CHAMBERS SH 73 (0508-03-115)

Items: 17

County: CHAMBERS
Length: N/A
Highway: SH 73
District: BEAUMONT
Control Number: 0508-03-115
DBE Goal: N/A
Project: STP 2023(581)HES
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $4,685,275.00
Date: 04/04/2023 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ROBERTO RODRIGUEZ
NYEMB NYEMB
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$4,685,275.00
$3,456,563.00
Over/Under Est: -26.22% -$1,228,712.00
Over/Under Est: -18.88% -$884,707.00
Amt Left: 9.95% $344,005.00
Over/Under Est: -10.36% -$485,481.14
Amt Left: 21.5% $743,230.86
Delta: -10.50% -$399,225.86
$4,883,887.00
Over/Under Est: 4.24% $198,612.00
Amt Left: 41.29% $1,427,324.00
Delta: -16.29% -$684,093.14
Subcontractor Percentage Amount
J. H. ODEN CONTRACTING COMPANY 8.51% $279,614.18
JB PINNACLE GROUP, LLC 5.64% $185,314.21
LONESTAR TRAFFIC SAFETY, LLC 0.28% $9,200.00
Total: 14.43% $474,128.39

Bid Items & Bid Tabulations

17 Total 0 of 17
CHAMBERS  |  SH 73  |  BEAUMONT  |  0508-03-115  |  04/04/2023  |  $4,685,275.00  |  STP 2023(581)HES  |  HAZARD ELIM & SAFETY  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SCR CIVIL CONSTRUCTION, LLC
MASSANA CONSTRUCTION INC.
ROADWAY SPECIALTIES, INC.
FNH CONSTRUCTION, LLC
EXCAVATION (ROADWAY)
CY 918.000 $20.000 $30.000 $55.000 $25.090 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 703.000 $25.000 $55.000 $60.000 $35.000 $50.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 675.000 $30.000 $55.000 $60.000 $50.000 $50.000
BULLDOZER WORK
HR 68.000 $150.000 $190.000 $160.000 $108.460 $150.000
FURNISHING AND PLACING TOPSOIL (3")
SY 36,884.000 $20.000 $2.500 $4.000 $4.500 $8.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 174,300.000 $0.500 $0.350 $0.400 $0.520 $0.750
VEGETATIVE WATERING
MG 2,960.000 $14.000 $60.000 $62.000 $50.000 $50.000
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 1,110.000 $2.000 $6.000 $2.100 $2.690 $6.500
RIPRAP (MOW STRIP)(4 IN)
CY 3,448.000 $450.000 $440.000 $350.000 $415.000 $525.000
MOBILIZATION
LS 1.000 $350,000.000 $98,500.000 $394,511.000 $606,440.350 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $5,000.000 $3,750.000 $12,500.000 $1,551.550 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,960.000 $7.000 $11.450 $8.000 $8.090 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,960.000 $2.000 $1.100 $5.000 $2.500 $9.000
CABLE BARRIER SYSTEM (TL-4)
LF 92,135.000 $16.000 $12.000 $12.000 $15.890 $17.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 54.000 $4,500.000 $3,000.000 $6,500.000 $2,870.540 $3,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $11,000.000 $3,500.000 $2,500.000 $2,405.500 $16,500.000
TMA (STATIONARY)
DAY 120.000 $250.000 $425.000 $500.000 $35.380 $250.000
Totals: $4,685,275.000 $3,456,563.000 $3,800,568.000 $4,199,793.860 $4,883,887.000