COLLIN US 75 (0047-06-165)
Items: 25
County: COLLIN
Length: N/A
Highway: US 75
District: DALLAS
Control Number: 0047-06-165
DBE Goal: N/A
Project: NH 2019(630)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $1,569,452.00
Date: 03/05/2019 (7 years ago)
Contract Number: N/A
Type: FULL DEPTH CONCRETE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,569,452.00 | |||
| $1,923,008.00 |
22.53%
$353,556.00
|
|||
| $1,932,526.00 |
23.13%
$363,074.00
|
0.49%
$9,518.00
|
||
| $1,997,790.00 |
27.29%
$428,338.00
|
3.89%
$74,782.00
|
-3.38%
-$65,264.00
|
|
| $2,182,247.00 |
39.05%
$612,795.00
|
13.48%
$259,239.00
|
-9.23%
-$184,457.00
|
|
| $2,497,231.72 |
59.11%
$927,779.72
|
29.86%
$574,223.72
|
-14.43%
-$314,984.72
|
|
| $3,005,883.47 |
91.52%
$1,436,431.47
|
56.31%
$1,082,875.47
|
-20.37%
-$508,651.75
|
E
Engineer's Estimate
$1,569,452.00
1
Awarded
$1,923,008.00
Over/Under Est:
22.53%
$353,556.00
$1,932,526.00
Over/Under Est:
23.13%
$363,074.00
Amt Left:
0.49%
$9,518.00
$1,997,790.00
Over/Under Est:
27.29%
$428,338.00
Amt Left:
3.89%
$74,782.00
Delta:
-3.38%
-$65,264.00
$2,182,247.00
Over/Under Est:
39.05%
$612,795.00
Amt Left:
13.48%
$259,239.00
Delta:
-9.23%
-$184,457.00
$2,497,231.72
Over/Under Est:
59.11%
$927,779.72
Amt Left:
29.86%
$574,223.72
Delta:
-14.43%
-$314,984.72
$3,005,883.47
Over/Under Est:
91.52%
$1,436,431.47
Amt Left:
56.31%
$1,082,875.47
Delta:
-20.37%
-$508,651.75
Bid Items & Bid Tabulations
25
Total
0 of 25