Job Info for 0816-05-025

County: COLLIN Highway: FM 2862 Date: 06/02/2023 (1 year ago) Engineer's Estimate: $5,851,894 Control Number: 0816-05-025
Project: STP 2023(916)HES District: DALLAS Time: 230 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $5,851,893.90
FOUTSCO PAVING COMPANY, LLC   $7,607,273.37 1
30% | $1,755,379.47
FNH CONSTRUCTION, LLC   $8,170,885.50 2
39.63% | $2,318,991.60
7.41% | $563,612.13
ED BELL CONSTRUCTION COMPANY   $8,451,825.97 3
44.43% | $2,599,932.07
11.1% | $844,552.60
3.44% | $280,940.47
Subcontractor Percentage Amount
LOLLAR CONSTRUCTION GROUP LLC 17.11% $1,301,604.47
KITCHING & CO., LLC 4.42% $336,241.48
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 2.01% $152,906.19
MARCOMS CONSTRUCTION LLC 1.32% $100,416.01
LINEAR TRAFFIC MARKINGS LLC 0.91% $69,226.19
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.55% $41,840.00
FORTSON CONTRACTING, INC. 0.43% $32,711.28
KING GEORGE TRAFFIC SOLUTIONS LLC 0.21% $15,975.27
WEST TEXAS ROCK RESOURCES, LLC 0.10% $7,607.27
Total: 27.06% $2,058,528.16

Bid Items

Items: 92, 0 filtered
COLLIN FM 2862  |  DALLAS  |  0816-05-025  |  06/02/2023  |  $5,851,894  |  STP 2023(916)HES  |  HAZARD ELIM & SAFETY  |  230 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate FOUTSCO PAVING COMPANY, LLC FNH CONSTRUCTION, LLC ED BELL CONSTRUCTION COMPANY
100 6002 PREPARING ROW STA 240.050 $600.000 $100.000 $2,415.000 $2,100.000
104 6015 REMOVING CONC (SIDEWALKS) SY 22.000 $12.000 $25.000 $20.000 $63.000
104 6017 REMOVING CONC (DRIVEWAYS) SY 749.000 $13.000 $25.000 $20.000 $21.000
110 6001 EXCAVATION (ROADWAY) CY 4,451.000 $10.000 $30.000 $20.000 $21.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 9,369.000 $10.000 $30.000 $30.000 $21.000
134 6004 BACKFILL (TY A OR B) STA 240.050 $215.000 $200.000 $450.000 $450.000
150 6001 BLADING STA 240.050 $205.000 $50.000 $250.000 $900.000
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 149,554.000 $0.100 $0.150 $0.500 $0.220
164 6051 DRILL SEED (TEMP)(WARM OR COOL) SY 149,554.000 $0.100 $0.010 $0.500 $0.200
168 6001 VEGETATIVE WATERING MG 44,495.000 $2.500 $0.010 $10.000 $1.000
351 6006 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 803.000 $143.000 $150.000 $120.000 $136.820
354 6045 PLANE ASPH CONC PAV (2") SY 67,013.000 $3.150 $1.500 $5.000 $4.000
400 6005 CEM STABIL BKFL CY 366.000 $190.000 $200.000 $350.000 $185.000
400 6006 CUT & RESTORING PAV SY 323.000 $150.000 $150.000 $200.000 $155.000
401 6001 FLOWABLE BACKFILL CY 4.000 $145.000 $220.000 $350.000 $1,250.000
402 6001 TRENCH EXCAVATION PROTECTION LF 154.000 $3.000 $24.000 $10.000 $10.000
432 6003 RIPRAP (CONC)(6 IN) CY 1.000 $600.000 $1,500.000 $2,000.000 $2,100.000
432 6024 RIPRAP (STONE COMMON)(DRY)(12 IN) CY 158.000 $150.000 $175.000 $165.000 $250.000
432 6026 RIPRAP (STONE COMMON)(DRY)(18 IN) CY 592.000 $200.000 $166.000 $185.000 $215.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 51.000 $41.000 $550.000 $550.000 $800.000
462 6021 CONC BOX CULV (8 FT X 6 FT) LF 58.000 $405.000 $2,000.000 $1,500.000 $840.000
464 6003 RC PIPE (CL III)(18 IN) LF 1,846.000 $44.500 $86.000 $85.000 $84.000
