Show Job Controls
Bid Cobra

COLLIN FM 544 (0619-03-061)

Items: 148

County: COLLIN
Length: N/A
Highway: FM 544
District: DALLAS
Control Number: 0619-03-061
DBE Goal: N/A
Project: CM 2022(513)
Guaranty: N/A
Time: 275 WORKING DAYS
Engineer's Estimate: $4,118,638.96
Date: 05/05/2022 (4 years ago)
Contract Number: N/A
Type: CONSTRUCT INTERSECTION IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (8)
E
Engineer's Estimate
$4,118,638.96
$4,570,584.95
Over/Under Est: 10.97% $451,945.99
$4,799,765.05
Over/Under Est: 16.54% $681,126.09
Amt Left: 5.01% $229,180.10
Over/Under Est: 26.74% $1,101,306.61
Amt Left: 14.21% $649,360.62
Delta: -8.75% -$420,180.52
Over/Under Est: 31.6% $1,301,329.27
Amt Left: 18.58% $849,383.28
Delta: -3.83% -$200,022.66
Over/Under Est: 34.25% $1,410,605.28
Amt Left: 20.97% $958,659.29
Delta: -2.02% -$109,276.01
Over/Under Est: 34.49% $1,420,638.09
Amt Left: 21.19% $968,692.10
Delta: -0.18% -$10,032.81
Over/Under Est: 42.39% $1,745,926.71
Amt Left: 28.31% $1,293,980.72
Delta: -5.87% -$325,288.62
$5,963,418.60
Over/Under Est: 44.79% $1,844,779.64
Amt Left: 30.47% $1,392,833.65
Delta: -1.69% -$98,852.93
Subcontractor Percentage Amount
2R CONSTRUCTION SERVICES LLC 20.83% $973,157.45
MICA CORPORATION 11.95% $558,292.44
REYNOLDS ASPHALT & CONSTRUCTION COMPANY 4.50% $210,235.65
FARR FOUNDATION, INC. 3.27% $152,771.24
JDS SURVEYING INC. 1.07% $49,989.36
IBCTX, LLC 1.04% $48,587.79
PRECISE TRUCKS, LLC 0.86% $40,178.37
TRP CONSTRUCTION GROUP, LLC 0.85% $39,711.18
DENALI SERVICES & TRANSPORT LLC 0.43% $20,089.18
G J SEEDING, LLC 0.38% $17,753.23
ACT SAW CUTTING & REMOVAL 0.21% $9,811.00
BARRICADES UNLIMITED 0.17% $7,942.24
DURABLE SPECIALTIES, INC. 0.00% $0.00
Total: 45.56% $2,128,519.13

Bid Items & Bid Tabulations

148 Total 0 of 148
COLLIN  |  FM 544  |  DALLAS  |  0619-03-061  |  05/05/2022  |  $4,118,638.96  |  CM 2022(513)  |  CONSTRUCT INTERS IMPRVS  |  275 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
NEW WORLD CONTRACTING, LLC
TEXAS-REYES GROUP LTD.
SEMA CONSTRUCTION, INC.
RAGLE CONSTRUCTION, INC.
ED BELL CONSTRUCTION COMPANY
D D M CONSTRUCTION CORPORATION
INDUS ROAD & BRIDGE, INC.
