Job Info for 0275-04-061

County: CARSON Highway: IH 40 Date: 12/05/2023 (11 months ago) Engineer's Estimate: $14,893,249 Control Number: 0275-04-061
Project: BR 2024(461) District: AMARILLO Time: 468 WORKING DAYS Type: BRIDGE MAINTENANCE
Bidder's List
Email All | Notice
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $14,893,248.50
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC   $13,665,830.90 1
-8.24% | -$1,227,417.60
ALTUS CONSTRUCTION LLC   $16,559,110.23 2
11.19% | $1,665,861.73
21.17% | $2,893,279.33
GIBSON & ASSOCIATES, INC.   $17,148,698.13 3
15.14% | $2,255,449.63
25.49% | $3,482,867.23
3.56% | $589,587.90
GILVIN-TERRILL, LTD.   $17,938,471.85 4
20.45% | $3,045,223.35
31.27% | $4,272,640.95
4.61% | $789,773.72
SOUTHERN ROAD & BRIDGE, LLC   $24,854,638.00 5
66.89% | $9,961,389.50
81.87% | $11,188,807.10
38.55% | $6,916,166.15
Subcontractor Percentage Amount
MOBILE ENTERPRISES, INC. 11.18% $1,527,839.89
AARON CONCRETE CONTRACTORS, LLC 10.09% $1,378,882.34
L A FULLER & SONS CONSTRUCTION, LTD. 5.93% $810,383.77
HYDRO TECHNOLOGIES, INC. 3.89% $531,600.82
DIIBS SPECIALISTS, LLC 2.41% $329,346.52
TEXAS CUTTING & CORING GP, INC. 1.65% $225,486.21
RK HALL, LLC 0.73% $99,760.57
BARRICADES UNLIMITED 0.51% $69,695.74
A-CORE CONCRETE CUTTING OF TEXAS, INC. 0.38% $51,930.16
CRANE SERVICES, INC. 0.09% $12,299.25
TRP CONSTRUCTION GROUP, LLC 0.00% $0.00
2H, LLC 0.00% $0.00
Total: 36.86% $5,037,225.27

Bid Items

Items: 96, 0 filtered
CARSON IH 40  |  AMARILLO  |  0275-04-061  |  12/05/2023  |  $14,893,249  |  BR 2024(461)  |  BRIDGE MAINT  |  468 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC ALTUS CONSTRUCTION LLC GIBSON & ASSOCIATES, INC. GILVIN-TERRILL, LTD. SOUTHERN ROAD & BRIDGE, LLC
104 6009 REMOVING CONC (RIPRAP) SY 209.000 $30.000 $50.000 $34.910 $285.000 $25.000 $77.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 18.000 $75.000 $50.000 $104.720 $250.000 $30.000 $95.000
354 6048 PLANE ASPH CONC PAV (3") SY 4,761.000 $5.000 $13.000 $17.660 $7.150 $15.000 $20.000
354 6049 PLANE ASPH CONC PAV (6") SY 1,190.000 $8.000 $22.000 $29.460 $20.350 $15.000 $31.000
354 6064 PLANE ASPH CONC PAV (2 1/2") SY 2,469.000 $5.000 $7.000 $8.590 $7.150 $15.000 $11.000
354 6075 PLANE ASPH CONC PAV (2" TO 6.5") SY 10,354.000 $5.000 $14.000 $17.520 $20.350 $15.000 $16.000
354 6076 PLANE ASPH CONC PAV (6.5") SY 4,597.000 $8.000 $24.000 $30.860 $20.350 $15.000 $30.000
354 6100 PLANE ASPH CONC PAV (5") SY 1,307.000 $8.000 $21.000 $26.250 $20.350 $15.000 $24.000
354 6137 PLANE ASPH CONC PAV (5.5") SY 2,100.000 $8.000 $24.000 $31.410 $20.350 $15.000 $28.000
401 6001 FLOWABLE BACKFILL CY 75.000 $600.000 $400.000 $366.510 $700.000 $500.000 $98.000
420 6066 CL C CONC (RAIL FOUNDATION) CY 121.800 $700.000 $800.000 $942.450 $630.030 $1,000.000 $1,500.000
427 6007 EPOXY WATERPROOF FINISH (TY X) SF 33,917.000 $15.000 $11.000 $19.480 $15.350 $20.000 $13.000
429 6003 CONC STR REPAIR(DECK REP(PART DEPTH)) SF 1,505.000 $180.000 $155.000 $253.570 $75.000 $200.000 $205.000
