CLAY FM 174 (0137-10-026)

Items: 78

County: CLAY
Length: N/A
Highway: FM 174
District: WICHITA FALLS
Control Number: 0137-10-026
DBE Goal: N/A
Project: STP 2023(471)HES
Guaranty: N/A
Time: 187 WORKING DAYS
Engineer's Estimate: $4,196,246.40
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
CALLAN COLTHARP
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$4,196,246.40
$4,557,308.85
Over/Under Est: 8.6% $361,062.45
$4,595,817.53
Over/Under Est: 9.52% $399,571.13
Amt Left: 0.84% $38,508.68
$5,092,983.39
Over/Under Est: 21.37% $896,736.99
Amt Left: 11.75% $535,674.54
Delta: -10.82% -$497,165.86
$5,096,041.46
Over/Under Est: 21.44% $899,795.06
Amt Left: 11.82% $538,732.61
Delta: -0.06% -$3,058.07

Bid Items & Bid Tabulations

78 Total 0 of 78
CLAY  |  FM 174  |  WICHITA FALLS  |  0137-10-026  |  03/07/2023  |  $4,196,246.40  |  STP 2023(471)HES  |  HAZARD ELIM & SAFETY  |  187 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EUROVIA ATLANTIC COAST LLC
DUININCK, INC.
A. L. HELMCAMP, INC.
JAGOE-PUBLIC COMPANY
REMOVING CONC (RIPRAP)
SY 19.000 $25.000 $35.000 $39.500 $36.750 $39.000
EXCAVATION (ROADWAY)
CY 2,405.000 $6.430 $45.000 $46.500 $75.000 $53.000
EXCAVATION (CHANNEL)
CY 292.000 $34.110 $45.000 $44.500 $50.000 $73.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 4,137.000 $31.190 $43.000 $46.500 $20.000 $53.000
BLADING
STA 1.000 $300.000 $1,650.000 $405.000 $750.000 $1,200.000
BROADCAST SEED (TEMP) (WARM)
SY 29,222.000 $0.120 $0.140 $0.140 $0.150 $0.140
BROADCAST SEED (TEMP) (COOL)
SY 29,222.000 $0.140 $0.140 $0.160 $0.170 $0.140
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 58,431.000 $0.140 $0.180 $0.110 $0.120 $0.200
VEGETATIVE WATERING
MG 968.000 $29.880 $45.000 $32.500 $5.000 $55.000
CEMENT
TON 434.300 $237.300 $235.000 $250.000 $265.000 $230.000
CEMENT TREAT (SUBGRADE) (8")
SY 40,164.000 $3.060 $3.550 $5.150 $7.000 $6.750
PRIME COAT (MC-30)
GAL 10,038.000 $5.170 $6.000 $5.500 $15.000 $3.500
EMULS ASPH (PRIME)(MS-2 OR SS-1)
GAL 13,693.000 $4.450 $3.000 $3.850 $5.000 $2.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 1,390.000 $58.180 $67.000 $68.500 $90.000 $64.000
PLANE ASPH CONC PAV(0" TO 2")
SY 1,397.000 $2.940 $15.500 $8.600 $12.000 $8.900
CEM STABIL BKFL
CY 154.000 $187.770 $275.000 $275.000 $288.750 $310.000
CUT & RESTORING PAV
SY 162.000 $79.260 $147.520 $120.000 $150.000 $28.000
TRENCH EXCAVATION PROTECTION
LF 88.000 $90.000 $10.000 $10.000 $10.500 $11.000
TEMPORARY SPL SHORING
SF 174.000 $100.000 $60.000 $100.000 $84.000 $89.000
RIPRAP (CONC)(5 IN)
CY 20.000 $580.600 $850.000 $625.000 $656.250 $690.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 18.000 $200.000 $550.000 $300.000 $315.000 $330.000
RIPRAP (MOW STRIP)(4 IN)
CY 92.000 $650.660 $675.000 $625.000 $656.250 $690.000
CMP (GAL STL 18 IN)
LF 422.000 $82.040 $65.000 $65.000 $68.250 $72.000
CMP (GAL STL 24 IN)
LF 122.000 $98.970 $80.000 $80.000 $84.000 $89.000
RC PIPE (CL III)(24 IN)
LF 292.000 $100.000 $120.000 $120.000 $126.000 $130.000
RC PIPE (CL III)(30 IN)
LF 294.000 $120.000 $160.000 $160.000 $168.000 $180.000
RC PIPE (CL III)(36 IN)
LF 108.000 $158.300 $200.000 $200.000 $210.000 $220.000
SET (TY I)(S= 6 FT)(HW= 4 FT)(4:1) (C)
EA 2.000 $9,500.000 $9,500.000 $10,000.000 $10,500.000 $11,100.000
SET (TY I)(S= 9 FT)(HW= 4 FT)(4:1) (C)
EA 4.000 $17,000.000 $9,900.000 $12,000.000 $12,600.000 $13,300.000
SET (TY I)(S= 9 FT)(HW= 7 FT)(3:1) (C)
EA 2.000 $20,000.000 $17,500.000 $20,500.000 $21,525.000 $22,800.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 36.000 $1,260.000 $1,400.000 $1,400.000 $1,470.000 $1,600.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 10.000 $2,842.690 $1,500.000 $1,600.000 $1,627.500 $1,700.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 7.000 $2,000.000 $1,350.000 $1,400.000 $1,470.000 $1,600.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 5.000 $2,500.000 $1,500.000 $1,500.000 $1,575.000 $1,700.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 12.000 $4,800.000 $2,000.000 $2,100.000 $2,205.000 $2,300.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 2.000 $5,200.000 $3,000.000 $3,300.000 $3,465.000 $3,700.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 4.000 $6,170.000 $3,800.000 $4,000.000 $4,200.000 $4,400.000
