CAMERON FM 3069 (3093-01-002)

Items: 78

County: CAMERON
Length: N/A
Highway: FM 3069
District: PHARR
Control Number: 3093-01-002
DBE Goal: N/A
Project: STP 2022(729)HES
Guaranty: N/A
Time: 224 WORKING DAYS
Engineer's Estimate: $4,967,568.85
Date: 08/04/2022 (3 years ago)
Contract Number: N/A
Type: SAFETY
Mail/Deliver Bids To: N/A
ANDRES ESPINOZA
HECTOR SILLER
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$4,967,568.85
$5,289,300.97
Over/Under Est: 6.48% $321,732.12
Over/Under Est: 24.06% $1,195,372.90
Amt Left: 16.52% $873,640.78
$6,877,330.08
Over/Under Est: 38.44% $1,909,761.23
Amt Left: 30.02% $1,588,029.11
Delta: -11.59% -$714,388.33
$7,046,014.37
Over/Under Est: 41.84% $2,078,445.52
Amt Left: 33.21% $1,756,713.40
Delta: -2.45% -$168,684.29
Subcontractor Percentage Amount
HIGHWAY BARRICADES AND SERVICES, LLC 3.62% $189,732.42
TEXAS ICON CONSTRUCTION, LLC 1.99% $104,300.42
Total: 5.61% $294,032.84

