Job Info for 2529-02-010

County: CAMERON Highway: FM 2556 Date: 07/09/2024 (4 months ago) Engineer's Estimate: $8,651,632 Control Number: 2529-02-010
Project: STP 2B24(212)HES District: PHARR Time: 225 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $8,651,632.20
FOREMOST PAVING, INC.   $7,945,428.50 1
-8.16% | -$706,203.70
IOC COMPANY LLC   $8,822,513.80 2
1.98% | $170,881.60
11.04% | $877,085.30
Subcontractor Percentage Amount
RIO GRANDE REBAR RODBUSTERS, LLC. 4.12% $327,351.65
SOIL TECH ADVANCE INC. 1.26% $100,112.40
DEPENDABLE FENCE 0.77% $61,179.80
HIGHWAY BARRICADES AND SERVICES, LLC 0.43% $34,165.34
TEXAS HIGHWAY SYSTEMS, INC. 0.28% $22,247.20
Total: 6.86% $545,056.39

Bid Items

Items: 65, 0 filtered
CAMERON FM 2556  |  PHARR  |  2529-02-010  |  07/09/2024  |  $8,651,632  |  STP 2B24(212)HES  |  HAZARD ELIM & SAFETY  |  225 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate FOREMOST PAVING, INC. IOC COMPANY LLC
100 6002 PREPARING ROW STA 39.000 $2,600.000 $7,250.000 $7,300.000
104 6027 REMOVING CONC (APPR SLAB) SY 164.000 $60.000 $50.000 $35.000
105 6014 REMOVING STAB BASE & ASPH PAV (7"-12") SY 11,330.000 $13.000 $3.750 $3.000
106 6001 OBLITERATING ABANDONED ROAD STA 22.000 $2,500.000 $150.000 $100.000
110 6001 EXCAVATION (ROADWAY) CY 2,327.000 $12.000 $16.000 $5.000
132 6006 EMBANKMENT (FINAL)(DENS CONT)(TY C) CY 18,438.000 $15.000 $19.000 $22.500
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 38,491.000 $3.000 $4.000 $1.500
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 36,570.000 $0.500 $0.400 $0.390
166 6002 FERTILIZER TON 1.800 $1,200.000 $750.000 $1,000.000
168 6001 VEGETATIVE WATERING MG 615.000 $65.000 $60.000 $35.000
247 6060 FL BS (CMP IN PLC)(TY E GR 4)(FNAL POS) CY 2,799.000 $75.000 $45.000 $61.000
260 6011 LIME TRT (EXST MATL) (12") SY 12,200.000 $5.000 $6.000 $3.250
260 6016 LIME (HYD, COM, OR QK(SLURRY)) TON 302.000 $350.000 $320.000 $200.000
275 6001 CEMENT TON 91.000 $250.000 $190.000 $215.000
275 6009 CEMENT TREAT (NEW BASE) (8") SY 12,110.000 $5.500 $3.500 $3.000
310 6009 PRIME COAT (MC-30) GAL 2,474.000 $6.500 $6.000 $5.000
400 6005 CEM STABIL BKFL CY 224.000 $120.000 $150.000 $100.000
403 6001 TEMPORARY SPL SHORING SF 690.000 $48.000 $1.000 $1.000
416 6001 DRILL SHAFT (18 IN) LF 122.000 $160.000 $245.000 $80.000
416 6003 DRILL SHAFT (30 IN) LF 1,134.000 $280.000 $275.000 $200.000
416 6004 DRILL SHAFT (36 IN) LF 495.000 $320.000 $320.000 $300.000
416 6005 DRILL SHAFT (42 IN) LF 2,445.000 $425.000 $330.000 $375.000
420 6013 CL C CONC (ABUT) CY 62.600 $1,500.000 $1,700.000 $1,800.000
420 6029 CL C CONC (CAP) CY 332.200 $1,700.000 $1,400.000 $1,600.000
420 6037 CL C CONC (COLUMN) CY 207.400 $1,800.000 $1,300.000 $2,000.000
420 6043 CL C CONC (FOOTING) CY 147.000 $1,200.000 $1,100.000 $1,100.000
422 6001 REINF CONC SLAB SF 43,700.000 $27.000 $27.000 $32.500
422 6015 APPROACH SLAB CY 70.600 $800.000 $900.000 $1,000.000