REBCON, LLC
PREPARING ROW
STA 20.000 $11,087.300 $18,000.000 $1,500.000 $24,235.000 $10,000.000 $11,000.000 $2,500.000 $5,000.000 $15,000.000
REMOVING CONC (PAV)
SY 1,061.000 $7.750 $7.250 $33.000 $25.000 $58.000 $25.000 $25.000 $43.000 $73.000
REMOVING CONC (MEDIANS)
SY 741.000 $16.500 $7.450 $26.000 $12.000 $25.000 $20.000 $13.000 $33.000 $75.000
REMOVING CONC (SIDEWALKS)
SY 996.000 $8.500 $5.000 $14.000 $8.000 $25.000 $20.000 $11.000 $34.000 $12.000
REMOVING CONC (DRIVEWAYS)
SY 359.000 $13.750 $20.000 $26.000 $14.000 $30.000 $20.000 $14.000 $46.000 $25.000
REMOVING CONC (CURB)
LF 5,918.000 $5.250 $9.000 $3.000 $4.000 $5.000 $2.500 $6.000 $17.000 $1.000
REMOVE STAB BASE AND ASPH PAV (6"-20")
SY 48.000 $30.000 $37.000 $50.000 $31.000 $20.000 $75.000 $30.000 $166.000 $100.000
EXCAVATION (ROADWAY)
CY 3,664.000 $9.100 $12.000 $20.000 $13.000 $50.000 $21.000 $25.000 $72.000 $38.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 2,113.000 $35.900 $32.000 $15.000 $67.000 $50.000 $63.000 $33.000 $36.000 $38.000
COMPOST MANUF TOPSOIL (4")
SY 5,068.000 $1.150 $2.000 $1.000 $3.800 $1.140 $2.000 $1.500 $3.000 $5.000
BLOCK SODDING
SY 5,068.000 $3.080 $7.200 $5.000 $4.600 $6.510 $3.150 $4.500 $8.000 $5.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 5,068.000 $0.210 $2.000 $0.500 $0.170 $0.140 $0.100 $0.300 $0.420 $0.300
VEGETATIVE WATERING
MG 1,508.000 $2.020 $25.000 $9.000 $8.000 $1.000 $1.050 $25.000 $62.000 $50.000
LIME (HYDRATED LIME (SLURRY))
TON 177.000 $185.000 $465.000 $300.000 $196.000 $201.000 $225.000 $308.000 $280.000 $221.000
LIME TRT (EXST MATL)(10")
SY 6,030.000 $4.500 $5.500 $15.000 $13.000 $20.000 $15.000 $28.000 $7.000 $14.000
CONC PVMT (CONT REINF - CRCP) (8")
SY 5,341.000 $115.000 $95.000 $129.000 $112.000 $90.000 $125.000 $125.000 $105.000 $130.000
CUT & RESTORING PAV
SY 30.000 $146.840 $95.000 $96.000 $230.000 $110.000 $525.000 $305.000 $150.000 $250.000
TRENCH EXCAVATION PROTECTION
LF 362.000 $7.560 $31.000 $2.500 $16.000 $1.000 $3.200 $4.500 $15.000 $3.300
TEMPORARY SPL SHORING
SF 5,870.000 $38.070 $35.000 $70.000 $40.000 $40.000 $29.720 $55.000 $35.000 $45.000
DRILL SHAFT (TRF SIG POLE) (48 IN)
LF 88.000 $442.300 $565.000 $461.000 $440.000 $430.000 $452.630 $450.000 $470.000 $470.000
RETAINING WALL (CAST - IN - PLACE)
SF 5,214.000 $82.000 $95.000 $121.000 $84.000 $135.000 $125.000 $171.000 $100.000 $125.000
RAIL (TY C221)
LF 514.000 $74.000 $65.000 $104.000 $156.000 $105.000 $120.000 $260.000 $165.000 $250.000
RC PIPE (CL III)(18 IN)
LF 192.000 $54.020 $120.000 $136.000 $105.000 $100.000 $152.770 $140.000 $110.000 $158.000
RC PIPE (CL III)(24 IN)
LF 106.000 $75.080 $135.000 $230.000 $140.000 $125.000 $181.370 $197.000 $140.000 $190.000
JCTBOX(COMPL)(PJB)(3FTX5FT)
EA 3.000 $3,733.330 $6,995.000 $8,271.000 $5,800.000 $6,500.000 $7,508.250 $7,950.000 $12,000.000 $7,755.000
INLET (COMPL)(PCU)(3FT)(BOTH)
EA 6.000 $5,256.000 $6,985.000 $7,437.000 $6,500.000 $6,500.000 $7,508.250 $8,100.000 $8,500.000 $7,755.000
REMOV STR (INLET)
