PREPARING ROW
|
AC
|
0.180
|
$30,000.000
|
$6,000.000
|
$20,000.000
|
$15,000.000
|
$42,000.000
|
$2,900.000
|
|
|
PREPARING ROW
|
STA
|
279.200
|
$500.000
|
$200.000
|
$200.000
|
$600.000
|
$350.000
|
$1,100.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
87.000
|
$18.000
|
$40.000
|
$30.000
|
$15.000
|
$30.000
|
$14.500
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
705.000
|
$6.000
|
$8.000
|
$15.000
|
$10.000
|
$11.000
|
$10.500
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
3,188.000
|
$12.000
|
$5.500
|
$12.000
|
$5.000
|
$8.750
|
$6.500
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
8,470.000
|
$17.500
|
$25.000
|
$8.000
|
$8.000
|
$7.250
|
$9.500
|
|
|
BACKFILL (TY C)
|
STA
|
461.350
|
$14.000
|
$190.000
|
$100.000
|
$230.000
|
$195.000
|
$225.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
116,120.000
|
$2.000
|
$1.000
|
$0.900
|
$1.000
|
$1.950
|
$0.900
|
|
|
STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
30,946.000
|
$0.220
|
$0.330
|
$0.250
|
$0.300
|
$0.350
|
$0.280
|
|
|
STRAW/HAY MLCH SEED(TEMP)(WARM)
|
SY
|
15,473.000
|
$0.400
|
$0.340
|
$0.250
|
$0.300
|
$0.350
|
$0.280
|
|
|
STRAW/HAY MLCH SEED(TEMP)(COOL)
|
SY
|
15,473.000
|
$0.400
|
$0.310
|
$0.250
|
$0.300
|
$0.330
|
$0.280
|
|
|
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
|
SY
|
85,175.000
|
$0.900
|
$0.850
|
$1.000
|
$0.900
|
$0.900
|
$0.860
|
|
|
BONDED FBR MTRX SEED (TEMP)(WARM)
|
SY
|
42,587.000
|
$0.700
|
$0.780
|
$1.000
|
$0.850
|
$0.800
|
$0.860
|
|
|
BONDED FBR MTRX SEED (TEMP)(COOL)
|
SY
|
42,587.000
|
$0.700
|
$0.760
|
$1.000
|
$0.850
|
$0.800
|
$0.860
|
|
|
VEGETATIVE WATERING
|
MG
|
2,555.000
|
$10.000
|
$10.000
|
$10.000
|
$10.000
|
$1.000
|
$13.500
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY B)
|
SY
|
85,175.000
|
$1.000
|
$1.250
|
$1.000
|
$0.920
|
$1.250
|
$0.950
|
|
|
LIME (HYDRATED LIME (DRY))
|
TON
|
164.000
|
$170.000
|
$153.000
|
$165.000
|
$200.000
|
$180.000
|
$180.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
9,956.000
|
$3.000
|
$3.500
|
$6.000
|
$5.000
|
$1.750
|
$3.750
|
|
|
CEMENT
|
TON
|
164.000
|
$145.000
|
$150.000
|
$165.000
|
$160.000
|
$170.000
|
$150.000
|
|
|
CEMENT TREAT(EXIST MATL)(8")
|
SY
|
9,956.000
|
$3.000
|
$3.000
|
$8.000
|
$4.000
|
$1.550
|
$2.350
|
|
|
EMULS ASPH (EROSN CONT)(CSS-1H)
|
GAL
|
3,569.000
|
$2.750
|
$2.500
|
$4.000
|
$6.000
|
$3.800
|
$4.500
|
|
|
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
|
GAL
|
122,061.000
|
$3.250
|
$2.600
|
$3.000
|
$3.000
|
$3.150
|
$2.600
|
|
|
AGGR (TY-PD GR-3 OR TY-PL GR-3)
|
CY
|
2,906.000
|
$110.000
|
$110.000
|
$85.000
|
$120.000
|
$120.000
|
$130.000
|
|
|
D-GR HMA(SQ) TY-D PG64-22
|
TON
|
999.000
|
$155.000
|
$150.000
|
$110.000
|
$150.000
|
$100.000
|
$150.000
|
|
|
PFC (ASPHALT) PG76-22
|
TON
|
1,282.000
|
$145.000
|
$0.010
|
$136.000
|
$130.000
|
$130.000
|
$140.000
|
|
|
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
|
TON
|
20,081.000
|
$105.000
|
$124.000
|
$136.000
|
$130.000
|
$130.000
|
$140.000
|
|
|
SUPERPAVE MIXTURES SP-B PG64-22
|
TON
|
9,293.000
|
$90.000
|
$96.000
|
$105.000
|
$97.000
|
$95.000
|
$128.000
|
|
|
SUPERPAVE MIXTURES SP-D PG64-22(LEV-UP)
|
TON
|
11,809.000
|
$100.000
|
$98.000
|
$98.000
|
$101.000
|
$95.000
|
$105.530
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
1,000.000
|
$75.000
|
$48.000
|
$42.000
|
$50.000
|
$60.000
|
$1.050
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
73,146.000
|
$1.500
|
$2.000
|
$1.250
|
$2.500
|
$2.350
