Show Job Controls
Bid Cobra

CAMERON CS (0921-06-252)

Items: 137

County: CAMERON
Length: N/A
Highway: CS
District: PHARR
Control Number: 0921-06-252
DBE Goal: N/A
Project: CBI 2022(173)
Guaranty: N/A
Time: 376 WORKING DAYS
Engineer's Estimate: $8,745,889.12
Date: 12/01/2021 (4 years ago)
Contract Number: N/A
Type: WIDEN ROAD - ADD LANES AND SHOULDERS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (5)
E
Engineer's Estimate
$8,745,889.12
$9,511,089.36
Over/Under Est: 8.75% $765,200.24
Over/Under Est: 12.16% $1,063,675.09
Amt Left: 3.14% $298,474.85
$9,939,998.90
Over/Under Est: 13.65% $1,194,109.78
Amt Left: 4.51% $428,909.54
Delta: -1.33% -$130,434.69
$9,978,824.54
Over/Under Est: 14.1% $1,232,935.42
Amt Left: 4.92% $467,735.18
Delta: -0.39% -$38,825.64
Over/Under Est: 41.55% $3,634,233.24
Amt Left: 30.17% $2,869,033.00
Delta: -24.06% -$2,401,297.82
Subcontractor Percentage Amount
GP7 CONSTRUCTION INC. 10.73% $1,027,373.81
SOIL TECH ADVANCE INC. 5.42% $518,953.03
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. 0.78% $74,683.28
HIGHWAY BARRICADES AND SERVICES, LLC 0.47% $45,001.46
RIO GRANDE REBAR RODBUSTERS, LLC 0.07% $6,702.35
Total: 17.47% $1,672,713.93

Bid Items & Bid Tabulations

137 Total 0 of 137
CAMERON  |  CS  |  PHARR  |  0921-06-252  |  12/01/2021  |  $8,745,889.12  |  CBI 2022(173)  |  WIDEN ROAD - ADD LANES AND SHOULDERS  |  376 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
FOREMOST PAVING, INC.
TEXAS CORDIA CONSTRUCTION, LLC
ASAGO, LLC
IOC COMPANY, LLC
ANDERSON COLUMBIA CO., INC.
PREPARING ROW
STA 161.560 $1,500.000 $4,500.000 $1,000.000 $750.000 $3,500.000 $700.000
REMOVING CONC (PAV)
SY 618.000 $6.000 $4.000 $10.000 $10.000 $15.000 $10.000
REMOVING CONC (SIDEWALKS)
SY 64.000 $6.500 $12.000 $11.000 $10.000 $15.000 $10.000
REMOVING CONC (CURB AND GUTTER)
LF 426.000 $3.250 $4.000 $3.000 $3.000 $8.000 $10.000
REMOVE CONC (GUTTER)
LF 88.000 $5.000 $4.000 $8.000 $6.000 $13.000 $10.000
OBLITERATING ABANDONED ROAD
SY 1,152.000 $24.000 $3.000 $7.000 $5.000 $2.000 $4.000
EXCAVATION (ROADWAY)
CY 43,488.000 $6.000 $3.500 $5.000 $4.000 $2.500 $7.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 100,984.000 $6.500 $6.000 $7.730 $6.000 $7.250 $14.000
FURNISHING AND PLACING TOPSOIL
CY 60.000 $21.000 $25.000 $66.000 $40.000 $25.000 $50.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 141,809.000 $0.400 $0.420 $0.320 $0.350 $0.320 $0.300
CELL FBR MLCH SEED(TEMP)(WARM)
SY 141,809.000 $0.400 $0.420 $0.190 $0.220 $0.190 $0.190
VEGETATIVE WATERING
MG 4,480.000 $18.000 $38.000 $10.000 $30.000 $20.000 $34.000
SPRINKLING (DUST CONTROL)
MG 640.000 $8.000 $1.000 $2.000 $1.000 $0.100 $5.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 22,309.000 $27.000 $0.000 $0.000 $0.000 $0.000 $65.000
LIME TRT (EXST MATL) (12")
SY 82,166.000 $2.600 $3.000 $2.000 $3.500 $1.500 $4.500
LIME (HYD, COM OR QK)(SLURRY)