EA 4.000 $587.000 $2,350.000 $2,170.000 $1,000.000 $750.000 $814.730 $1,200.000 $1,800.000 $842.000
REMOV STR (PIPE)
LF 48.000 $23.250 $51.000 $118.000 $180.000 $25.000 $23.430 $55.000 $52.000 $24.000
REMOV STR (RET WALL)
LF 503.000 $45.000 $92.000 $68.000 $100.000 $40.000 $125.000 $43.000 $145.000 $275.000
MOBILIZATION
LS 1.000 $313,442.000 $385,000.000 $397,000.000 $521,000.000 $540,000.000 $550,000.000 $250,000.000 $549,824.110 $573,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $13,500.000 $3,500.000 $2,000.000 $14,000.000 $30,000.000 $28,000.000 $10,000.000 $12,300.000 $11,500.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 20.000 $24.250 $25.000 $49.000 $39.000 $40.000 $40.000 $76.000 $60.000 $55.000
ROCK FILTER DAMS (REMOVE)
LF 20.000 $9.900 $15.000 $25.000 $10.000 $20.000 $20.000 $59.000 $27.000 $27.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $16.750 $35.000 $31.000 $36.000 $22.000 $22.000 $38.000 $40.000 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $7.750 $25.000 $7.000 $15.000 $11.000 $11.000 $38.000 $10.000 $9.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,537.000 $2.240 $5.000 $4.000 $3.600 $1.750 $2.000 $2.500 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,537.000 $0.500 $1.400 $1.000 $1.000 $0.200 $0.250 $2.000 $1.200 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 237.000 $4.380 $9.000 $7.000 $6.100 $3.950 $6.000 $5.500 $10.000 $8.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 237.000 $1.050 $5.000 $2.000 $1.000 $1.250 $1.500 $2.500 $2.000 $2.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 540.000 $32.000 $65.000 $200.000 $40.000 $40.000 $30.000 $125.000 $70.000 $61.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 540.000 $10.000 $12.000 $22.000 $10.000 $15.000 $15.000 $25.000 $14.000 $29.000
CONC CURB (TY II)
LF 6,579.000 $24.630 $32.000 $10.000 $22.000 $8.000 $10.000 $15.000 $13.000 $5.000
DRIVEWAYS (CONC)
SY 327.000 $115.700 $95.000 $67.000 $122.000 $105.000 $160.000 $138.000 $150.000 $141.000
CONC SIDEWALKS (4")
SY 1,229.000 $47.000 $65.000 $46.000 $85.000 $50.000 $84.000 $80.000 $50.000 $85.000
CURB RAMPS (TY 1)
EA 1.000 $1,737.000 $1,500.000 $3,980.000 $1,950.000 $2,000.000 $2,000.000 $2,700.000 $2,100.000 $1,630.000
CURB RAMPS (TY 2)
EA 2.000 $2,060.280 $1,600.000 $3,585.000 $2,050.000 $2,200.000 $2,000.000 $2,200.000 $2,300.000 $1,710.000
CURB RAMPS (TY 5)
EA 4.000 $3,019.730 $2,000.000 $3,357.000 $2,500.000 $2,000.000 $3,500.000 $3,500.000 $3,700.000 $2,389.000
CURB RAMPS (TY 10)
EA 2.000 $1,936.970 $2,100.000 $4,093.000 $2,600.000 $2,500.000 $2,000.000 $3,600.000 $1,900.000 $2,793.000
CONC MEDIAN
SY 1,168.000 $60.000 $90.000 $53.000 $82.000 $70.000 $90.000 $80.000 $80.000 $117.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $975.000 $2,100.000 $1,500.000 $700.000 $640.000 $1,000.000 $800.000 $600.000 $1,650.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $8,000.000 $16,500.000 $13,450.000 $12,000.000 $7,510.000 $10,000.000 $10,000.000 $9,000.000 $14,795.000
