CAMERON FM 511 (0684-01-069)

Items: 84

County: CAMERON
Length: N/A
Highway: FM 511
District: PHARR
Control Number: 0684-01-069
DBE Goal: N/A
Project: NH 2018(643)
Guaranty: N/A
Time: 180 WORKING DAYS
Engineer's Estimate: $3,589,601.37
Date: 03/06/2018 (8 years ago)
Contract Number: N/A
Type: REHABILITATE PAVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$3,589,601.37
$3,399,954.24
Over/Under Est: -5.28% -$189,647.13
$3,488,856.70
Over/Under Est: -2.81% -$100,744.67
Amt Left: 2.61% $88,902.46
Over/Under Est: -1.73% -$62,162.76
Amt Left: 3.75% $127,484.37
Delta: -1.11% -$38,581.91
$3,707,447.72
Over/Under Est: 3.28% $117,846.35
Amt Left: 9.04% $307,493.48
Delta: -5.10% -$180,009.11
$3,828,310.64
Over/Under Est: 6.65% $238,709.27
Amt Left: 12.6% $428,356.40
Delta: -3.26% -$120,862.92
Over/Under Est: 17.31% $621,393.09
Amt Left: 23.85% $811,040.22
Delta: -10.00% -$382,683.82
Over/Under Est: 26.61% $955,029.07
Amt Left: 33.67% $1,144,676.20
Delta: -7.92% -$333,635.98