TON 3,254.000 $190.000 $0.000 $0.000 $0.000 $0.000 $265.000
CEMENT
TON 753.000 $190.000 $0.000 $0.000 $0.000 $0.000 $154.000
CEMENT TREAT (NEW BASE) (10")
SY 80,310.000 $2.000 $0.000 $0.000 $0.000 $0.000 $10.000
PRIME COAT (MC-30)
GAL 16,063.000 $4.000 $4.000 $7.000 $5.200 $4.000 $3.800
ASPH (TIER II)
GAL 25,700.000 $3.500 $5.000 $5.000 $3.550 $3.500 $3.800
AGGR (GR 4P)
CY 670.000 $68.000 $38.000 $84.000 $120.000 $100.000 $100.000
PLAN & TEXT CONC PAV(0" TO 1-1/2")
SY 708.000 $10.000 $15.000 $19.000 $12.000 $3.000 $10.000
CEM STABIL BKFL
CY 1,476.600 $60.000 $41.000 $38.000 $60.000 $50.000 $46.000
STRUCT EXCAV (SPECIAL)
CY 1,405.000 $45.000 $39.000 $52.000 $76.000 $60.000 $42.000
TRENCH EXCAVATION PROTECTION
LF 5,108.000 $2.000 $2.500 $8.000 $3.000 $0.100 $2.000
PRESTR CONC PIL (16 IN SQ)
LF 1,180.000 $65.000 $102.000 $170.000 $255.000 $180.000 $210.000
PRESTR CONC PIL (20 IN SQ)
LF 870.000 $95.000 $120.000 $140.000 $400.000 $189.000 $224.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 60.800 $260.000 $285.000 $270.000 $332.000 $280.000 $280.000
CL C CONC (ABUT)
CY 65.600 $850.000 $1,200.000 $800.000 $1,635.000 $950.000 $930.000
CL C CONC (BENT)
CY 52.000 $855.000 $2,000.000 $890.000 $2,725.000 $1,250.000 $984.000
REINF CONC SLAB
SF 7,560.000 $16.000 $22.000 $15.000 $36.350 $25.000 $26.000
PRESTR CONC GIRDER (TX28)
LF 891.600 $135.000 $170.000 $330.000 $218.000 $146.000 $176.000
RIPRAP (CONC)(5 IN)
CY 985.000 $400.000 $345.000 $420.000 $397.000 $400.000 $345.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 210.300 $150.000 $175.000 $130.000 $181.500 $120.000 $192.000
RIPRAP (MOW STRIP)(4 IN)
CY 110.000 $400.000 $405.000 $440.000 $374.000 $400.000 $400.000
RAIL (TY T223)
LF 408.000 $98.000 $130.000 $170.000 $181.750 $145.000 $175.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 110.000 $100.000 $170.000 $200.000 $260.500 $240.000 $182.000
SRCMP (POLYMER COAT)(GAL ST 24 IN)
LF 2,986.000 $47.000 $0.000 $85.000 $0.000 $0.000 $0.000
RC PIPE (CL III)(72 IN)
LF 1,032.000 $400.000 $350.000 $360.000 $375.000 $320.000 $348.000
RC PIPE (CL III)(18 IN)(SPL)
LF 500.000 $30.000 $39.000 $45.000 $45.000 $69.000 $39.000
RC PIPE (CL III)(24 IN)(SPL)
LF 120.000 $47.000 $0.000 $54.000 $0.000 $0.000 $0.000
RC PIPE (CL III)(36 IN)(SPL)
LF 662.000 $82.000 $94.000 $110.000 $125.000 $120.000 $94.000
RC PIPE (CL III)(48 IN)(SPL)
LF 224.000 $140.000 $134.000 $160.000 $170.000 $160.000 $134.000
RC PIPE (CL III)(60 IN)(SPL)
LF 214.000 $230.000 $185.000 $230.000 $240.000 $235.000 $185.000
RC PIPE (CL IV) (36 IN) (SPL)
LF 88.000 $100.000 $99.000 $130.000 $135.000 $130.000 $99.000
MANH (COMPL)(PRM)(60IN)
EA 6.000 $5,000.000 $3,660.000 $5,330.000 $5,800.000 $4,300.000 $3,700.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 6.000 $3,000.000 $2,880.000 $3,130.000 $5,300.000 $4,000.000 $2,900.000
INLET (COMPL)(PSL)(RC)(8FTX8FT)
