CHAMBERS FM 565 (1024-01-078)

Items: 30

County: CHAMBERS
Length: N/A
Highway: FM 565
District: BEAUMONT
Control Number: 1024-01-078
DBE Goal: N/A
Project: STP 1802(599)HES
Guaranty: N/A
Time: 26 WORKING DAYS
Engineer's Estimate: $140,986.92
Date: 05/08/2020 (6 years ago)
Contract Number: N/A
Type: SFT- SAFETY IMPROVEMENT PROJECTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$140,986.92
$206,938.90
Over/Under Est: 46.78% $65,951.98
Over/Under Est: 119.61% $168,627.58
Amt Left: 49.62% $102,675.60
Over/Under Est: 131.81% $185,841.13
Amt Left: 57.93% $119,889.15
Delta: -5.56% -$17,213.55

Bid Items & Bid Tabulations

30 Total 0 of 30
CHAMBERS  |  FM 565  |  BEAUMONT  |  1024-01-078  |  05/08/2020  |  $140,986.92  |  STP 1802(599)HES  |  SFT- SAFETY IMPRV PROJECTS  |  26 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
FNH CONSTRUCTION, LLC
ISI CONTRACTING, INC.
SUBGRADE WIDENING (ORD COMP)
STA 6.610 $420.000 $1,350.000 $450.000 $1,500.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 200.000 $20.000 $42.000 $50.000 $33.000
BACKFILL (TY A OR B)
STA 10.000 $200.000 $260.000 $450.000 $550.000
BLOCK SODDING
SY 8.000 $5.300 $15.100 $100.000 $65.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 368.000 $0.350 $3.050 $2.000 $13.000
VEGETATIVE WATERING
MG 0.320 $16.000 $630.000 $3,000.000 $13,000.000
ASPHALT STAB BASE (GR 2)(PG 70)
TON 68.000 $120.000 $185.000 $200.000 $250.000
D-GR HMA (SQ) TY-D PG 70-22(LEVEL-UP)
TON 601.000 $80.000 $105.000 $150.000 $180.000
TACK COAT
GAL 298.000 $4.000 $7.000 $10.000 $6.600
PLAN & TEXT ASPH CONC PAV (1.5")
SY 289.000 $1.500 $31.000 $20.000 $53.000
RC PIPE (CL III)(24 IN)
LF 12.000 $75.000 $305.000 $150.000 $400.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 2.000 $765.000 $1,500.000 $2,500.000 $3,300.000
REMOV STR (SET)
EA 2.000 $450.000 $610.000 $1,500.000 $2,000.000
MOBILIZATION
LS 1.000 $15,000.000 $20,000.000 $30,000.000 $30,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $2,500.000 $1,500.000 $8,500.000 $1,300.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 367.000 $8.200 $5.600 $18.000 $5.600
BIODEG EROSN CONT LOGS (REMOVE)
LF 367.000 $1.680 $1.050 $9.000 $1.250
DRIVEWAYS AND TURNOUTS (SURF TREAT)
SY 132.000 $27.800 $48.000 $45.000 $35.000
RUMBLE STRIPS (SHOULDER)
LF 2,000.000 $0.140 $2.550 $5.000 $5.600
RUMBLE STRIPS (CENTERLINE)
LF 1,000.000 $0.150 $3.000 $5.000 $8.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 1.000 $290.000 $300.000 $850.000 $325.000
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
EA 33.000 $100.000 $43.000 $100.000 $85.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 76.000 $0.990 $5.750 $5.000 $0.800
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 2,000.000 $0.360 $0.860 $5.000 $2.500
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 120.000 $0.300 $1.050 $5.000 $3.000
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 1,520.000 $0.300 $0.860 $5.000 $2.150
REFL PAV MRKR TY II-A-A
EA 17.000 $3.300 $12.050 $15.000 $6.500
SP MIXES SP-C SAC-A PG76-22
TON 249.000 $120.000 $134.000 $200.000 $228.000
TMA (STATIONARY)
DAY 30.000 $250.000 $400.000 $500.000 $295.000
TMA (MOBILE OPERATION)
DAY 2.000 $400.000 $102.000 $850.000 $500.000
Totals: $140,986.920 $206,938.900 $309,614.500 $326,828.050