429 6005 CONC STR REPAIR(DECK REP (FULL DEPTH)) SF 355.000 $220.000 $235.000 $314.150 $190.000 $200.000 $325.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 2,554.000 $230.000 $280.000 $88.380 $212.750 $200.000 $355.000
431 6002 PNEUMATICALLY PLACED CONC (REPAIR) CF 55.000 $200.000 $435.000 $279.240 $840.000 $1,200.000 $650.000
432 6001 RIPRAP (CONC)(4 IN) CY 945.000 $700.000 $800.000 $790.740 $568.460 $600.000 $850.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 594.000 $700.000 $800.000 $977.350 $625.900 $600.000 $850.000
438 6004 CLEANING AND SEALING EXIST JOINTS(CL7) LF 445.000 $55.000 $58.000 $53.150 $42.000 $50.000 $80.000
438 6010 RESIZING AND SEALING JOINTS LF 222.000 $125.000 $52.000 $50.260 $65.000 $50.000 $80.000
439 6001 CONCRETE OVERLAY (1.5 IN) SY 482.000 $90.000 $100.000 $68.070 $177.000 $270.000 $225.000
439 6003 CONCRETE OVERLAY (2.5 IN) SY 4,660.000 $90.000 $110.000 $72.120 $85.000 $280.000 $265.000
439 6004 CONCRETE OVERLAY (3 IN) SY 11,478.000 $105.000 $120.000 $68.920 $149.000 $290.000 $295.000
439 6011 REINFORCED CONCRETE OVERLAY (4.0 IN) SY 2,052.000 $200.000 $150.000 $7.180 $184.000 $295.000 $400.000
450 6023 RAIL (TY SSTR) LF 630.000 $140.000 $145.000 $139.620 $92.320 $90.000 $150.000
450 6054 RAIL (TY SSTR) (W/DRAIN SLOTS) LF 240.000 $165.000 $145.000 $202.450 $93.170 $95.000 $200.000
451 6024 RETROFIT RAIL (TY SSTR) LF 6,109.000 $250.000 $235.000 $256.190 $190.230 $160.000 $400.000
483 6005 HYDRO-DEMOLITION (1 IN) SY 11,178.000 $65.000 $55.000 $43.590 $136.000 $61.600 $115.000
483 6006 HYDRO-DEMOLITION (1 1/2 IN) SY 7,494.000 $70.000 $60.000 $90.010 $100.000 $61.600 $150.000
496 6056 REMOVE STR (STL SECTIONS) LF 35.000 $45.000 $250.000 $39.370 $200.000 $40.000 $250.000
500 6001 MOBILIZATION LS 1.000 $1,200,000.000 $750,000.000 $1,535,480.220 $1,350,000.000 $1,800,000.000 $1,850,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 27.000 $22,000.000 $3,500.000 $41,886.550 $15,500.000 $50,000.000 $15,000.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 1,120.000 $70.000 $35.000 $31.410 $5.000 $35.000 $33.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 1,120.000 $23.000 $15.000 $10.470 $5.000 $10.000 $15.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 10,025.000 $6.000 $10.000 $13.960 $8.250 $8.000 $10.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 10,025.000 $3.000 $3.000 $2.790 $1.650 $2.000 $3.000
512 6017 PORT CTB (DES SOURCE)(F-SHAPE)(TY 1) LF 1,620.000 $35.000 $25.000 $29.320 $23.100 $10.000 $30.000
512 6029 PORT CTB (MOVE)(F-SHAPE)(TY 1) LF 14,580.000 $15.000 $15.000 $20.940 $16.500 $10.000 $20.000
512 6041 PORT CTB (STKPL)(F-SHAPE)(TY 1) LF 1,620.000 $30.000 $20.000 $29.320 $23.100 $10.000 $30.000
514 6001 PERM CTB (SGL SLOPE) (TY 1) (42 ) LF 5,500.000 $155.000 $90.000 $172.660 $126.480 $120.000 $225.000