EA 1.000 $10,300.000 $12,800.000 $14,020.000 $14,000.000 $25,000.000 $13,000.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 2.000 $4,000.000 $2,800.000 $3,040.000 $5,800.000 $4,300.000 $2,800.000
HEADWALL (CH - PW - 0)(DIA= 24 IN)(MOD)
EA 2.000 $15,000.000 $3,500.000 $7,690.000 $13,700.000 $15,000.000 $3,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 14.000 $800.000 $990.000 $1,010.000 $1,000.000 $750.000 $985.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $1,200.000 $1,200.000 $1,150.000 $1,500.000 $850.000 $1,200.000
SET (TY II) (24 IN) (RCP) (5: 1) (C)
EA 2.000 $1,200.000 $1,400.000 $1,350.000 $2,700.000 $1,000.000 $1,400.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 101.000 $1,100.000 $1,425.000 $1,350.000 $1,800.000 $1,000.000 $1,400.000
REMOV STR (INLET)
EA 1.000 $410.000 $150.000 $590.000 $1,400.000 $500.000 $200.000
REMOV STR (SET)
EA 3.000 $190.000 $150.000 $230.000 $400.000 $300.000 $200.000
REMOV STR (PIPE)
LF 963.000 $9.000 $5.000 $3.000 $10.000 $8.000 $5.000
REMOV STR (IRRIGATION WELL)(EA)
EA 3.000 $700.000 $2,900.000 $2,470.000 $1,000.000 $1,000.000 $3,000.000
REMOV STR (IRRIGATION VENT)
EA 1.000 $500.000 $850.000 $2,420.000 $1,000.000 $1,500.000 $1,000.000
MOBILIZATION
LS 1.000 $789,081.000 $750,000.000 $614,500.000 $358,000.000 $1,000,000.000 $967,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $3,000.000 $3,000.000 $3,670.000 $7,200.000 $796.000 $1,100.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 2,800.000 $30.000 $60.000 $37.000 $35.000 $28.000 $28.000
ROCK FILTER DAMS (REMOVE)
LF 2,800.000 $10.000 $20.000 $19.000 $15.000 $12.000 $12.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 1,092.000 $17.000 $22.000 $9.000 $8.000 $15.000 $10.000
CONSTRUCTION EXITS (REMOVE)
SY 1,092.000 $10.000 $12.000 $4.000 $3.000 $4.000 $6.300
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,065.000 $3.000 $4.000 $4.000 $6.000 $3.500 $3.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,065.000 $1.000 $2.000 $1.000 $2.000 $1.450 $1.500
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 40.000 $2.000 $10.000 $6.000 $12.000 $6.250 $6.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 40.000 $1.000 $5.000 $3.000 $4.000 $3.250 $3.300
CONSTRUCTING DETOURS
SY 62.000 $45.000 $175.000 $85.000 $165.000 $90.000 $105.000
CONC CURB & GUTTER (TY A)
LF 300.000 $12.000 $19.000 $16.000 $20.000 $24.000 $24.000
CONC CURB & GUTTER(VALLEY GUTTER)(48")
LF 212.000 $30.000 $48.000 $37.000 $30.000 $85.000 $47.000
DRIVEWAYS (CONC)
SY 97.000 $53.000 $77.000 $47.000 $83.000 $145.000 $67.000
DRIVEWAYS (ACP)
SY 6,359.000 $26.000 $36.000 $24.000 $35.000 $40.000 $43.000
TURNOUTS (CONC)
SY 279.000 $105.000 $81.000 $77.000 $85.000 $115.000 $120.000
TURNOUTS (ACP)
SY 2,902.000 $40.000 $41.000 $25.000 $45.000 $35.000 $72.000
CONC SIDEWALKS (4")
SY 66.000 $36.000 $85.000 $59.000 $75.000 $125.000 $68.000
CURB RAMPS (TY 1)
EA 4.000 $1,500.000 $1,500.000 $1,580.000 $1,150.000 $2,500.000 $3,430.000
