Job Info for 0919-00-085

County: CASS Highway: VA Date: 01/04/2024 (10 months ago) Engineer's Estimate: $2,154,877 Control Number: 0919-00-085
Project: C 919-00-85 District: ATLANTA Time: 102 WORKING DAYS Type: HIGHWAY IMPROVEMENT
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,154,877.25
STRIPE-A-ZONE, LLC   $2,925,770.24 1
35.77% | $770,892.99
STRIPING TECHNOLOGY, L.P.   $3,206,526.25 2
48.8% | $1,051,649.00
9.6% | $280,756.01
TRAFFIC HIGHWAY MAINTENANCE, LLC   $3,633,716.31 3
68.63% | $1,478,839.06
24.2% | $707,946.07
13.32% | $427,190.06
TRP CONSTRUCTION GROUP, LLC   $4,992,327.15 4
131.68% | $2,837,449.90
70.63% | $2,066,556.91
37.39% | $1,358,610.84
INTERSTATE BARRICADES & MARKINGS, INC.   $5,246,626.40 5
143.48% | $3,091,749.15
79.32% | $2,320,856.16
5.09% | $254,299.25

Bid Items

Items: 11, 0 filtered
CASS VA  |  ATLANTA  |  0919-00-085  |  01/04/2024  |  $2,154,877  |  C 919-00-85  |  HWY IMPRV  |  102 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPE-A-ZONE, LLC STRIPING TECHNOLOGY, L.P. TRAFFIC HIGHWAY MAINTENANCE, LLC TRP CONSTRUCTION GROUP, LLC INTERSTATE BARRICADES & MARKINGS, INC.
500 6001 MOBILIZATION LS 1.000 $100,000.000 $40,000.000 $25,000.000 $47,000.000 $150,000.000 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $1,000.000 $1,000.000 $500.000 $1,500.000 $5,000.000 $25,000.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 1,600.000 $1.500 $1.250 $1.350 $1.500 $1.050 $1.250
666 6285 REF PROF PAV MRK TY I(W)6"(SLD)(090MIL) LF 799,067.000 $0.450 $0.760 $0.750 $0.900 $1.450 $1.250
6056 6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP LF 144,250.000 $2.750 $3.900 $4.350 $4.000 $5.900 $6.350
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 136,621.000 $2.750 $3.900 $4.350 $4.000 $5.900 $6.350
6149 6004 REFL PAV MRK AWT (W) 6" (SLD) (100MIL) LF 886,607.000 $0.400 $0.520 $0.600 $0.740 $0.900 $0.950
6149 6005 REFL PAV MRK AWT (W) 6" (BRK) (100MIL) LF 19,005.000 $0.650 $0.580 $0.850 $0.810 $1.000 $0.950
6149 6010 REFL PAV MRK AWT (Y) 6" (SLD) (100MIL) LF 1,203,102.000 $0.400 $0.540 $0.600 $0.740 $0.900 $0.950
6149 6011 REFL PAV MRK AWT (Y) 6" (BRK) (100MIL) LF 94,930.000 $0.500 $0.560 $0.750 $0.810 $1.000 $0.950
6185 6005 TMA (MOBILE OPERATION) DAY 188.000 $100.000 $1.000 $75.000 $500.000 $1.000 $100.000
Totals: $2,154,877.25 $2,925,770.24 $3,206,526.25 $3,633,716.31 $4,992,327.15 $5,246,626.40