514 6003 PERM CTB (SGL SLOPE) (TY 3) (42 ) LF 460.000 $200.000 $300.000 $335.090 $260.830 $250.000 $450.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 4,600.000 $33.000 $40.000 $41.890 $33.000 $30.000 $115.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 17.000 $2,750.000 $2,400.000 $3,490.550 $2,750.000 $2,650.000 $3,500.000
540 6010 MTL W-BEAM GD FEN ADJUSTMENT LF 1,850.000 $18.000 $26.000 $20.940 $16.500 $17.000 $25.000
540 6011 MTL THRIE-BEAM GD FEN ADJUSTMENT LF 304.000 $300.000 $150.000 $27.920 $22.000 $40.000 $28.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $1,800.000 $1,600.000 $174.530 $137.500 $1,700.000 $150.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 5,275.000 $3.000 $6.000 $2.790 $2.200 $3.000 $4.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 7.000 $300.000 $350.000 $279.240 $220.000 $300.000 $400.000
542 6003 REMOVE DOWNSTREAM ANCHOR TERMINAL EA 2.000 $300.000 $250.000 $279.240 $220.000 $300.000 $400.000
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 6.000 $5,000.000 $4,200.000 $6,981.090 $5,500.000 $2,600.000 $8,500.000
543 6021 REMOVE CABLE BARRIER LF 260.000 $4.250 $8.000 $6.980 $5.500 $5.000 $8.000
543 6022 REMOVE CABLE BARRIER TERMINAL SECTION EA 6.000 $500.000 $850.000 $2,094.330 $1,650.000 $500.000 $2,000.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 15.000 $3,500.000 $3,500.000 $4,537.710 $3,575.000 $3,200.000 $4,500.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 7.000 $300.000 $350.000 $279.240 $220.000 $300.000 $400.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 18.000 $3,000.000 $3,000.000 $3,490.550 $2,750.000 $3,750.000 $3,500.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $2,000.000 $1,500.000 $2,094.330 $1,650.000 $2,150.000 $2,500.000
545 6007 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) EA 14.000 $27,500.000 $30,000.000 $34,718.570 $38,500.000 $34,000.000 $45,400.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 2.000 $26,000.000 $10,000.000 $10,471.640 $8,250.000 $9,800.000 $9,500.000
636 6011 REPLACE EXISTING ALUMINUM SIGNS (TY O) EA 14.000 $1,000.000 $100.000 $6,981.090 $5,500.000 $2,000.000 $7,500.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 2.000 $1,000.000 $750.000 $1,396.220 $1,100.000 $2,500.000 $2,000.000
644 6074 RELOCATE SM RD SN SUP&AM(RAIL MOUNT) EA 3.000 $7,000.000 $4,500.000 $6,981.090 $5,500.000 $3,000.000 $7,500.000
658 6013 INSTL DEL ASSM (D-SW)SZ (BRF)CTB EA 43.000 $40.000 $50.000 $83.770 $66.000 $52.500 $80.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 8.000 $35.000 $50.000 $83.770 $66.000 $54.950 $80.000
658 6026 INSTL DEL ASSM (D-SY)SZ (BRF)CTB EA 30.000 $25.000 $50.000 $83.770 $66.000 $54.500 $80.000
658 6061 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 EA 87.000 $45.000 $55.000 $69.810 $55.000 $62.500 $80.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 8.000 $45.000 $60.000 $69.810 $55.000 $69.500 $80.000
658 6064 INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 EA 25.000 $40.000 $55.000 $69.810 $55.000 $64.500 $80.000
662 6067 WK ZN PAV MRK REMOV (W)6"(SLD) LF 58,800.000 $1.000 $1.200 $1.400 $1.100 $1.000 $2.000