MTL W-BEAM GD FEN (TIM POST)
LF 2,107.000 $23.000 $26.000 $29.000 $28.000 $29.490 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,450.000 $1,900.000 $2,200.000 $2,950.000 $1,949.210 $2,250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 16.000 $2,300.000 $3,200.000 $3,200.000 $3,450.000 $3,349.210 $2,920.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 4.000 $205.000 $300.000 $230.000 $400.000 $300.000 $260.000
CONDT (PVC) (SCH 40) (4")
LF 16.000 $17.000 $40.000 $43.000 $47.500 $40.000 $42.000
ELEC CONDR (NO.6) BARE
LF 70.000 $2.000 $2.000 $2.000 $2.130 $1.800 $2.000
ELEC CONDR (NO.6) INSULATED
LF 140.000 $2.000 $2.000 $2.000 $2.260 $1.900 $2.000
TRAY CABLE (4 CONDR) (12 AWG)
LF 400.000 $2.000 $2.250 $2.000 $2.620 $2.200 $2.300
ZINC-COAT STL WIRE STRAND (3/8")
LF 260.000 $4.000 $1.850 $2.000 $2.020 $1.700 $2.000
ELC SRV TY T 120/240 000(NS)GS(L)TS(O)
EA 2.000 $2,200.000 $2,825.000 $3,030.000 $3,325.000 $2,800.000 $2,940.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 40.000 $535.000 $650.000 $900.000 $693.000 $630.000 $615.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $650.000 $850.000 $900.000 $737.000 $670.000 $630.000
REMOVE SM RD SN SUP&AM
EA 1.000 $64.000 $150.000 $150.000 $153.000 $267.010 $52.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 33.000 $55.000 $55.000 $170.000 $41.800 $38.000 $37.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 179.000 $55.000 $75.000 $180.000 $41.800 $38.000 $37.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 2,809.000 $0.200 $0.500 $0.500 $0.500 $0.450 $0.500
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 44.000 $3.000 $14.000 $14.000 $15.400 $14.000 $15.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 5,702.000 $0.180 $0.500 $0.500 $0.500 $0.450 $0.500
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 108.000 $3.150 $5.000 $5.000 $5.500 $5.000 $5.250
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 600.000 $0.600 $1.000 $1.000 $1.100 $1.000 $1.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 600.000 $0.600 $1.000 $1.000 $1.100 $1.000 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,340.000 $1.200 $1.000 $1.000 $1.100 $1.000 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 231.000 $5.000 $14.000 $14.000 $15.400 $14.000 $15.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 31,453.000 $0.650 $0.450 $0.500 $0.460 $0.420 $0.450
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,420.000 $5.000 $0.450 $0.500 $0.440 $0.400 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 7,703.000 $0.450 $0.450 $0.500 $0.440 $0.400 $0.400
PREFAB PAV MRK TY B (W)(ARROW)
EA 8.000 $300.000 $700.000 $700.000 $770.000 $700.000 $730.000
PREFAB PAV MRK TY B (W)(WORD)
EA 7.000 $400.000 $950.000 $950.000 $1,045.000 $950.000 $1,000.000
REFL PAV MRKR TY I-C
EA 70.000 $4.000 $5.000 $5.000 $5.500 $5.000 $5.250
REFL PAV MRKR TY II-A-A