CONDT (PVC) (SCH 40) (2")
LF 65.000 $14.680 $29.000 $15.000 $14.500 $14.000 $23.430 $26.000 $26.000 $24.200
CONDT (PVC) (SCH 40) (3")
LF 107.000 $18.250 $33.000 $11.000 $18.500 $18.000 $26.630 $29.000 $30.000 $27.500
CONDT (PVC) (SCH 40) (3") (BORE)
LF 176.000 $29.300 $56.000 $31.000 $30.000 $29.000 $45.800 $51.000 $50.000 $47.300
CONDT (PVC) (SCH 40) (4")
LF 32.000 $21.250 $36.000 $30.000 $29.000 $28.000 $29.820 $33.000 $32.000 $30.800
CONDT (PVC) (SCH 40) (4") (BORE)
LF 627.000 $37.600 $59.000 $42.000 $41.000 $40.000 $48.990 $50.000 $52.000 $50.600
CONDT (PVC) (SCH 80) (2")
LF 21.000 $16.110 $30.000 $18.000 $18.500 $17.000 $24.500 $27.000 $27.000 $25.300
ELEC CONDR (NO.12) INSULATED
LF 320.000 $1.000 $1.300 $2.000 $1.250 $1.200 $1.070 $1.200 $1.250 $1.100
ELEC CONDR (NO.8) INSULATED
LF 1,490.000 $2.500 $2.550 $2.000 $1.650 $1.600 $2.130 $2.400 $2.250 $2.200
ELEC CONDR (NO.6) BARE
LF 664.000 $1.650 $4.000 $3.000 $2.150 $2.100 $3.200 $3.500 $3.500 $3.300
ELEC CONDR (NO.6) INSULATED
LF 408.000 $4.430 $4.200 $3.000 $2.600 $2.500 $3.200 $3.500 $3.500 $3.300
GROUND BOX TY A (122311)W/APRON
EA 2.000 $1,075.410 $1,650.000 $1,020.000 $980.000 $950.000 $1,384.500 $1,200.000 $1,500.000 $1,430.000
GROUND BOX TY C (162911)W/APRON
EA 5.000 $1,255.000 $1,710.000 $1,180.000 $1,120.000 $1,100.000 $1,437.750 $1,200.000 $1,500.000 $1,485.000
ELC SRV TY D 120/240 070(NS)SS(E)PS(U)
EA 1.000 $6,099.750 $10,300.000 $11,263.000 $11,000.000 $10,500.000 $8,520.000 $8,000.000 $9,000.000 $8,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 16.000 $609.850 $905.000 $735.000 $670.000 $650.000 $782.780 $800.000 $790.000 $808.500
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $701.850 $1,018.000 $750.000 $840.000 $818.000 $798.750 $1,050.000 $890.000 $825.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 6.000 $976.830 $1,050.000 $1,220.000 $1,200.000 $1,100.000 $1,299.300 $1,150.000 $990.000 $1,342.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 232.000 $3.050 $1.200 $1.000 $1.650 $1.000 $1.070 $1.000 $2.000 $1.600
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,478.000 $1.050 $2.000 $1.000 $1.100 $1.100 $0.910 $1.200 $1.200 $1.100
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 863.000 $6.450 $9.000 $6.000 $7.300 $7.000 $6.390 $8.000 $8.000 $7.200
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 26.000 $134.700 $150.000 $125.000 $140.000 $110.000 $133.130 $165.000 $150.000 $137.500
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 26.000 $150.000 $170.000 $125.000 $170.000 $140.000 $154.430 $195.000 $180.000 $165.000
PAVEMENT SEALER 4"
LF 9,465.000 $0.150 $0.500 $1.000 $0.150 $0.250 $0.270 $0.350 $0.130 $0.200
PAVEMENT SEALER 8"
LF 4,478.000 $0.290 $0.600 $1.000 $0.250 $0.480 $0.530 $0.700 $0.270 $0.300
PAVEMENT SEALER 24"
LF 863.000 $2.050 $2.500 $2.000 $1.350 $1.650 $2.130 $2.700 $1.500 $1.300
PAVEMENT SEALER (ARROW)
EA 26.000 $25.860 $25.000 $50.000 $26.000 $20.000 $53.250 $67.000 $28.000 $25.300
PAVEMENT SEALER (WORD)
