 $593,925.00 $901,425.00 $946,502.00