|
$2.000
|
|
|
PLANE ASPH CONC PAV (0" TO 1 1/2")
|
SY
|
10,236.000
|
$1.200
|
$2.000
|
$1.650
|
$2.500
|
$2.150
|
$2.000
|
|
|
PLANE ASPH CONC PAV (0"- 2 1/2")
|
SY
|
5,085.000
|
$1.900
|
$2.000
|
$1.700
|
$3.000
|
$2.550
|
$1.900
|
|
|
PAV JT UNDERSEAL (24")
|
LF
|
677.000
|
$30.000
|
$17.000
|
$45.000
|
$37.000
|
$42.000
|
$28.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
70.000
|
$350.000
|
$760.000
|
$1,200.000
|
$650.000
|
$575.000
|
$445.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
1.000
|
$1,400.000
|
$1,000.000
|
$4,000.000
|
$1,000.000
|
$1,000.000
|
$685.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
111.000
|
$425.000
|
$500.000
|
$470.000
|
$425.000
|
$425.000
|
$330.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
28.000
|
$145.000
|
$200.000
|
$250.000
|
$200.000
|
$200.000
|
$128.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
178.000
|
$400.000
|
$525.000
|
$520.000
|
$450.000
|
$450.000
|
$400.000
|
|
|
CLEANING AND SEALING EXISTING JOINTS
|
LF
|
677.000
|
$12.000
|
$25.000
|
$28.000
|
$35.000
|
$38.000
|
$36.000
|
|
|
CLEANING AND SEALING JOINTS (CL 3)
|
LF
|
542.000
|
$35.000
|
$18.000
|
$28.000
|
$28.000
|
$33.000
|
$25.000
|
|
|
RAIL (TY T552)
|
LF
|
496.000
|
$50.000
|
$125.000
|
$123.000
|
$80.000
|
$75.000
|
$71.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
397.000
|
$50.000
|
$50.000
|
$52.000
|
$42.000
|
$40.000
|
$47.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
58.000
|
$70.000
|
$105.000
|
$85.000
|
$52.000
|
$60.000
|
$68.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
16.000
|
$858.000
|
$800.000
|
$500.000
|
$575.000
|
$600.000
|
$600.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
1.000
|
$1,200.000
|
$950.000
|
$530.000
|
$600.000
|
$650.000
|
$750.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$950.000
|
$1,050.000
|
$780.000
|
$925.000
|
$950.000
|
$1,100.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$760,000.000
|
$500,000.000
|
$560,000.000
|
$550,000.000
|
$850,000.000
|
$434,960.870
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
14.000
|
$5,000.000
|
$5,500.000
|
$7,500.000
|
$7,000.000
|
$2,600.000
|
$6,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
1,560.000
|
$28.000
|
$26.000
|
$25.000
|
$28.000
|
$29.000
|
$25.500
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
740.000
|
$35.000
|
$30.000
|
$30.000
|
$32.000
|
$32.000
|
$29.500
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
2,300.000
|
$8.000
|
$13.000
|
$4.000
|
$2.000
|
$14.000
|
$10.500
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
780.000
|
$25.000
|
$27.000
|
$10.000
|
$32.000
|
$28.000
|
$22.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
780.000
|
$15.000
|
$14.000
|
$2.000
|
$2.000
|
$15.000
|
$10.500
|
|
|
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
|
CY
|
1,000.000
|
$25.000
|
$16.000
|
$11.000
|
$30.000
|
$12.000
|
$15.750
|
|
|
BACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
100.000
|
$65.000
|
$120.000
|
$65.000
|
$75.000
|
$125.000
|
$72.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
10,335.000
|
$3.000
|
$3.300
|
$4.000
|
$3.500
|
$2.850
|
$2.900
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
10,335.000
|
$1.000
|
$1.000
|
$2.000
|
$0.500
|
$1.100
|
$1.000
|
|
|
TRACKHOE WORK (EROSION & SEDMT CONT)
|
HR
|
100.000
|
$120.000
|
$175.000
|
$85.000
|
$125.000
|
$125.000
|
$150.000
|
|
|
PORT CTB (DES SOURCE) (SAFETY SH)(TY 2)
|
LF
|
750.000
|
$4.500
|
$17.000
|
