Job Info for 0218-03-094

County: CASS Highway: US 59 Date: 01/05/2024 (10 months ago) Engineer's Estimate: $9,753,014 Control Number: 0218-03-094
Project: C 218-3-94 District: ATLANTA Time: 0 X Type: REHABILITATE EXISTING ROADWAY
Bidder's List
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $9,753,014.10
RK HALL, LLC   $9,155,619.99 1
-6.13% | -$597,394.11
EAST TEXAS BRIDGE, INC.   $9,222,213.85 2
-5.44% | -$530,800.25
0.73% | $66,593.86
LONGVIEW BRIDGE AND ROAD, LTD.   $9,788,270.76 3
0.36% | $35,256.66
6.91% | $632,650.77
6.14% | $566,056.91
Subcontractor Percentage Amount
TEXOP CONSTRUCTION 6.32% $493,375.86
STRIPING TECHNOLOGY, L.P. 3.47% $270,888.33
WITHERS CONSTRUCTION, LLC 2.53% $197,506.47
O. TREVINO CONSTRUCTION, LLC 2.38% $185,796.60
SOUTHWEST ENVIRONMENT SERVICES LLC 1.30% $101,485.54
PANOLA SIGN & BARRICADE, INC. 0.38% $29,665.00
DUSTIN ALLEN, INC. 0.35% $27,323.03
BAHENA CONSTRUCTION CO.,INC. 0.29% $22,639.08
ACT SAW CUTTING & REMOVAL 0.25% $19,516.45
INDUSTRIAL FABRICS, INC. 0.21% $16,393.82
SURFACE PREPARATION TECHNOLOGIES, LLC 0.13% $10,148.55
BRENDA PRICE TRUCKING, INC. 0.04% $3,122.63
H. V. CAVER, INC. 0.04% $3,122.63
Total: 17.69% $1,380,983.99