464 6005 RC PIPE (CL III)(24 IN) LF 658.000 $75.000 $121.000 $105.000 $126.000
464 6007 RC PIPE (CL III)(30 IN) LF 195.000 $90.000 $165.000 $135.000 $157.500
464 6008 RC PIPE (CL III)(36 IN) LF 67.000 $120.000 $211.000 $200.000 $262.500
464 6009 RC PIPE (CL III)(42 IN) LF 108.000 $150.000 $300.000 $300.000 $315.000
464 6010 RC PIPE (CL III)(48 IN) LF 9.000 $280.000 $365.000 $350.000 $840.000
464 6018 RC PIPE (CL IV)(24 IN) LF 205.000 $110.000 $256.000 $135.000 $157.500
466 6099 HEADWALL (CH - PW - 0) (DIA= 30 IN) EA 4.000 $5,500.000 $8,100.000 $6,500.000 $9,400.000
466 6101 HEADWALL (CH - PW - 0) (DIA= 36 IN) EA 4.000 $5,000.000 $11,000.000 $7,500.000 $11,550.000
466 6102 HEADWALL (CH - PW - 0) (DIA= 42 IN) EA 2.000 $9,000.000 $17,000.000 $11,500.000 $13,650.000
466 6103 HEADWALL (CH - PW - 0) (DIA= 48 IN) EA 2.000 $10,166.670 $22,000.000 $15,000.000 $15,750.000
466 6172 WINGWALL (PW - 1) (HW=11 FT) EA 1.000 $72,000.000 $38,000.000 $50,000.000 $73,500.000
466 6173 WINGWALL (PW - 1) (HW=12 FT) EA 1.000 $87,000.000 $41,000.000 $60,000.000 $84,000.000
467 6359 SET (TY II) (18 IN) (RCP) (4: 1) (P) EA 4.000 $600.000 $1,200.000 $1,000.000 $840.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 116.000 $660.000 $1,000.000 $850.000 $1,155.000
467 6388 SET (TY II) (24 IN) (RCP) (3: 1) (C) EA 14.000 $787.500 $1,400.000 $1,250.000 $945.000
467 6391 SET (TY II) (24 IN) (RCP) (4: 1) (P) EA 2.000 $775.000 $2,500.000 $1,350.000 $1,050.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 30.000 $1,000.000 $1,500.000 $1,450.000 $1,260.000
467 6423 SET (TY II) (30 IN) (RCP) (6: 1) (P) EA 8.000 $2,525.160 $3,500.000 $2,350.000 $2,100.000
496 6004 REMOV STR (SET) EA 20.000 $1,100.000 $600.000 $500.000 $210.000
496 6007 REMOV STR (PIPE) LF 2,611.000 $10.000 $10.000 $50.000 $15.750
500 6001 MOBILIZATION LS 1.000 $512,809.850 $660,000.000 $700,000.000 $862,500.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 14.000 $12,000.000 $35,000.000 $8,500.000 $31,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 1,670.000 $28.000 $15.000 $30.000 $47.250
506 6011 ROCK FILTER DAMS (REMOVE) LF 1,670.000 $7.000 $5.000 $15.000 $23.100
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 172.000 $23.000 $10.000 $40.000 $15.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 172.000 $8.000 $2.000 $20.000 $7.500
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 22,370.000 $2.000 $1.000 $4.000 $2.100
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 22,370.000 $0.500 $0.500 $2.000 $0.530
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,584.000 $4.000 $2.000 $18.000 $4.730
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,584.000 $0.750 $1.000 $9.000 $2.100
530 6004 DRIVEWAYS (CONC) SY 919.000 $91.670 $85.000 $85.000 $126.000
530 6005 DRIVEWAYS (ACP) SY 5,895.000 $45.000 $90.000 $45.000 $85.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 37,009.000 $0.350 $0.150 $0.500 $0.250
533 6002 RUMBLE STRIPS (CENTERLINE) LF 18,183.000 $0.350 $0.150 $0.500 $0.250
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 312.500 $21.250 $20.000 $28.000 $26.560