$22.000
|
$12.000
|
$12.000
|
$18.000
|
|
|
PORT CTB (STKPL)(SAFETY SH)
|
LF
|
750.000
|
$5.250
|
$17.000
|
$22.000
|
$12.000
|
$12.000
|
$10.500
|
|
|
INTERSECTIONS (ACP)
|
SY
|
1,147.000
|
$40.000
|
$37.010
|
$40.000
|
$30.000
|
$28.000
|
$45.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
2,589.000
|
$30.000
|
$43.000
|
$40.000
|
$30.000
|
$26.000
|
$45.000
|
|
|
TURNOUTS (ACP)
|
SY
|
187.000
|
$35.000
|
$39.000
|
$60.000
|
$30.000
|
$33.000
|
$45.000
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
87.000
|
$90.000
|
$150.000
|
$100.000
|
$100.000
|
$94.000
|
$73.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
92,300.000
|
$0.350
|
$0.170
|
$0.140
|
$0.120
|
$0.120
|
$0.150
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
46,150.000
|
$0.350
|
$0.200
|
$0.140
|
$0.120
|
$0.120
|
$0.150
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,575.000
|
$25.000
|
$21.000
|
$19.000
|
$22.000
|
$19.800
|
$21.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
10.000
|
$1,600.000
|
$1,400.000
|
$1,500.000
|
$1,800.000
|
$1,550.000
|
$1,401.750
|
|
|
MTL BEAM GD FEN TRANS (T101)
|
EA
|
4.000
|
$1,200.000
|
$1,200.000
|
$1,100.000
|
$1,200.000
|
$1,115.000
|
$1,155.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,575.000
|
$3.000
|
$10.500
|
$2.000
|
$11.000
|
$2.200
|
$10.500
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$500.000
|
$210.000
|
$260.000
|
$250.000
|
$275.000
|
$210.000
|
|
|
RM MTL BM GD FEN TRANS (T101)
|
EA
|
4.000
|
$200.000
|
$210.000
|
$260.000
|
$250.000
|
$275.000
|
$210.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
14.000
|
$2,500.000
|
$2,350.000
|
$2,500.000
|
$2,500.000
|
$2,550.000
|
$2,362.500
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
12.000
|
$350.000
|
$210.000
|
$260.000
|
$250.000
|
$275.000
|
$210.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
2.000
|
$11,000.000
|
$9,700.000
|
$15,000.000
|
$10,000.000
|
$14,000.000
|
$9,660.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,760.000
|
$1,100.000
|
$2,500.000
|
$1,500.000
|
$1,200.000
|
$1,050.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
46.000
|
$215.000
|
$300.000
|
$230.000
|
$300.000
|
$310.000
|
$69.000
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
11.000
|
$300.000
|
$365.000
|
$250.000
|
$400.000
|
$380.000
|
$79.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 2
|
EA
|
1.000
|
$450.000
|
$480.000
|
$310.000
|
$500.000
|
$500.000
|
$153.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
14.000
|
$475.000
|
$568.000
|
$490.000
|
$600.000
|
$595.000
|
$79.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
11.000
|
$525.000
|
$775.000
|
$620.000
|
$800.000
|
$800.000
|
$164.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
|
EA
|
2.000
|
$670.000
|
$735.000
|
$830.000
|
$800.000
|
$770.000
|
$120.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$620.000
|
$750.000
|
$700.000
|
$800.000
|
$785.000
|
$122.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
3.000
|
$525.000
|
$770.000
|
$620.000
|
$800.000
|
$810.000
|
$175.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
6.000
|
$630.000
|
$900.000
|
$750.000
|
$900.000
|
$935.000
|
$231.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$775.000
|
$815.000
|
$670.000
|
$800.000
|
$850.000
|
$105.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
1.000
|
$850.000
|
$1,000.000
|
$920.000
|
$1,100.000
|
$1,050.000
|
$208.000
|
|
|
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
