Show Job Controls
Bid Cobra

CHAMBERS IH0010 (6326-82-001)

Items: 22

County: CHAMBERS
Length: N/A
Highway: IH0010
District: BEAUMONT
Control Number: 6326-82-001
DBE Goal: N/A
Project: BPM - 632682001
Guaranty: N/A
Time: 30 W
Engineer's Estimate: $307,119.17
Date: 03/06/2018 (8 years ago)
Contract Number: N/A
Type: RAIL UPGRADE/JOINT/CONCRETE REP/CLEAN&SE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$307,119.17
$335,275.50
Over/Under Est: 9.17% $28,156.33
Over/Under Est: 14.74% $45,255.83
Amt Left: 5.1% $17,099.50
Over/Under Est: 33.13% $101,739.13
Amt Left: 21.95% $73,582.80
Delta: -16.03% -$56,483.30
Over/Under Est: 37.73% $115,882.33
Amt Left: 26.17% $87,726.00
Delta: -3.46% -$14,143.20
Over/Under Est: 57.95% $177,990.83
Amt Left: 44.69% $149,834.50
Delta: -14.68% -$62,108.50
Over/Under Est: 84.51% $259,559.98
Amt Left: 69.02% $231,403.65
Delta: -16.81% -$81,569.15

Bid Items & Bid Tabulations

22 Total 0 of 22
CHAMBERS  |  IH0010  |  BEAUMONT  |  6326-82-001  |  03/06/2018  |  $307,119.17  |  BPM - 632682001  |  RAIL UPGRADE/JOINT/CONC REP/CLEAN&SE  |  30 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
OLDCASTLE MATERIALS TEXAS, INC.
ISI CONTRACTING, INC.
WIDGEON CONSTRUCTION, INC.
FNH CONSTRUCTION, LLC
CHAMPION INFRASTRUCTURE, LLC
SCR CIVIL CONSTRUCTION, LLC
REMOVING CONC (MISC)
SY 25.000 $20.000 $245.000 $33.000 $210.000 $25.000 $200.000 $50.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 8.000 $75.000 $510.000 $310.000 $165.000 $150.000 $250.000 $1,200.000
FLOWABLE BACKFILL
CY 13.000 $250.000 $470.000 $235.000 $177.000 $350.000 $230.000 $670.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 157.000 $150.000 $210.000 $160.000 $165.000 $165.000 $390.000 $473.000
RIPRAP (MOW STRIP)(4 IN)
CY 80.000 $450.000 $440.000 $560.000 $645.000 $550.000 $640.000 $1,150.000
CLEANING AND SEALING EXISTING JOINTS
LF 1,152.000 $22.000 $20.000 $20.000 $33.600 $55.000 $42.000 $33.000
RAIL (TY SSTR)
LF 283.000 $50.000 $63.000 $130.000 $153.500 $185.000 $240.000 $268.000
RETROFIT RAIL (TY T131RC)
LF 310.000 $175.000 $145.000 $170.000 $174.000 $165.000 $210.000 $246.000
MOBILIZATION
LS 1.000 $27,000.000 $35,000.000 $35,000.000 $9,845.000 $40,000.000 $40,000.000 $33,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,500.000 $2,500.000 $4,700.000 $21,445.000 $15,000.000 $4,000.000 $7,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,147.000 $22.000 $19.000 $22.000 $25.000 $18.500 $28.000 $22.400
MTL W-BEAM GD FEN (STEEL POST)
LF 300.000 $25.000 $43.000 $48.000 $48.000 $35.000 $35.000 $74.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $1,786.740 $2,300.000 $2,500.000 $2,500.000 $1,850.000 $2,100.000 $1,675.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,250.000 $1,900.000 $1,100.000 $1,020.000 $1,850.000 $1,300.000 $1,230.000
REMOVE METAL BEAM GUARD FENCE
LF 2,539.000 $2.750 $7.500 $2.000 $4.800 $3.000 $5.000 $5.650
REMOVE TERMINAL ANCHOR SECTION
EA 12.000 $150.000 $215.000 $75.000 $190.000 $500.000 $300.000 $85.000
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $2,500.000 $2,350.000 $2,750.000 $1,950.000 $2,500.000 $2,800.000 $2,400.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 1.000 $2,330.000 $1,100.000 $425.000 $1,680.000 $1,500.000 $750.000 $1,565.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 29.000 $25.000 $24.000 $12.000 $25.000 $100.000 $200.000 $25.000
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 81.000 $100.000 $150.000 $100.000 $178.400 $20.000 $75.000 $240.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 3.000 $70.000 $170.000 $360.000 $274.000 $1,000.000 $250.000 $130.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,900.000 $1,900.000 $4,200.000 $6,500.000 $3,500.000 $4,000.000 $6,600.000
Totals: $307,119.170 $335,275.500 $352,375.000 $408,858.300 $423,001.500 $485,110.000 $566,679.150