Job Info for 0910-36-137

County: CHEROKEE Highway: VA Date: 09/06/2024 (2 months ago) Engineer's Estimate: $180,909 Control Number: 0910-36-137
Project: STP 2025(022)HESG District: TYLER Time: 50 WORKING DAYS Type: INSTALL/REPLACE SIGNS
Bidder's List

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $180,908.61
RISE UP CONSTRUCTION LLC   $159,987.10 1
-11.56% | -$20,921.51
TRAFFIC HIGHWAY MAINTENANCE, LLC   $168,493.20 2
-6.86% | -$12,415.41
5.32% | $8,506.10
TIGHT LINE CONSTRUCTION, LLC   $169,500.50 3
-6.31% | -$11,408.11
5.95% | $9,513.40
0.60% | $1,007.30
GARRET SHIELDS INFRASTRUCTURE   $242,668.50 4
34.14% | $61,759.89
51.68% | $82,681.40
43.17% | $73,168.00

Bid Items

Items: 19, 0 filtered
CHEROKEE VA  |  TYLER  |  0910-36-137  |  09/06/2024  |  $180,909  |  STP 2025(022)HESG  |  INSTL/REPLACE SIGNS  |  50 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate RISE UP CONSTRUCTION LLC TRAFFIC HIGHWAY MAINTENANCE, LLC TIGHT LINE CONSTRUCTION, LLC GARRET SHIELDS INFRASTRUCTURE
500 7001 MOBILIZATION LS 1.000 $20,000.000 $10,000.000 $18,250.000 $10,000.000 $25,000.000
502 7001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $5,000.000 $3,401.000 $2,750.000 $7,500.000 $5,000.000
505 7003 TMA (MOBILE OPERATION) DAY 70.000 $196.000 $1.000 $0.010 $1.000 $100.000
644 7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 42.000 $750.000 $800.000 $735.000 $650.000 $1,500.000
644 7002 IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM) EA 36.000 $800.000 $900.000 $860.000 $750.000 $1,500.000
644 7073 REMOVE SM RD SN SUP&AM EA 37.000 $120.500 $60.000 $163.000 $200.000 $200.000
666 7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 1,126.000 $8.580 $7.000 $12.000 $7.800 $7.500
666 7081 REFL PAV MRK TY I (W)(RR XING)(100MIL) EA 5.000 $500.000 $800.000 $1,500.000 $850.000 $840.000
666 7175 RE PM TY II (W) 6" (SLD) LF 9,950.000 $0.270 $0.500 $0.150 $0.500 $0.450
666 7184 RE PM TY II (W) 24" (SLD) LF 1,126.000 $3.130 $4.000 $0.750 $4.800 $5.000
666 7198 RE PM TY II (W) (RR XING) EA 5.000 $450.000 $750.000 $50.000 $650.000 $525.000
666 7213 RE PM TY II (Y) 6" (SLD) LF 14,776.000 $0.270 $0.500 $0.150 $0.500 $0.500
666 7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) LF 9,950.000 $1.000 $0.990 $1.500 $1.050 $1.000
666 7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) LF 14,776.000 $1.000 $0.950 $1.500 $1.050 $1.000
672 7004 REFL PAV MRKR TY II-A-A EA 188.000 $4.710 $10.000 $8.000 $9.000 $8.500
677 7002 ELIM EXT PM & MRKS (6") LF 2,306.000 $1.000 $0.900 $2.550 $0.850 $1.000
677 7008 ELIM EXT PM & MRKS (24") LF 367.000 $5.550 $8.000 $9.500 $6.500 $6.000
678 7002 PAV SURF PREP FOR MRK (6") LF 24,730.000 $0.410 $0.200 $0.010 $0.250 $0.200
678 7008 PAV SURF PREP FOR MRK (24") LF 1,090.000 $2.500 $3.000 $0.100 $2.750 $2.500
Totals: $180,908.61 $159,987.10 $168,493.20 $169,500.50 $242,668.50