Show Job Controls
Bid Cobra

CHEROKEE SH 204 (0198-07-015)

Items: 16

County: CHEROKEE
Length: N/A
Highway: SH 204
District: TYLER
Control Number: 0198-07-015
DBE Goal: N/A
Project: STP 2019(882)HESG
Guaranty: N/A
Time: 67 WORKING DAYS
Engineer's Estimate: $656,699.00
Date: 05/08/2019 (7 years ago)
Contract Number: N/A
Type: CENTERLINE & PROFILE PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$656,699.00
$562,313.80
Over/Under Est: -14.37% -$94,385.20
Over/Under Est: -12.35% -$81,106.64
Amt Left: 2.36% $13,278.56
Over/Under Est: -1.59% -$10,444.25
Amt Left: 14.93% $83,940.95
Delta: -12.28% -$70,662.39
Over/Under Est: 2.13% $13,963.60
Amt Left: 19.27% $108,348.80
Delta: -3.78% -$24,407.85

Bid Items & Bid Tabulations

16 Total 0 of 16
CHEROKEE  |  SH 204  |  TYLER  |  0198-07-015  |  05/08/2019  |  $656,699.00  |  STP 2019(882)HESG  |  CENTERLINE & PROFILE PAVMT MRK  |  67 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
STRIPE-A-ZONE, INC.
TOTAL HIGHWAY MAINTENANCE, LLC
TRP CONSTRUCTION GROUP, LLC
STRIPING TECHNOLOGY, L.P.
MOBILIZATION
LS 1.000 $13,000.000 $2,500.000 $24,500.000 $30,000.000 $20,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $1.000 $1,300.000 $3,000.000 $2,500.000
PAVEMENT SEALER 4"
LF 3,325.000 $0.500 $1.000 $0.500 $1.250 $0.500
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,720.000 $0.300 $0.350 $0.340 $0.350 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 11,600.000 $0.300 $0.350 $0.340 $0.300 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 10,620.000 $0.300 $0.350 $0.340 $0.350 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 43,260.000 $0.300 $0.350 $0.340 $0.300 $0.500
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 653,800.000 $0.540 $0.510 $0.500 $0.540 $0.550
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 14,010.000 $0.550 $0.550 $0.500 $0.600 $1.000
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 284,410.000 $0.600 $0.510 $0.500 $0.550 $0.600
REFL PAV MRKR TY I-C
EA 86.000 $3.000 $2.600 $2.480 $15.000 $2.550
REFL PAV MRKR TY II-A-A
EA 14,396.000 $2.500 $2.600 $2.480 $3.000 $2.550
ELIM EXT PAV MRK & MRKS (4")
LF 3,325.000 $1.000 $1.000 $0.700 $1.000 $1.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 1,160.000 $5.000 $4.400 $6.000 $6.000 $15.000
TMA (STATIONARY)
EA 2.000 $2,500.000 $10.000 $1.000 $2,500.000 $75.000
TMA (MOBILE OPERATION)
DAY 67.000 $300.000 $10.000 $1.000 $25.000 $50.000
Totals: $656,699.000 $562,313.800 $575,592.360 $646,254.750 $670,662.600