Bid Items

Items: 57, 0 filtered
CASS US 59  |  ATLANTA  |  0218-03-094  |  01/05/2024  |  $9,753,014  |  C 218-3-94  |  REHAB EXIST ROADWAY  |  0 X
Item code Description Unit Quantity Engineer's Estimate RK HALL, LLC EAST TEXAS BRIDGE, INC. LONGVIEW BRIDGE AND ROAD, LTD.
100 6002 PREPARING ROW STA 222.500 $1,500.000 $1,023.500 $1,200.000 $1,500.000
104 6054 REMOVING CONCRETE(MOW STRIP) LF 475.000 $8.830 $18.710 $15.000 $30.000
132 6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C) CY 14.000 $40.000 $220.800 $80.000 $100.000
134 6002 BACKFILL (TY B) STA 334.100 $265.180 $159.800 $300.000 $200.000
164 6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) SY 148,335.000 $0.750 $0.610 $0.620 $0.800
164 6071 BROADCAST SEED (TEMP)(WARM OR COOL) SY 148,335.000 $0.170 $0.120 $0.120 $0.150
168 6001 VEGETATIVE WATERING MG 4,746.700 $10.000 $24.920 $7.000 $15.000
351 6075 FLEX PAVEMENT STRUCTURE REPAIR (2"-4") SY 2,000.000 $45.000 $44.230 $55.000 $100.000
354 6045 PLANE ASPH CONC PAV (2") SY 5,512.000 $4.750 $3.460 $5.000 $2.100
354 6065 PLANE ASPH CONC PAV (3 1/2") SY 144,531.000 $2.500 $3.800 $4.250 $3.100
356 6007 ASPH BINDER(PG 64-22) GAL 1,203.000 $6.000 $5.180 $3.000 $20.000
356 6017 FABRIC SY 5,512.000 $110.000 $3.210 $3.000 $10.000
361 6080 FULL-DEPTH REPAIR CPCD (12"-14") SY 287.000 $287.000 $698.660 $800.000 $475.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 29.000 $600.000 $805.000 $600.000 $1,015.000
500 6001 MOBILIZATION LS 1.000 $665,499.000 $366,224.800 $800,000.000 $725,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $10,000.000 $20,838.310 $20,000.000 $10,500.000
533 6003 RUMBLE STRIPS (SHOULDER) ASPHALT LF 38,279.000 $0.500 $0.170 $0.500 $0.300
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 325.000 $30.000 $31.050 $36.000 $40.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 50.000 $45.000 $105.800 $110.000 $122.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $1,155.000 $1,725.000 $1,500.000 $2,000.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 325.000 $3.000 $5.750 $3.000 $7.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 3.000 $175.000 $575.000 $200.000 $660.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $3,300.000 $4,312.500 $3,200.000 $5,000.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 $275.000 $345.000 $250.000 $400.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 2.000 $785.000 $1,276.500 $1,500.000 $1,500.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 6.000 $496.080 $911.950 $1,000.000 $1,050.000
644 6076 REMOVE SM RD SN SUP&AM EA 10.000 $87.300 $110.400 $150.000 $130.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 6.000 $35.000 $49.390 $60.000 $60.000
662 6008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) LF 34,189.000 $0.500 $0.290 $0.270 $0.350
662 6037 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) LF 36,971.000 $0.500 $0.290 $0.270 $0.350
662 6048 WK ZN PAV MRK REMOV (REFL) TY I-C EA 418.000 $4.500 $4.600 $5.000 $5.300
662 6056 WK ZN PAV MRK REMOV (TRAF BTN) TY W EA 510.000 $4.750 $4.600 $5.000 $5.300
662 6058 WK ZN PAV MRK REMOV (TRAF BTN) TY Y EA 510.000 $4.000 $4.600 $5.000 $5.300
662 6064 WK ZN PAV MRK REMOV (W)6"(BRK) LF 8,355.000 $2.280 $5.800 $4.000 $2.200
662 6112 WK ZN PAV MRK SHT TERM RMV (W)(4") LF 4,234.000 $0.500 $5.800 $2.000 $2.200
666 6227 PAVEMENT SEALER 10" LF 1,338.000 $0.500 $1.150 $1.100 $1.350
668 6010 PREFAB PAV MRK TY B (W)(6")(BRK)CNTST LF 8,375.000 $9.820 $12.650 $12.000 $14.500
668 6070 PREFAB PAV MRK TY C (W) (8") (DOT) LF 814.000 $5.310 $5.750 $5.500 $6.600
668 6072 PREFAB PAV MRK TY C (W) (8") (SLD) LF 5,715.000 $5.500 $5.750 $5.500 $6.600
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 495.000 $20.000 $16.100 $15.000 $18.500
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 1.000 $316.190 $316.250 $300.000 $365.000
672 6007 REFL PAV MRKR TY I-C EA 1,122.000 $3.750 $4.600 $4.500 $5.300
672 6009 REFL PAV MRKR TY II-A-A EA 335.000 $4.500 $4.600 $4.500 $5.300
672 6010 REFL PAV MRKR TY II-C-R EA 702.000 $4.000 $4.600 $4.500 $5.300
677 6002 ELIM EXT PAV MRK & MRKS (6") LF 35,077.000 $0.750 $0.630 $0.600 $0.750
800 6001 NO. OF WORKING DAYS $/D 20,440.000 $66.000 $66.000 $51.000 $60.000
3077 6064 SP MIXES SP-D PG76-22 TON 17,637.740 $175.000 $162.590 $165.000 $175.850
3077 6075 TACK COAT GAL 18,629.000 $6.000 $5.700 $4.000 $7.000
3080 6007 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 TON 11,173.800 $200.000 $212.520 $200.000 $216.800
3080 6029 TACK COAT GAL 10,159.000 $6.000 $6.240 $4.000 $7.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $12,000.000 $13,031.930 $30,000.000 $24,000.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 5,350.000 $5.000 $5.750 $5.500 $6.600
6149 6004 REFL PAV MRK AWT (W) 6" (SLD) (100MIL) LF 35,809.000 $0.750 $0.920 $0.880 $1.100
6149 6010 REFL PAV MRK AWT (Y) 6" (SLD) (100MIL) LF 35,191.000 $0.750 $0.920 $0.880 $1.100
6149 6011 REFL PAV MRK AWT (Y) 6" (BRK) (100MIL) LF 2,695.000 $0.630 $1.150 $1.100 $1.350
6185 6002 TMA (STATIONARY) DAY 74.000 $150.000 $487.710 $300.000 $330.000
6185 6005 TMA (MOBILE OPERATION) DAY 6.000 $200.000 $898.450 $300.000 $330.000
Totals: $9,753,014.10 $9,155,620.01 $9,222,213.85 $9,788,270.77