425 6037 PRESTR CONC GIRDER (TX40) LF 4,296.000 $230.000 $200.000 $240.000
425 6039 PRESTR CONC GIRDER (TX54) LF 1,374.000 $230.000 $200.000 $240.000
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 15.000 $200.000 $220.000 $500.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 366.000 $225.000 $205.000 $350.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 78.000 $600.000 $1,000.000 $750.000
450 6006 RAIL (TY T223) LF 1,960.000 $170.000 $145.000 $250.000
454 6001 SEALED EXPANSION JOINT (4 IN) (SEJ - A) LF 226.000 $225.000 $280.000 $250.000
464 6014 RC PIPE (CL III)(72 IN) LF 56.000 $600.000 $900.000 $700.000
464 6025 RC PIPE (CL V)(18 IN) LF 92.000 $140.000 $130.000 $150.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 3.000 $1,400.000 $1,300.000 $1,500.000
467 6506 SET (TY II) (72 IN) (RCP) (4: 1) (P) EA 1.000 $15,000.000 $25,000.000 $15,000.000
496 6006 REMOV STR (HEADWALL) EA 1.000 $1,500.000 $5,000.000 $3,000.000
496 6007 REMOV STR (PIPE) LF 25.000 $25.000 $15.000 $50.000
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $140,000.000 $75,000.000 $10,000.000
496 6043 REMOV STR (SMALL FENCE) LF 1,500.000 $9.000 $5.000 $5.000
500 6001 MOBILIZATION LS 1.000 $810,280.700 $690,000.000 $875,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 15.000 $3,000.000 $5,100.000 $2,500.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 120.000 $40.000 $65.000 $48.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 6,975.000 $4.000 $4.500 $3.000
530 6005 DRIVEWAYS (ACP) SY 80.000 $80.000 $160.000 $100.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,275.000 $32.000 $26.000 $25.500
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $2,300.000 $2,500.000 $2,450.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 825.000 $5.000 $5.000 $5.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 8.000 $250.000 $225.000 $225.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $3,400.000 $3,300.000 $3,265.000
644 6027 IN SM RD SN SUP&AM TYS80(1)SA(P) EA 16.000 $885.000 $800.000 $785.000
644 6030 IN SM RD SN SUP&AM TYS80(1)SA(T) EA 7.000 $850.000 $900.000 $875.000
644 6076 REMOVE SM RD SN SUP&AM EA 14.000 $150.000 $200.000 $200.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 14.000 $40.000 $35.000 $35.000
658 6071 INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI) EA 20.000 $40.000 $25.000 $25.000
666 6174 REFL PAV MRK TY II (W) 6" (SLD) LF 7,770.000 $0.200 $0.600 $0.600
666 6208 REFL PAV MRK TY II (Y) 6" (BRK) LF 50.000 $0.250 $1.100 $1.100
666 6210 REFL PAV MRK TY II (Y) 6" (SLD) LF 7,880.000 $0.200 $0.600 $0.600
672 6009 REFL PAV MRKR TY II-A-A EA 95.000 $7.000 $7.500 $7.500
678 6002 PAV SURF PREP FOR MRK (6") LF 15,630.000 $0.700 $0.200 $0.200
3076 6049 D-GR HMA TY-D SAC-A PG76-22 TON 46.000 $145.000 $160.000 $300.000
3077 6033 SP MIXES SP-C SAC-A PG76-22 TON 1,970.000 $145.000 $160.000 $175.000
Totals: $8,651,632.20 $7,945,428.50 $8,822,513.80