Bid Items & Bid Tabulations

78 Total 0 of 78
CAMERON  |  FM 3069  |  PHARR  |  3093-01-002  |  08/04/2022  |  $4,967,568.85  |  STP 2022(729)HES  |  SAFETY  |  224 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOREMOST PAVING, INC.
TEXAS CORDIA CONSTRUCTION, LLC
ASAGO, LLC
IOC COMPANY, LLC
PREPARING ROW
STA 157.800 $1,800.000 $2,300.000 $890.000 $4,000.000 $2,000.000
REMOVING CONC (DRIVEWAYS)
SY 622.000 $30.000 $10.000 $6.000 $20.000 $15.000
EXCAVATION (ROADWAY)
CY 6,103.000 $8.000 $10.000 $6.000 $6.000 $10.000
EXCAVATION (CHANNEL)
CY 57.000 $10.250 $100.000 $45.000 $30.000 $75.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 2,946.000 $5.000 $9.000 $3.000 $10.000 $20.000
BACKFILL (TY A)
STA 157.800 $150.000 $150.000 $546.000 $160.000 $450.000
FURNISHING AND PLACING TOPSOIL
CY 50.000 $40.000 $20.000 $53.000 $50.000 $75.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 78,181.000 $0.400 $0.420 $0.500 $0.600 $0.850
CELL FBR MLCH SEED(TEMP)(WARM)
SY 78,181.000 $0.400 $0.310 $0.450 $0.500 $0.750
VEGETATIVE WATERING
MG 1,426.000 $30.000 $32.000 $28.000 $50.000 $50.000
SPRINKLING (DUST CONTROL)
MG 631.000 $7.000 $1.000 $18.000 $20.000 $1.000
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS)
CY 8,716.000 $70.000 $85.000 $145.000 $110.000 $125.000
REWRKING BS MTRL(TY B)(5")(DC)(ORG POS)
CY 7,762.000 $6.000 $5.000 $6.000 $12.000 $15.000
LIME TRT (EXST MATL) (12")
SY 62,538.000 $2.000 $2.500 $2.000 $4.000 $3.000
LIME (HYD, COM OR QK)(SLURRY)
TON 1,548.000 $180.000 $225.000 $195.000 $300.000 $220.000
CEMENT
TON 556.000 $180.000 $205.000 $180.000 $220.000 $200.000
CEMENT TRT (MX EXST MTL & NW BS)(10")
SY 59,322.000 $2.000 $2.500 $2.000 $3.000 $3.000
SALV, HAUL & STKPL RCL APH PV (3")
SY 52,383.000 $3.000 $3.000 $4.000 $2.500 $1.750
PRIME COAT (MC-30)
GAL 11,222.000 $5.000 $4.000 $7.000 $7.000 $7.000
ASPH (TIER II)
GAL 16,832.000 $5.000 $6.000 $5.000 $7.500 $7.000
AGGR (TY-B GR-4P SAC-B)
CY 468.000 $90.000 $55.000 $136.000 $115.000 $275.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 756.000 $5.000 $12.000 $3.000 $20.000 $10.000
CEM STABIL BKFL
CY 94.000 $80.000 $45.000 $72.000 $70.000 $115.000
CUT & RESTORING PAV
SY 54.000 $90.000 $100.000 $201.000 $180.000 $195.000
STRUCT EXCAV (SPECIAL)
CY 84.000 $40.000 $50.000 $93.000 $75.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 322.000 $2.950 $5.000 $15.000 $1.500 $1.000
RIPRAP (CONC)(5 IN)
CY 24.000 $450.000 $390.000 $871.000 $850.000 $925.000
RC PIPE (CL III)(18 IN)
LF 2,481.000 $70.000 $55.000 $56.000 $60.000 $95.000
RC PIPE (CL III)(24 IN)
LF 132.000 $90.000 $63.000 $84.000 $80.000 $130.000
RC PIPE (CL IV) (24 IN) (SPL)
LF 45.000 $90.000 $72.000 $104.000 $85.000 $155.000
RC PIPE (CL IV) (30 IN) (SPL)
LF 109.000 $120.000 $92.000 $120.000 $120.000 $172.000
RC PIPE (CL IV) (18") (SPL)
LF 90.000 $70.000 $68.000 $80.000 $68.000 $110.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 3.000 $1,250.000 $1,450.000 $1,251.000 $2,000.000 $1,500.000
SET (TY II) (18 IN) (RCP) (5: 1) (C)
EA 1.000 $1,300.000 $1,450.000 $1,327.000 $2,200.000 $1,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 122.000 $1,250.000 $1,500.000 $1,327.000 $1,200.000 $2,000.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 2.000 $1,350.000 $1,785.000 $1,516.000 $2,600.000 $2,750.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,550.000 $1,850.000 $1,629.000 $2,600.000 $3,500.000
REMOV STR (SET)
EA 30.000 $550.000 $500.000 $401.000 $300.000 $500.000
REMOV STR (PIPE)
LF 2,244.000 $22.000 $7.000 $7.000 $8.000 $20.000
MOBILIZATION
LS 1.000 $490,000.000 $450,000.000 $400,000.000 $680,000.000 $700,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $4,500.000 $4,500.000 $8,000.000 $8,000.000 $8,000.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 312.000 $25.000 $22.000 $22.000 $15.000 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 312.000 $10.000 $10.000 $12.000 $5.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,670.000 $3.300 $3.500 $4.000 $5.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,670.000 $1.300 $1.500 $1.000 $1.500 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,820.000 $6.000 $6.500 $5.750 $7.000 $5.750
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,820.000 $1.300 $1.600 $1.400 $1.500 $2.000
DRIVEWAYS (CONC)
SY 635.000 $80.000 $65.000 $109.000 $75.000 $150.000
DRIVEWAYS (ACP)
SY 2,529.000 $50.000 $55.000 $49.000 $50.000 $55.000
TURNOUTS (ACP)
SY 786.000 $50.000 $90.000 $51.000 $100.000 $75.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 44.000 $255.000 $315.000 $447.000 $350.000 $410.000
ALUMINUM SIGNS (TY A)
SF 12.000 $30.000 $28.000 $30.000 $40.000 $28.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 9.000 $660.000 $800.000 $1,000.000 $800.000 $795.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 7.000 $900.000 $930.000 $1,200.000 $1,000.000 $925.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $1,100.000 $1,050.000 $1,545.000 $1,250.000 $1,050.000
REMOVE SM RD SN SUP&AM
EA 17.000 $90.000 $220.000 $62.000 $80.000 $75.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 8.000 $160.000 $125.000 $142.000 $135.000 $125.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 31,580.000 $0.600 $0.450 $0.450 $0.500 $0.450
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 31,580.000 $0.600 $0.450 $0.450 $0.500 $0.450
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,460.000 $1.500 $1.500 $5.000 $2.000 $0.750
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 42.000 $6.500 $12.000 $12.000 $13.000 $12.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,405.000 $0.400 $0.500 $0.500 $0.520 $0.480
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 8,450.000 $0.400 $0.500 $0.480 $0.520 $0.480
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 31,619.000 $0.500 $0.500 $0.500 $0.520 $0.480
REFL PAV MRKR TY II-A-A
EA 284.000 $4.500 $3.500 $3.000 $3.500 $3.250
TRAFFIC BUTTON TY Y
EA 1,693.000 $3.000 $2.000 $2.000 $2.500 $2.000
TRAFFIC BUTTON TY B
EA 4,717.000 $1.800 $2.000 $2.000 $2.500 $2.000
ELIM EXT PAV MRK & MRKS (4")
LF 26,240.000 $0.350 $0.300 $0.300 $0.400 $0.300
PRSSR IRRIG PVC PIPE (24")
LF 154.000 $70.000 $180.000 $226.000 $200.000 $95.000
PRSSR IRRIG PVC PIPE (12")
LF 80.000 $48.000 $150.000 $149.000 $150.000 $90.000
D-GR HMA TY-D SAC-A PG76-22
TON 9,655.000 $125.000 $127.000 $178.000 $150.000 $168.000
BONDING COURSE
GAL 3,976.000 $5.000 $4.100 $7.000 $6.500 $7.500
GEOGRID BASE REINFORCEMENT (TY II)
SY 59,332.000 $1.400 $1.720 $2.000 $2.500 $3.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $8,000.000 $2,500.000 $7,572.000 $20,000.000 $1,000.000
TMA (STATIONARY)
DAY 224.000 $220.000 $40.000 $10.000 $230.000 $150.000
TMA (MOBILE OPERATION)
DAY 20.000 $220.000 $0.010 $20.000 $250.000 $265.000
CASING (STEEL) (20 IN) (OPEN TRENCH)
LF 50.000 $160.000 $400.000 $401.000 $300.000 $240.000
CASING (STEEL) (30 IN) (OPEN TRENCH)
LF 105.000 $250.000 $475.000 $498.000 $400.000 $250.000
Totals: $4,967,568.850 $5,289,300.970 $6,162,941.750 $6,877,330.080 $7,046,014.370