CHAMBERS SH 73 (0508-03-115)
Items: 17
County: CHAMBERS
Length: N/A
Highway: SH 73
District: BEAUMONT
Control Number: 0508-03-115
DBE Goal: N/A
Project: STP 2023(581)HES
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $4,685,275.00
Date: 04/04/2023 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ROBERTO RODRIGUEZ
NYEMB NYEMB
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$4,685,275.00 | |||
| $3,456,563.00 |
-26.22%
-$1,228,712.00
|
|||
| $3,800,568.00 |
-18.88%
-$884,707.00
|
9.95%
$344,005.00
|
||
| $4,199,793.86 |
-10.36%
-$485,481.14
|
21.5%
$743,230.86
|
-10.50%
-$399,225.86
|
|
| $4,883,887.00 |
4.24%
$198,612.00
|
41.29%
$1,427,324.00
|
-16.29%
-$684,093.14
|
E
Engineer's Estimate
$4,685,275.00
1
Awarded
$3,456,563.00
Over/Under Est:
-26.22%
-$1,228,712.00
$3,800,568.00
Over/Under Est:
-18.88%
-$884,707.00
Amt Left:
9.95%
$344,005.00
$4,199,793.86
Over/Under Est:
-10.36%
-$485,481.14
Amt Left:
21.5%
$743,230.86
Delta:
-10.50%
-$399,225.86
$4,883,887.00
Over/Under Est:
4.24%
$198,612.00
Amt Left:
41.29%
$1,427,324.00
Delta:
-16.29%
-$684,093.14
| Subcontractor | Percentage | Amount |
|---|---|---|
| J. H. ODEN CONTRACTING COMPANY | 8.51% | $279,614.18 |
| JB PINNACLE GROUP, LLC | 5.64% | $185,314.21 |
| LONESTAR TRAFFIC SAFETY, LLC | 0.28% | $9,200.00 |
| Total: | 14.43% | $474,128.39 |