CASS US 59 (0218-04-121)

Items: 36

County: CASS
Length: N/A
Highway: US 59
District: ATLANTA
Control Number: 0218-04-121
DBE Goal: N/A
Project: STP 2020(042)HES
Guaranty: N/A
Time: 72 WORKING DAYS
Engineer's Estimate: $2,189,321.30
Date: 08/06/2020 (5 years ago)
Contract Number: N/A
Type: HIGH FRICTION SURFACE TREATMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,189,321.30
$2,417,417.00
Over/Under Est: 10.42% $228,095.70
$2,574,444.80
Over/Under Est: 17.59% $385,123.50
Amt Left: 6.5% $157,027.80
Over/Under Est: 21.07% $461,327.30
Amt Left: 9.65% $233,231.60
Delta: -2.96% -$76,203.80
Over/Under Est: 44.11% $965,678.70
Amt Left: 30.51% $737,583.00
Delta: -19.03% -$504,351.40

Bid Items & Bid Tabulations

36 Total 0 of 36
CASS  |  US 59  |  ATLANTA  |  0218-04-121  |  08/06/2020  |  $2,189,321.30  |  STP 2020(042)HES  |  HIGH FRICTION SURF TREATMENT  |  72 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE TRUESDELL CORPORATION
DEANGELO BROTHERS LLC
EAST TEXAS BRIDGE, INC.
AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC
BACKFILL (TY C)
STA 96.000 $300.000 $500.000 $550.000 $425.000 $500.000
D-GR HMA(SQ) TY-F PG64-22
TON 1,941.000 $150.000 $200.000 $220.000 $175.000 $200.000
TACK COAT
GAL 2,823.000 $3.000 $8.000 $9.000 $5.000 $8.000
MOBILIZATION
LS 1.000 $141,000.000 $70,001.400 $161,400.000 $250,000.000 $250,251.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $4,000.000 $11,000.000 $1,500.000 $15,000.000 $15,000.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 16,460.000 $0.180 $0.220 $0.250 $0.500 $0.200
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 16,460.000 $0.200 $0.220 $0.250 $0.500 $0.200
RUMBLE STRIPS (CENTERLINE) CONCRETE
LF 3,280.000 $0.900 $0.650 $1.500 $2.000 $1.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 18,980.000 $0.200 $0.250 $0.500 $0.300 $0.300
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 18,980.000 $0.800 $1.000 $0.900 $1.100 $1.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,662.000 $0.900 $0.950 $1.500 $2.000 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 959.000 $0.900 $1.000 $1.500 $2.000 $2.000
PAVEMENT SEALER 6"
LF 15,020.000 $0.200 $0.250 $0.200 $0.270 $0.300
PREFAB PAV MRK TY C (W) (ARROW)
EA 12.000 $200.000 $215.000 $300.000 $250.000 $250.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 4.000 $260.000 $250.000 $300.000 $300.000 $275.000
PREFAB PAV MRK TY C (W) (WORD)
EA 4.000 $275.000 $250.000 $400.000 $300.000 $275.000
REFL PAV MRKR TY II-A-A
EA 818.000 $2.950 $3.150 $5.000 $4.000 $3.500
REFL PAV MRKR TY II-C-R
EA 276.000 $3.500 $3.150 $5.000 $4.000 $3.500
ELIM EXT PAV MRK & MRKS (4")
LF 37,960.000 $0.350 $0.350 $0.700 $0.380 $0.400
ELIM EXT PAV MRK & MRKS (6")
LF 19,140.000 $0.460 $0.650 $1.200 $0.720 $0.750
ELIM EXT PAV MRK & MRKS (24")
LF 830.000 $3.500 $3.100 $3.500 $3.300 $3.500
ELIM EXT PAV MRK & MRKS (ARROW)
EA 2.000 $60.000 $125.000 $55.000 $130.000 $135.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 3.000 $60.000 $125.000 $65.000 $130.000 $135.000
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
LF 1,978.000 $0.300 $2.550 $3.450 $2.700 $3.000
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
MI 5.000 $61.000 $975.000 $500.000 $5,000.000 $2,000.000
HIGH FRICTION SURFACE COURSE
SY 96,362.000 $16.000 $16.750 $17.100 $17.000 $21.500
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 4,745.000 $3.200 $4.100 $6.500 $4.400 $5.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 2,373.000 $3.500 $4.100 $6.500 $4.400 $5.000
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
LF 18,980.000 $0.400 $0.450 $0.600 $0.480 $0.500
REFL PAV MRK AWT (W) 6" (SLD) (100MIL)
LF 22,120.000 $0.470 $0.600 $0.800 $0.660 $0.750
REFL PAV MRK AWT (W) 6" (BRK) (100MIL)
LF 5,540.000 $0.550 $0.600 $0.850 $0.660 $0.750
REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)
LF 18,980.000 $0.400 $0.450 $0.550 $0.480 $0.550
REFL PAV MRK AWT (Y) 6" (SLD) (100MIL)
LF 24,640.000 $0.470 $0.600 $0.800 $0.660 $0.750
REFL PAV MRK AWT (Y) 6" (BRK) (100MIL)
LF 3,100.000 $0.500 $0.600 $0.850 $0.660 $0.750
TMA (STATIONARY)
DAY 22.000 $200.000 $300.000 $500.000 $300.000 $500.000
TMA (MOBILE OPERATION)
DAY 32.000 $150.000 $100.000 $65.000 $300.000 $750.000
Totals: $2,189,321.300 $2,417,417.000 $2,574,444.800 $2,650,648.600 $3,155,000.000