Job Info for 0919-00-081

County: CASS Highway: VA Date: 01/06/2022 (2 years ago) Engineer's Estimate: $1,146,416 Control Number: 0919-00-081
Project: F 2022(293) District: ATLANTA Time: 57 WORKING DAYS Type: SEAL COAT PAVEMENT MARKINGS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,146,416.40
STRIPING TECHNOLOGY, L.P.   $934,909.00 1
-18.45% | -$211,507.40
STRIPE-A-ZONE, LLC   $996,679.87 2
-13.06% | -$149,736.53
6.61% | $61,770.87
TRP CONSTRUCTION GROUP, LLC   $1,197,553.84 3
4.46% | $51,137.44
28.09% | $262,644.84
20.15% | $200,873.97
TOTAL HIGHWAY MAINTENANCE, LLC   $1,200,976.58 4
4.76% | $54,560.18
28.46% | $266,067.58
0.29% | $3,422.74

Bid Items

Items: 15, 0 filtered
CASS VA  |  ATLANTA  |  0919-00-081  |  01/06/2022  |  $1,146,416  |  F 2022(293)  |  SEAL COAT PAVMT MRK  |  57 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPING TECHNOLOGY, L.P. STRIPE-A-ZONE, LLC TRP CONSTRUCTION GROUP, LLC TOTAL HIGHWAY MAINTENANCE, LLC
500 6001 MOBILIZATION LS 1.000 $100,000.000 $1.000 $1.000 $42,500.000 $35,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $7,000.000 $1.000 $1.000 $500.000 $2,500.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 2,981.000 $1.000 $1.000 $1.200 $0.800 $1.000
666 6283 REF PROF PAV MRK TY I(W)4"(SLD)(090MIL) LF 220,368.000 $0.450 $0.520 $0.550 $0.560 $0.480
6056 6001 PREFORMED IN-LANE(TRANS) RUMBLE STRIP LF 42,939.000 $3.000 $2.900 $2.900 $3.400 $4.100
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 43,912.000 $3.500 $2.900 $2.900 $3.400 $4.100
6149 6001 REFL PAV MRK AWT (W) 4" (SLD) (100MIL) LF 560,631.000 $0.380 $0.340 $0.390 $0.440 $0.420
6149 6002 REFL PAV MRK AWT (W) 4" (BRK) (100MIL) LF 13,150.000 $0.450 $0.500 $0.440 $0.480 $0.460
6149 6004 REFL PAV MRK AWT (W) 6" (SLD) (100MIL) LF 172,012.000 $0.550 $0.450 $0.480 $0.640 $0.540
6149 6005 REFL PAV MRK AWT (W) 6" (BRK) (100MIL) LF 21,790.000 $0.600 $0.650 $0.510 $0.680 $0.590
6149 6007 REFL PAV MRK AWT (Y) 4" (SLD) (100MIL) LF 582,564.000 $0.380 $0.350 $0.390 $0.440 $0.430
6149 6008 REFL PAV MRK AWT (Y) 4" (BRK) (100MIL) LF 23,170.000 $0.400 $0.500 $0.440 $0.480 $0.470
6149 6010 REFL PAV MRK AWT (Y) 6" (SLD) (100MIL) LF 130,392.000 $0.550 $0.450 $0.480 $0.640 $0.560
6149 6011 REFL PAV MRK AWT (Y) 6" (BRK) (100MIL) LF 3,830.000 $0.500 $0.650 $0.490 $0.680 $0.610
6185 6005 TMA (MOBILE OPERATION) DAY 57.000 $50.000 $1.000 $1.000 $10.000 $125.000
Totals: $1,146,416.40 $934,909.00 $996,679.87 $1,197,553.84 $1,200,976.58