CHAMBERS FM 565 (1024-01-042)
Items: 92
County: CHAMBERS
Length: N/A
Highway: FM 565
District: BEAUMONT
Control Number: 1024-01-042
DBE Goal: N/A
Project: STP 2018(850)
Guaranty: N/A
Time: 0 X
Engineer's Estimate: $8,262,078.83
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: RECONSTRUCT AND REALIGN EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$8,262,078.83 | |||
| $6,739,978.21 |
-18.42%
-$1,522,100.62
|
|||
| $7,744,949.20 |
-6.26%
-$517,129.63
|
14.91%
$1,004,970.99
|
||
| $8,232,717.83 |
-0.36%
-$29,361.00
|
22.15%
$1,492,739.62
|
-6.30%
-$487,768.63
|
|
| $8,382,726.90 |
1.46%
$120,648.07
|
24.37%
$1,642,748.69
|
-1.82%
-$150,009.07
|
|
| $9,719,046.70 |
17.63%
$1,456,967.87
|
44.2%
$2,979,068.49
|
-15.94%
-$1,336,319.80
|
|
| $9,723,914.00 |
17.69%
$1,461,835.17
|
44.27%
$2,983,935.79
|
-0.05%
-$4,867.30
|
E
Engineer's Estimate
$8,262,078.83
1
Awarded
$6,739,978.21
Over/Under Est:
-18.42%
-$1,522,100.62
$7,744,949.20
Over/Under Est:
-6.26%
-$517,129.63
Amt Left:
14.91%
$1,004,970.99
$8,232,717.83
Over/Under Est:
-0.36%
-$29,361.00
Amt Left:
22.15%
$1,492,739.62
Delta:
-6.30%
-$487,768.63
$8,382,726.90
Over/Under Est:
1.46%
$120,648.07
Amt Left:
24.37%
$1,642,748.69
Delta:
-1.82%
-$150,009.07
$9,719,046.70
Over/Under Est:
17.63%
$1,456,967.87
Amt Left:
44.2%
$2,979,068.49
Delta:
-15.94%
-$1,336,319.80
$9,723,914.00
Over/Under Est:
17.69%
$1,461,835.17
Amt Left:
44.27%
$2,983,935.79
Delta:
-0.05%
-$4,867.30
Bid Items & Bid Tabulations
92
Total
0 of 92