662 6098 WK ZN PAV MRK REMOV (Y)6"(SLD) LF 44,850.000 $1.000 $1.200 $1.400 $1.100 $1.000 $2.000
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 2,190.000 $1.750 $0.010 $1.400 $5.000 $1.000 $5.000
666 6225 PAVEMENT SEALER 6" LF 47,600.000 $0.500 $0.500 $0.420 $0.330 $0.300 $0.600
666 6305 RE PM W/RET REQ TY I (W)6"(BRK)(090MIL) LF 5,140.000 $0.750 $2.200 $2.790 $2.200 $2.000 $3.000
666 6308 RE PM W/RET REQ TY I (W)6"(SLD)(090MIL) LF 21,630.000 $0.700 $1.700 $2.090 $1.650 $1.500 $2.000
666 6320 RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL) LF 20,830.000 $0.700 $1.700 $2.090 $1.650 $1.500 $2.000
677 6002 ELIM EXT PAV MRK & MRKS (6") LF 58,200.000 $1.000 $0.900 $1.050 $0.830 $0.750 $1.250
678 6002 PAV SURF PREP FOR MRK (6") LF 20,120.000 $0.150 $0.350 $0.350 $0.280 $0.250 $1.000
678 6005 PAV SURF PREP FOR MRK (10") LF 2,280.000 $0.550 $0.750 $0.700 $0.550 $0.500 $1.000
712 6009 JT / CRCK SEAL (HOT - POURED RUBBER) LF 5,112.000 $20.000 $25.000 $80.600 $28.000 $3.300 $95.000
713 6005 CRACK CLEANING AND SEALING (JCP) LF 1,961.000 $25.000 $25.000 $26.440 $75.000 $3.300 $35.000
785 6004 BRIDGE JOINT REPAIR (ARMOR) LF 4.000 $800.000 $500.000 $549.240 $2,000.000 $234.710 $750.000
785 6010 BRIDGE JOINT REPLACEMENT (ARMOR) LF 683.000 $675.000 $550.000 $575.940 $895.000 $234.710 $850.000
785 6011 BRIDGE JOINT REPLACEMENT (SEJ) LF 624.000 $625.000 $600.000 $628.300 $790.000 $354.710 $850.000
785 6015 BRIDGE JOINT REPLACEMENT (SPECIAL) LF 1,560.000 $400.000 $165.000 $415.870 $700.000 $129.710 $650.000
786 6001 CARBON FIBER REINF POLYMER PROTECTION SF 1,200.000 $100.000 $135.000 $51.560 $97.750 $43.560 $70.000
3077 6057 SP MIXES SP-D PG70-28 TON 923.000 $250.000 $475.000 $593.250 $638.000 $566.520 $555.000
3077 6075 TACK COAT GAL 833.000 $10.000 $18.000 $24.570 $12.820 $10.000 $22.000
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $15,000.000 $15,000.000 $13,962.180 $52,000.000 $18,500.000 $18,500.000
6019 6006 PREFB PV MK W/WNTY TY B (W)(6")(SLD) LF 10,160.000 $10.000 $10.000 $12.570 $9.900 $9.000 $14.000
6019 6007 PREFB PV MK W/WNTY TY B(W)6"(BRK)CNTST LF 2,280.000 $13.000 $15.000 $18.850 $14.850 $13.500 $18.000
6019 6014 PREFB PV MK W/WNTY TY B (Y)(6")(SLD) LF 9,960.000 $12.000 $10.000 $12.570 $9.900 $9.000 $14.000
6185 6002 TMA (STATIONARY) DAY 400.000 $400.000 $220.000 $244.340 $300.000 $550.000 $425.000
6185 6003 TMA (MOBILE OPERATION) HR 96.000 $100.000 $150.000 $139.620 $100.000 $95.000 $150.000
6362 6004 REC REFL PAV MRKR TY II-A-A EA 20.000 $10.000 $55.000 $69.810 $55.000 $50.000 $65.000
6362 6005 REC REFL PAV MRKR TY II-C-R EA 380.000 $10.000 $55.000 $69.810 $55.000 $50.000 $65.000
7309 6001 CLEANING STRUCTURE (BENT) EA 28.000 $1,750.000 $1,400.000 $2,802.210 $550.000 $884.140 $1,500.000
7309 6002 CLEANING STRUCTURE (ABUTMENT) EA 24.000 $1,750.000 $1,400.000 $2,802.210 $550.000 $884.140 $1,500.000
Totals: $14,893,248.50 $13,665,830.90 $16,559,110.23 $17,148,698.13 $17,938,471.85 $24,854,638.00