EA 26.000 $33.900 $35.000 $75.000 $32.000 $30.000 $79.880 $100.000 $34.000 $30.800
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,417.000 $0.550 $0.850 $1.000 $0.550 $0.550 $1.070 $1.400 $0.600 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 3,767.000 $0.400 $0.850 $1.000 $0.550 $0.550 $0.640 $0.800 $0.600 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 4,049.000 $0.420 $0.850 $1.000 $0.550 $0.550 $0.640 $0.800 $0.600 $0.500
REFL PAV MRKR TY II-C-R
EA 77.000 $4.240 $6.000 $5.000 $4.500 $4.500 $5.330 $6.700 $5.000 $4.400
ELIM EXT PAV MRK & MRKS (4")
LF 4,407.000 $0.430 $1.200 $1.000 $0.450 $0.500 $0.640 $0.800 $0.500 $0.500
ELIM EXT PAV MRK & MRKS (8")
LF 2,375.000 $0.880 $1.200 $1.000 $0.900 $1.250 $1.070 $1.400 $1.000 $0.900
ELIM EXT PAV MRK & MRKS (24")
LF 320.000 $3.500 $1.200 $3.000 $5.600 $3.000 $3.200 $4.000 $6.000 $5.500
ELIM EXT PAV MRK & MRKS (ARROW)
EA 30.000 $65.720 $175.000 $50.000 $140.000 $60.000 $53.250 $67.000 $150.000 $137.500
ELIM EXT PAV MRK & MRKS (WORD)
EA 20.000 $152.650 $175.000 $75.000 $170.000 $75.000 $79.880 $100.000 $185.000 $165.000
PAV SURF PREP FOR MRK (4")
LF 9,465.000 $0.100 $1.200 $0.050 $0.020 $0.200 $0.050 $0.100 $0.020 $0.250
PAV SURF PREP FOR MRK (8")
LF 4,478.000 $0.180 $1.600 $0.100 $0.070 $0.400 $0.110 $0.150 $0.090 $0.350
PAV SURF PREP FOR MRK (24")
LF 863.000 $1.430 $1.800 $0.500 $0.550 $1.000 $0.530 $0.700 $0.600 $0.500
PAV SURF PREP FOR MRK (ARROW)
EA 26.000 $23.290 $290.000 $35.000 $12.000 $20.000 $37.280 $47.000 $14.000 $11.900
PAV SURF PREP FOR MRK (WORD)
EA 26.000 $26.080 $290.000 $55.000 $15.000 $30.000 $58.580 $74.000 $16.000 $14.000
INSTALL HWY TRF SIG (ISOLATED)
EA 1.000 $22,600.000 $38,000.000 $20,382.000 $20,000.000 $19,000.000 $31,950.000 $30,000.000 $35,000.000 $33,000.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $4,489.640 $6,400.000 $4,827.000 $5,000.000 $4,500.000 $5,325.000 $5,880.000 $7,000.000 $5,500.000
TEMP TRAF SIGNALS
EA 1.000 $120,000.000 $105,000.000 $105,710.000 $125,000.000 $98,541.000 $85,200.000 $94,000.000 $100,000.000 $98,000.000
VEH SIG SEC (12")LED(GRN)
EA 11.000 $316.300 $510.000 $321.000 $305.000 $300.000 $426.000 $400.000 $450.000 $440.000
VEH SIG SEC (12")LED(GRN ARW)
EA 10.000 $312.050 $510.000 $321.000 $305.000 $300.000 $426.000 $400.000 $450.000 $440.000
VEH SIG SEC (12")LED(YEL)
EA 11.000 $311.600 $510.000 $321.000 $305.000 $300.000 $426.000 $400.000 $450.000 $440.000
VEH SIG SEC (12")LED(YEL ARW)
EA 11.000 $313.700 $510.000 $321.000 $305.000 $300.000 $426.000 $400.000 $450.000 $440.000
VEH SIG SEC (12")LED(RED)
EA 11.000 $307.600 $510.000 $321.000 $305.000 $300.000 $426.000 $400.000 $450.000 $440.000
VEH SIG SEC (12")LED(RED ARW)
EA 14.000 $312.350 $510.000 $321.000 $305.000 $300.000 $426.000 $400.000 $450.000 $440.000
PED SIG SEC (LED)(COUNTDOWN)
EA 8.000 $771.910 $1,080.000 $643.000 $610.000 $600.000 $905.250 $1,000.000 $1,000.000 $935.000
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
EA 8.000 $217.500 $220.000 $215.000 $205.000 $200.000 $181.050 $200.000 $195.000 $187.000