CLEAN EXIST CULVERTS
EA 6.000 $3,991.780 $2,000.000 $2,000.000 $2,100.000 $2,200.000
REMOV STR (SET)
EA 2.000 $421.890 $300.000 $300.000 $315.000 $330.000
REMOV STR (WINGWALL)
EA 8.000 $806.690 $800.000 $1,200.000 $1,260.000 $1,300.000
REMOV STR (PIPE)
LF 1,244.000 $14.770 $10.000 $15.000 $15.750 $17.000
REMOV STR (SMALL FENCE)
LF 50.000 $4.120 $116.000 $25.000 $50.000 $36.000
MOBILIZATION
LS 1.000 $332,084.840 $355,000.000 $440,000.000 $460,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $8,000.000 $17,000.000 $23,000.000 $10,000.000 $30,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 660.000 $32.410 $38.000 $27.000 $28.350 $42.250
ROCK FILTER DAMS (REMOVE)
LF 660.000 $10.720 $10.000 $15.000 $23.100 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,400.000 $3.440 $4.000 $2.950 $3.100 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,400.000 $1.080 $1.000 $0.900 $0.950 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 3,880.000 $4.720 $6.000 $3.700 $3.890 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,880.000 $1.010 $1.000 $1.000 $1.050 $1.000
INTERSECTIONS (ACP)
SY 290.000 $50.060 $36.000 $29.500 $95.000 $26.000
TURNOUTS (ACP)
SY 589.000 $50.680 $141.000 $29.500 $95.000 $30.000
DRIVEWAYS (BASE)
SY 3,980.000 $19.000 $41.000 $14.000 $20.000 $45.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 65,728.000 $0.210 $0.110 $0.160 $0.190 $0.200
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 32,864.000 $0.230 $0.110 $0.210 $0.250 $0.200
MTL W-BEAM GD FEN (TIM POST)
LF 725.000 $28.950 $26.730 $22.000 $22.840 $33.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 100.000 $91.350 $63.590 $81.000 $85.050 $100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,547.750 $3,290.000 $2,950.000 $3,071.250 $3,600.000
WIRE FENCE (TY D)
LF 50.000 $25.440 $30.000 $20.000 $65.000 $90.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 17.000 $450.000 $530.000 $530.000 $556.500 $590.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 2.000 $341.750 $260.000 $260.000 $273.000 $290.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 16.000 $837.420 $515.000 $515.000 $540.750 $570.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 15.000 $766.010 $590.000 $590.000 $619.500 $660.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $1,260.000 $780.000 $780.000 $819.000 $870.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 10.000 $968.560 $825.000 $825.000 $866.250 $920.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,520.000 $1,100.000 $1,100.000 $1,155.000 $1,200.000
IN SM RD SN SUP&AM TYTWT(1)UA(P)
EA 12.000 $559.280 $575.000 $575.000 $603.750 $640.000
REMOVE SM RD SN SUP&AM
EA 55.000 $95.000 $100.000 $100.000 $105.000 $110.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,051.000 $0.880 $1.000 $1.350 $1.000 $3.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 65,980.000 $0.450 $0.490 $0.440 $0.460 $0.550
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 5,730.000 $0.440 $0.490 $0.450 $0.470 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 37,980.000 $0.460 $0.490 $0.440 $0.460 $0.550
REFL PAV MRKR TY II-A-A
EA 764.000 $4.470 $5.000 $3.750 $3.940 $5.600
D-GR HMA TY-B PG64-22
TON 8,039.000 $100.000 $98.000 $110.000 $115.000 $106.000
D-GR HMA TY-D SAC-B PG70-28
TON 11,256.000 $115.000 $114.000 $105.000 $125.000 $112.000
BONDING COURSE
GAL 6,136.000 $4.510 $3.450 $4.750 $6.000 $2.500
TMA (STATIONARY)
DAY 139.000 $175.680 $300.000 $250.000 $650.000 $320.000
TMA (MOBILE OPERATION)
DAY 4.000 $200.000 $880.000 $1,000.000 $900.000 $1,000.000
Totals: $4,196,246.400 $4,557,308.850 $4,595,817.530 $5,092,983.390 $5,096,041.460