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $1,601.360 $1,800.000 $1,850.000 $3,495.720
542 6001 REMOVE METAL BEAM GUARD FENCE LF 180.000 $2.350 $3.000 $3.000 $5.250
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 4.000 $175.000 $250.000 $500.000 $262.500
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 6.000 $2,524.120 $2,800.000 $3,250.000 $2,966.250
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 5.000 $375.000 $250.000 $1,000.000 $262.500
560 6011 MAILBOX INSTALL-S (TWW-POST) TY 4 EA 38.000 $235.000 $200.000 $850.000 $210.000
560 6012 MAILBOX INSTALL-D (TWW-POST) TY 4 EA 2.000 $300.000 $250.000 $850.000 $262.500
560 6013 MAILBOX INSTALL-M (TWW-POST) TY 4 EA 3.000 $718.000 $500.000 $850.000 $525.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 123.000 $603.250 $575.000 $800.000 $612.150
644 6002 IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM) EA 2.000 $625.000 $690.000 $1,120.000 $913.500
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 1.000 $533.000 $715.000 $1,120.000 $829.500
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 2.000 $727.290 $895.000 $1,120.000 $945.000
644 6036 IN SM RD SN SUP&AM TYS80(1)SA(U-BM) EA 1.000 $1,200.000 $1,100.000 $1,120.000 $1,050.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 17.000 $27.000 $22.000 $100.000 $47.250
658 6099 INSTL OM ASSM (OM-2Z)(WFLX)GND EA 28.000 $19.000 $70.000 $100.000 $57.750
662 6032 WK ZN PAV MRK NON-REMOV (Y)4"(BRK) LF 1,181.000 $0.350 $0.400 $1.000 $0.420
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 41,955.000 $0.400 $0.260 $0.350 $0.270
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 2,454.000 $1.000 $1.000 $4.000 $5.250
666 6018 REFL PAV MRK TY I (W)6"(DOT)(100MIL) LF 96.000 $2.000 $2.000 $6.000 $2.100
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 44.000 $3.460 $5.000 $6.000 $5.250
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 268.000 $6.500 $7.000 $20.000 $7.350
666 6196 REFL PAV MRK TY II (W) (RR XING) EA 2.000 $375.000 $300.000 $1,000.000 $315.000
666 6225 PAVEMENT SEALER 6" LF 2,056.000 $0.450 $0.560 $1.000 $0.590
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 47,967.000 $0.520 $0.560 $0.750 $0.590
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 1,181.000 $0.950 $0.600 $1.000 $0.630
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 41,955.000 $0.860 $0.560 $0.750 $0.590
672 6009 REFL PAV MRKR TY II-A-A EA 589.000 $4.130 $4.000 $6.000 $4.200
678 6002 PAV SURF PREP FOR MRK (6") LF 2,056.000 $0.450 $0.250 $1.000 $0.260
685 6005 RELOCT RDSD FLSH BCN AM (SOLAR PWRD) EA 2.000 $4,000.000 $4,000.000 $15,000.000 $7,500.000
3077 6001 SP MIXES SP-B PG64-22 TON 10,566.000 $135.000 $168.000 $130.000 $157.500
3077 6013 SP MIXES SP-C SAC-B PG64-22 TON 9,551.000 $120.000 $169.000 $145.000 $147.000
3077 6075 TACK COAT GAL 8,897.000 $4.170 $12.000 $6.000 $3.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $10,000.000 $23,000.000 $16,500.000 $15,000.000
6185 6002 TMA (STATIONARY) DAY 200.000 $130.000 $1.000 $250.000 $165.000
6185 6003 TMA (MOBILE OPERATION) HR 200.000 $125.000 $1.000 $65.000 $75.000
Totals: $5,851,893.91 $7,607,273.37 $8,170,885.50 $8,451,825.97