BACKPLATE W/REF BRDR(4 SEC)(VENT)ALUM
EA 6.000 $222.480 $245.000 $215.000 $205.000 $200.000 $202.350 $225.000 $210.000 $209.000
BACKPLATE W/REF BRDR(5 SEC)(VENT)ALUM
EA 4.000 $261.740 $254.000 $215.000 $205.000 $200.000 $213.000 $235.000 $225.000 $220.000
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 440.000 $2.150 $2.550 $3.000 $2.250 $2.200 $2.130 $2.500 $2.500 $2.200
TRF SIG CBL (TY A)(14 AWG)(7 CONDR)
LF 1,361.000 $2.300 $3.800 $3.000 $2.800 $2.750 $3.200 $3.500 $3.500 $3.300
TRF SIG CBL (TY A)(14 AWG)(9 CONDR)
LF 24.000 $4.000 $5.100 $3.000 $3.000 $2.900 $4.260 $4.500 $4.500 $4.400
TRF SIG CBL (TY A)(14 AWG)(16 CONDR)
LF 767.000 $4.750 $7.000 $5.000 $5.000 $4.850 $5.330 $6.000 $6.000 $5.500
TRF SIG CBL (TY C)(12 AWG)(2 CONDR)
LF 1,504.000 $1.750 $2.550 $2.000 $1.800 $1.750 $2.130 $2.300 $2.300 $2.200
INS TRF SIG PL AM(S)1 ARM(65')LUM
EA 4.000 $40,025.000 $38,000.000 $36,014.000 $35,000.000 $33,571.000 $31,950.000 $20,000.000 $35,000.000 $33,000.000
PED POLE ASSEMBLY
EA 4.000 $2,451.280 $4,000.000 $2,119.000 $2,100.000 $1,975.000 $3,195.000 $3,000.000 $3,400.000 $3,300.000
PED DETECT PUSH BUTTON (APS)
EA 8.000 $921.540 $1,065.000 $832.000 $790.000 $775.000 $852.000 $940.000 $900.000 $880.000
PED DETECTOR CONTROLLER UNIT
EA 1.000 $3,569.850 $4,715.000 $3,432.000 $3,300.000 $3,200.000 $3,834.000 $3,500.000 $4,000.000 $3,960.000
ANTI - GRAFFITI COATNG(PERMNENT-TY III)
SF 4,670.000 $0.590 $1.950 $1.000 $0.900 $0.850 $2.500 $1.000 $1.000 $1.000
SP MIXES SP-B PG64-22
TON 1,327.000 $130.000 $245.000 $150.000 $146.000 $166.860 $146.000 $182.000 $170.000 $160.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $18,200.000 $15,000.000 $12,500.000 $20,000.000 $21,000.000 $24,000.000 $30,000.000 $21,000.000
BBU SYSTEM (EXTERNAL BATT CABINET)
EA 1.000 $7,587.900 $10,100.000 $9,440.000 $9,000.000 $8,800.000 $8,094.000 $8,930.000 $10,000.000 $8,360.000
TMA (STATIONARY)
DAY 97.000 $225.000 $195.000 $300.000 $165.000 $250.000 $157.500 $195.000 $350.000 $150.000
TMA (MOBILE OPERATION)
HR 48.000 $150.500 $85.000 $1,000.000 $75.000 $30.000 $105.000 $100.000 $125.000 $75.000
RVDS(PRESENCE AND ADVANCE DET)
EA 4.000 $8,087.150 $8,436.000 $8,368.000 $8,000.000 $7,800.000 $6,709.500 $6,000.000 $7,000.000 $6,930.000
VIVDS TEMPORARY
EA 1.000 $22,237.550 $50,600.000 $24,674.000 $24,000.000 $23,000.000 $42,600.000 $33,100.000 $45,000.000 $44,000.000
FURNISH, INSTALL 20" C905 DR-18 PVC WAT
LF 1,172.000 $200.000 $65.000 $250.000 $250.000 $300.000 $264.970 $335.000 $325.000 $274.000
FURNISH, INSTALL 12" C900 DR-18 PVC WAT
LF 500.000 $100.000 $55.000 $123.000 $150.000 $200.000 $153.790 $170.000 $152.000 $159.000
FURNISH, INSTALL 8" C900 DR-18 PVC WATE
LF 26.000 $70.000 $45.000 $129.000 $285.000 $150.000 $127.000 $195.000 $133.480 $131.000
FURNISH, INSTALL 20" C905 DR-18 PVC WAT
LF 128.000 $300.000 $72.000 $122.000 $875.000 $850.000 $1,230.080 $680.000 $1,314.810 $1,270.500
DUCTILE IRON FITTINGS
TON 5.300 $6,000.000 $1,800.000 $11,285.000 $11,300.000 $15,000.000 $16,587.380 $16,700.000 $16,017.990 $17,132.500