EA 600.000 $3.600 $5.000 $5.000 $5.500 $5.000 $5.250
ELIM EXT PAV MRK & MRKS (4")
LF 436.000 $0.400 $1.000 $1.000 $1.100 $1.000 $1.000
ELIM EXT PAV MRK & MRKS (24")
LF 82.000 $3.000 $6.000 $6.000 $6.600 $6.000 $6.300
INSTALL HWY TRF SIG (FLASH BEACON)
EA 2.000 $3,400.000 $2,700.000 $2,700.000 $2,968.900 $2,500.000 $2,626.000
VEH SIG SEC (12")LED(YEL)
EA 8.000 $205.000 $285.000 $300.000 $332.520 $280.000 $300.000
VEH SIG SEC (12")LED(RED)
EA 8.000 $208.000 $285.000 $300.000 $332.520 $280.000 $300.000
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
LF 255.000 $2.000 $2.500 $3.000 $2.970 $2.500 $2.600
INS TRF SIG PL AM (S)STR(TY D)LUM
EA 4.000 $5,500.000 $8,600.000 $9,190.000 $10,095.000 $8,500.000 $8,930.000
IRRIGATION GATE (18")
EA 10.000 $2,000.000 $6,500.000 $7,820.000 $6,500.000 $8,500.000 $6,828.000
IRRIGATION GATE (30")
EA 1.000 $3,000.000 $7,500.000 $12,000.000 $11,700.000 $12,000.000 $7,878.000
IRRIGATION GATE (24")
EA 2.000 $3,750.000 $8,600.000 $10,670.000 $10,500.000 $10,000.000 $8,920.000
IRRIGATION WELL (48")
EA 9.000 $8,500.000 $13,600.000 $13,020.000 $7,500.000 $9,000.000 $14,100.000
IRRIGATION WELL (36")
EA 3.000 $8,000.000 $11,300.000 $12,500.000 $7,000.000 $10,000.000 $11,800.000
IRRIGATION VALVE (18")
EA 7.000 $2,000.000 $1,500.000 $2,120.000 $1,700.000 $2,500.000 $1,577.000
IRRIGATION WELL (54")
EA 1.000 $9,000.000 $15,200.000 $13,600.000 $9,000.000 $15,000.000 $15,770.000
IRRIGATION WELL (60")
EA 1.000 $10,000.000 $18,750.000 $14,170.000 $9,500.000 $15,000.000 $19,400.000
D-GR HMA TY-D SAC-B PG64-22
TON 13,201.000 $92.000 $93.000 $106.000 $90.000 $113.000 $105.000
TACK COAT
GAL 7,537.000 $2.980 $3.500 $6.000 $4.250 $3.000 $4.000
RC LOW HEAD PRSSR PIPE (CL III)(18")
LF 917.000 $50.000 $53.000 $75.000 $40.000 $70.000 $55.000
RC LOW HEAD PRSSR PIPE (CL III)(24")
LF 305.000 $75.000 $66.000 $72.000 $75.000 $85.000 $69.000
RC LOW HEAD PRSSR PIPE (CL III)(30")
LF 165.000 $95.000 $88.000 $120.000 $106.000 $105.000 $92.000
RC LOW HEAD PRSSR PIPE (CL III)(48")
LF 264.000 $175.000 $157.000 $170.000 $181.000 $180.000 $164.000
RC LOW HEAD PRSSR PIPE (CL IV)(18")
LF 72.000 $75.000 $65.000 $120.000 $46.000 $80.000 $67.000
GEOGRID BASE REINFORCEMENT (TY II)
SY 80,310.000 $1.300 $1.000 $1.000 $1.100 $1.350 $1.300
BIRD EXCLUSION METHOD
SF 8,760.000 $6.000 $2.250 $8.000 $1.800 $3.000 $6.500
TMA (STATIONARY)
DAY 22.000 $65.000 $200.000 $200.000 $200.000 $250.000 $180.000
1
FL BS (RDWY DEL)(TY E GR 4)(FNAL POS)
CY 22,309.000 $27.000 $34.000 $39.000 $39.000 $37.250 $0.000
1
LIME (HYD, COM OR QK)(SLURRY)
TON 4,007.000 $190.000 $135.000 $210.000 $205.000 $150.000 $0.000
1
LIME TRT (NEW BASE)(10")
SY 80,310.000 $2.000 $1.500 $1.500 $2.350 $1.350 $0.000
2
RC PIPE (CL III)(24 IN)(SPL)
LF 3,106.000 $47.000 $53.000 $0.000 $72.000 $70.000 $53.000
Totals: $10,416,164.120 $9,511,089.360 $9,809,564.210 $9,939,998.900 $9,978,824.540 $12,380,122.360