Job Info for 0345-03-023

County: CHEROKEE Highway: SH 110 Date: 01/08/2019 (5 years ago) Engineer's Estimate: $770,263 Control Number: 0345-03-023
Project: STP 2019(309)HES District: TYLER Time: 55 WORKING DAYS Type: PROFILE EDGELINE & CENTERLINE MKGS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $770,262.82
STRIPING TECHNOLOGY, L.P.   $491,833.83 1
-36.15% | -$278,428.99
STRIPE-A-ZONE, INC.   $618,880.75 2
-19.65% | -$151,382.07
25.83% | $127,046.92
TRP CONSTRUCTION GROUP, LLC   $1,737,142.82 3
125.53% | $966,880.00
253.2% | $1,245,308.99
180.69% | $1,118,262.07

Bid Items

Items: 16, 0 filtered
CHEROKEE SH 110  |  TYLER  |  0345-03-023  |  01/08/2019  |  $770,263  |  STP 2019(309)HES  |  PROFILE EDGELINE & CENTERLINE MKGS  |  55 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPING TECHNOLOGY, L.P. STRIPE-A-ZONE, INC. TRP CONSTRUCTION GROUP, LLC
500 6001 MOBILIZATION LS 1.000 $64,740.000 $10,000.000 $40,000.000 $106,221.020
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $5,000.000 $3,000.000 $16,250.000 $37,725.000
666 6224 PAVEMENT SEALER 4" LF 3,112.000 $0.200 $0.500 $0.150 $0.580
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 19,850.000 $0.350 $0.400 $0.500 $0.850
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 68,863.000 $0.300 $0.330 $0.500 $0.730
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 36,453.000 $0.370 $0.400 $0.500 $0.850
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 272,773.000 $0.350 $0.330 $0.350 $0.730
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 406,930.000 $0.850 $0.550 $0.560 $1.680
666 6344 REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL) LF 9,304.000 $1.250 $1.000 $0.600 $3.500
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 103,703.000 $1.000 $0.550 $0.600 $1.680
672 6007 REFL PAV MRKR TY I-C EA 993.000 $3.000 $3.400 $3.000 $6.410
672 6009 REFL PAV MRKR TY II-A-A EA 6,996.000 $2.700 $3.400 $3.000 $6.410
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 3,112.000 $0.430 $1.000 $1.700 $3.990
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 1,502.000 $3.000 $5.000 $9.000 $18.100
6185 6001 TMA (STATIONARY) EA 2.000 $8,000.000 $200.000 $25.000 $15,000.000
6185 6005 TMA (MOBILE OPERATION) DAY 24.000 $1,600.000 $70.000 $25.000 $5,500.000
Totals: $770,262.82 $491,833.83 $618,880.75 $1,737,142.82