FURNISH AND INSTALL 20" BUTTERFLY VALVE
EA 6.000 $15,000.000 $3,200.000 $10,945.000 $9,500.000 $20,000.000 $19,856.930 $26,000.000 $28,031.490 $20,509.500
FURNISH AND INSTALL 12" GATE VALVE
EA 3.000 $3,500.000 $2,800.000 $8,213.000 $4,600.000 $5,000.000 $5,448.540 $5,900.000 $6,407.190 $5,627.600
FURNISH AND INSTALL 8" GATE VALVE
EA 3.000 $2,500.000 $2,400.000 $4,470.000 $2,850.000 $4,000.000 $2,960.700 $3,600.000 $3,737.530 $3,058.000
FURNISH AND INSTALL AIR RELEASE VALVE
EA 2.000 $5,500.000 $1,800.000 $3,939.000 $5,800.000 $5,000.000 $7,518.900 $9,000.000 $13,214.850 $7,766.000
FURNISH AND INSTALL FIRE HYDRANT W/ 6"
EA 3.000 $6,500.000 $1,800.000 $7,536.000 $8,600.000 $6,000.000 $7,268.630 $8,200.000 $11,346.080 $7,507.500
TRENCH SAFETY (WATER LINE)
LF 1,492.000 $2.000 $25.000 $15.000 $6.000 $1.000 $3.200 $4.500 $6.670 $3.300
CONNECT TO EXISTING 20" WATER
EA 2.000 $5,500.000 $3,500.000 $3,524.000 $3,750.000 $10,000.000 $7,156.800 $11,800.000 $20,022.490 $7,392.000
CONNECT TO EXISTING 12" WATER
EA 1.000 $1,500.000 $2,800.000 $5,780.000 $1,480.000 $5,000.000 $2,164.080 $7,500.000 $12,680.910 $2,235.200
CONNECT TO EXISTING 8" WATER
EA 3.000 $1,400.000 $2,500.000 $3,524.000 $980.000 $2,500.000 $1,666.730 $3,170.000 $9,076.860 $1,721.500
SAWCUT & REMOVE CONCRETE PAVING
SY 23.000 $7.750 $95.000 $120.000 $23.000 $200.000 $24.500 $32.000 $60.070 $25.300
PROVIDE TEMPORARY GRAVEL SURFACE
SY 23.000 $15.000 $55.000 $68.000 $64.000 $50.000 $29.820 $37.000 $46.720 $30.800
SAWCUT, REMOVE & REPLACE 7" CONCRETE DR
SY 15.000 $45.000 $95.000 $120.000 $675.000 $150.000 $303.530 $180.000 $427.150 $150.000
SAWCUT, REMOVE & REPLACE 4" SIDEWALK
SY 36.000 $60.000 $65.000 $120.000 $130.000 $100.000 $155.490 $120.000 $340.380 $100.000
SAWCUT & REMOVE 4" SIDEWALK
SY 4.000 $8.500 $65.000 $120.000 $56.000 $50.000 $70.290 $68.000 $301.680 $50.000
CONSTRUCT BARRIER FREE RAMP
EA 1.000 $1,936.970 $5,500.000 $3,962.000 $3,100.000 $5,000.000 $3,056.550 $3,350.000 $7,341.580 $3,500.000
WATER LINE TEST
LS 1.000 $5,000.000 $2,500.000 $8,785.000 $20,000.000 $7,000.000 $8,040.750 $18,900.000 $20,022.480 $8,305.000
ABANDON AND BACKFILL VALVE
EA 4.000 $100.000 $1,800.000 $1,100.000 $1,200.000 $1,000.000 $479.250 $665.000 $467.190 $495.000
REMOVE TREE (2" - 6")
EA 4.000 $250.000 $500.000 $1,143.000 $475.000 $300.000 $415.350 $345.000 $1,957.710 $500.000
REMOVE TREE (6" - 12")
EA 3.000 $500.000 $650.000 $1,143.000 $800.000 $400.000 $852.000 $1,550.000 $2,610.280 $750.000
SODDING (10-FOOT WIDE)
SY 1,580.000 $3.080 $3.000 $4.500 $4.600 $6.500 $13.050 $5.200 $26.100 $5.000
POTHOLE WATERLINE
EA 2.000 $3,000.000 $1,500.000 $393.000 $1,000.000 $4,000.000 $4,419.750 $1,300.000 $4,137.980 $4,565.000
CASING (STEEL) (20 IN) (BORED)
LF 78.000 $250.000 $265.000 $386.000 $825.000 $800.000 $653.910 $555.000 $1,167.980 $675.000
Totals: $4,118,638.960 $4,570,584.950 $4,799,765.050 $5,219,945.570 $5,419,968.230 $5,529,244.244 $5,539,277.050 $5,864,565.677 $5,963,418.600