|
EA
|
2.000
|
$1,750.000
|
$1,450.000
|
$1,600.000
|
$1,500.000
|
$1,500.000
|
$1,650.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
78.000
|
$340.000
|
$425.000
|
$300.000
|
$500.000
|
$445.000
|
$65.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
1.000
|
$500.000
|
$510.000
|
$400.000
|
$500.000
|
$530.000
|
$98.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
107.000
|
$75.000
|
$100.000
|
$80.000
|
$100.000
|
$105.000
|
$70.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
|
EA
|
19.000
|
$30.000
|
$15.750
|
$42.000
|
$30.000
|
$26.000
|
$4.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
12.000
|
$60.000
|
$47.250
|
$130.000
|
$55.000
|
$85.000
|
$20.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
29.000
|
$30.000
|
$21.000
|
$60.000
|
$30.000
|
$32.000
|
$7.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
9,887.000
|
$0.200
|
$0.130
|
$0.130
|
$0.140
|
$0.130
|
$0.350
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
101,435.000
|
$0.250
|
$0.130
|
$0.130
|
$0.140
|
$0.130
|
$0.200
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
24,332.000
|
$0.200
|
$0.130
|
$0.130
|
$0.140
|
$0.130
|
$0.200
|
|
|
WK ZN PAV MRK REMOV (W)4"(BRK)
|
LF
|
9,887.000
|
$0.750
|
$1.000
|
$1.060
|
$1.000
|
$1.400
|
$1.100
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
24,332.000
|
$0.600
|
$1.000
|
$1.060
|
$1.000
|
$1.400
|
$0.550
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
5,202.000
|
$0.750
|
$1.000
|
$0.460
|
$2.000
|
$1.200
|
$0.800
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
978.000
|
$0.350
|
$1.050
|
$1.050
|
$1.100
|
$1.400
|
$1.250
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
150.000
|
$2.000
|
$1.050
|
$1.050
|
$1.100
|
$1.100
|
$0.850
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
356.000
|
$3.000
|
$5.780
|
$5.780
|
$6.000
|
$6.050
|
$6.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
10,220.000
|
$0.350
|
$0.530
|
$0.530
|
$0.550
|
$0.550
|
$0.300
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
102,230.000
|
$0.350
|
$0.400
|
$0.400
|
$0.420
|
$0.420
|
$0.310
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
2,062.000
|
$0.350
|
$0.530
|
$0.530
|
$0.550
|
$0.550
|
$0.300
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
96,723.000
|
$0.350
|
$0.400
|
$0.400
|
$0.420
|
$0.420
|
$0.280
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
8.000
|
$200.000
|
$189.000
|
$189.000
|
$220.000
|
$200.000
|
$200.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
2.000
|
$255.000
|
$262.500
|
$262.500
|
$300.000
|
$275.000
|
$265.000
|
|
PREFAB PAV MRK TY C (W) (RR XING)
|
EA
|
1.000
|
$525.000
|
$787.500
|
$787.500
|
$800.000
|
$825.000
|
$545.000
|
|
REFL PAV MRKR TY I-A
|
EA
|
196.000
|
$2.500
|
$3.360
|
$3.360
|
$4.000
|
$3.500
|
$3.800
|
|
REFL PAV MRKR TY I-C
|
EA
|
591.000
|
$2.500
|
$3.360
|
$3.360
|
$4.000
|
$3.500
|
$3.100
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,465.000
|
$2.500
|
$3.360
|
$3.360
|
$4.000
|
$3.500
|
$3.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
100.000
|
$125.000
|
$125.000
|
$200.000
|
$150.000
|
$80.000
|
$75.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$10,000.000
|
$5,000.000
|
$15,000.000
|
$15,000.000
|
$9,400.000
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$10,000.000
|
$7,000.000
|
$15,000.000
|
$25,000.000
|
$15,000.000
|
$12,800.000
|
|
Totals: |
$8,246,557.470
|
$8,257,306.230
|
$8,631,614.440
|
$8,755,569.220
|
$8,816,557.970
|
$9,034,278.230
|