Bid Items & Bid Tabulations

84 Total 0 of 84
CAMERON  |  FM 511  |  PHARR  |  0684-01-069  |  03/06/2018  |  $3,589,601.37  |  NH 2018(643)  |  REHAB PAVMT  |  180 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS SAI, INC.
FOREMOST PAVING, INC.
ARANDA BROTHERS CONSTRUCTION CO., INC.
EARTHWORKS ENTERPRISE
IOC COMPANY, LLC
TEXAS CORDIA CONSTRUCTION, LLC
REIM CONSTRUCTION, INC.
REMOVING CONC (DRIVEWAYS)
SY 1,526.000 $6.000 $9.000 $18.000 $10.000 $4.250 $11.000 $4.000 $9.950
REMOVING CONC (CURB AND GUTTER)
LF 200.000 $14.000 $5.000 $6.000 $3.000 $6.700 $10.000 $5.000 $4.500
REMOVING CONC (HEADWALL)
CY 10.000 $125.000 $260.000 $200.000 $150.000 $80.000 $550.000 $275.000 $146.000
REMOVING CONC (SIDEWALK OR RAMP)
SY 100.000 $4.000 $14.000 $19.000 $10.000 $19.500 $30.000 $17.000 $10.500
RMV STAB BASE & ASPH PV (17")
SY 43,513.000 $3.000 $4.500 $4.000 $9.250 $4.500 $7.750 $9.000 $6.250
EXCAVATION (ROADWAY)
CY 2,960.000 $2.500 $9.000 $10.000 $10.000 $12.000 $5.000 $8.000 $8.750
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 960.000 $3.500 $7.000 $12.000 $12.000 $13.800 $5.000 $10.000 $6.150
BACKFILL (TY A)
STA 132.000 $110.000 $225.000 $160.000 $550.000 $206.000 $150.000 $288.000 $153.000
FURNISHING AND PLACING TOPSOIL
CY 50.000 $20.000 $35.000 $25.000 $120.000 $33.000 $40.000 $29.000 $34.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
AC 2.440 $1,200.000 $1,500.000 $1,400.000 $550.000 $1,780.000 $1,500.000 $743.000 $1,710.000
DRILL SEEDING (TEMP) (WARM)
AC 2.440 $700.000 $1,400.000 $1,300.000 $570.000 $1,650.000 $1,400.000 $764.000 $1,590.000
VEGETATIVE WATERING
MG 1,000.000 $5.000 $30.000 $24.000 $15.000 $30.000 $20.000 $27.000 $23.750
SPRINKLING (DUST CONTROL)
MG 1,000.000 $1.000 $30.000 $1.000 $20.000 $70.000 $1.000 $11.000 $23.750
PROOF ROLLING
HR 100.000 $35.000 $75.000 $75.000 $60.000 $30.000 $50.000 $45.000 $50.000
CM TRT(PT MX)(CL M)(TYA)(GR1-2)(FN POS)
CY 19,821.000 $67.000 $52.000 $52.500 $21.000 $65.000 $60.000 $76.000 $83.000
PRIME COAT (MC-30)
GAL 10,194.000 $3.250 $3.500 $4.000 $4.750 $4.250 $3.450 $3.000 $4.180
ASPH (SPG 73-19)
GAL 15,720.000 $2.500 $2.750 $4.000 $3.750 $4.500 $3.000 $3.000 $3.720
AGGR (TY-PD GR-4P)(SAC-B)
CY 450.000 $67.000 $105.000 $65.000 $120.000 $125.000 $75.000 $112.000 $103.000
SUPERPAVE MIXTURES SP-C SAC-A PG76-22
TON 8,200.000 $80.000 $69.800 $81.000 $95.000 $91.000 $80.000 $92.000 $105.000
PLANE ASPH CONC PAV (1.5")
SY 1,200.000 $1.000 $9.000 $7.000 $10.000 $3.200 $3.000 $3.000 $1.850
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 1,800.000 $1.700 $9.000 $5.000 $8.500 $3.200 $3.000 $3.000 $1.750
RIPRAP (MOW STRIP)(4 IN)
CY 20.000 $450.000 $250.000 $500.000 $425.000 $320.000 $450.000 $339.000 $450.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 182.000 $900.000 $650.000 $600.000 $350.000 $900.000 $785.000 $833.000 $762.000
REMOV STR (SET)
EA 186.000 $225.000 $115.000 $220.000 $200.000 $200.000 $150.000 $335.000 $143.000
REMOV STR (PIPE)
LF 3,432.000 $8.000 $6.500 $19.000 $10.000 $10.000 $11.000 $4.000 $7.800
MOBILIZATION
LS 1.000 $266,000.000 $343,434.000 $310,000.000 $345,000.000 $60,000.000 $375,000.000 $270,000.000 $435,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $3,500.000 $5,750.000 $4,500.000 $1,850.000 $5,000.000 $3,000.000 $5,513.000 $8,000.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 40.000 $40.000 $80.000 $78.000 $25.000 $95.000 $55.000 $100.000 $22.000
ROCK FILTER DAMS (REMOVE)
LF 40.000 $10.000 $25.000 $24.000 $5.000 $30.000 $25.000 $31.000 $11.000
CONSTRUCTION EXITS (INSTALL) (TY 2)
SY 1,882.280 $20.000 $20.000 $21.000 $12.000 $25.000 $15.000 $10.000 $14.500
CONSTRUCTION EXITS (REMOVE)
SY 1,882.280 $7.000 $8.000 $9.000 $5.000 $9.000 $3.000 $11.000 $8.250
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,150.000 $2.500 $3.250 $4.000 $4.000 $3.900 $4.250 $0.600 $2.100
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,150.000 $0.700 $0.650 $1.000 $1.000 $0.750 $1.200 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 3,160.000 $2.500 $3.500 $4.000 $7.000 $4.100 $3.750 $4.000 $3.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,160.000 $0.700 $0.500 $1.000 $1.000 $0.600 $0.500 $1.000 $1.000
CONC CURB & GUTTER (TY II)
LF 200.000 $25.000 $26.000 $25.000 $12.000 $23.000 $21.500 $29.000 $14.500
DRIVEWAYS (CONC)
SY 1,526.000 $50.000 $47.000 $44.000 $55.000 $36.500 $53.000 $40.000 $62.500
DRIVEWAYS (ACP)
SY 6,690.000 $27.500 $24.000 $26.000 $32.000 $18.000 $28.000 $15.000 $25.000
CURB RAMPS (TY 1)
EA 1.000 $1,800.000 $455.000 $1,550.000 $1,500.000 $700.000 $1,750.000 $1,100.000 $1,010.000
MTL W-BEAM GD FEN (TIM POST)
LF 300.000 $19.000 $26.000 $29.000 $15.000 $30.000 $35.000 $30.000 $29.500
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,000.000 $2,400.000 $3,500.000 $1,350.000 $2,950.000 $3,000.000 $3,300.000 $2,790.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 42.000 $180.000 $165.000 $200.000 $200.000 $215.000 $400.000 $222.000 $201.000
MAILBOX INSTALL-D (TWG-POST) TY 1
EA 9.000 $180.000 $200.000 $225.000 $195.000 $280.000 $400.000 $285.000 $218.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 2.000 $300.000 $385.000 $600.000 $250.000 $370.000 $500.000 $349.000 $493.000
ALUMINUM SIGNS (TY A)
SF 18.000 $14.000 $18.800 $34.000 $50.000 $120.000 $100.000 $28.000 $21.500
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 22.000 $400.000 $540.000 $400.000 $500.000 $200.000 $600.000 $730.000 $445.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $800.000 $820.000 $660.000 $650.000 $300.000 $750.000 $1,600.000 $619.000
REMOVE SM RD SN SUP&AM
EA 26.000 $40.000 $85.000 $70.000 $150.000 $32.000 $75.000 $150.000 $77.000
INSTL OM ASSM (OM-4)(FLX)GND
EA 8.000 $100.000 $225.000 $200.000 $400.000 $60.000 $75.000 $500.000 $171.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 200.000 $0.750 $0.800 $0.800 $1.000 $1.000 $0.850 $1.000 $0.950
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 26,580.000 $0.600 $0.600 $0.600 $1.000 $0.750 $0.800 $1.000 $0.900
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 27,760.000 $0.600 $0.600 $0.600 $1.000 $0.750 $0.800 $1.000 $0.900
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 200.000 $0.540 $1.400 $1.000 $5.000 $0.950 $2.000 $4.000 $1.350
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,200.000 $0.540 $1.000 $1.000 $3.000 $0.950 $2.000 $4.000 $2.300
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 880.000 $0.740 $1.800 $1.800 $1.600 $2.150 $1.500 $2.000 $1.700
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 860.000 $2.740 $3.400 $3.400 $3.200 $4.000 $3.000 $4.000 $3.400
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 300.000 $6.000 $7.800 $7.800 $6.500 $9.200 $6.000 $7.000 $6.850
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 235.000 $3.000 $3.800 $3.800 $3.250 $4.500 $3.000 $4.000 $3.400
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,226.000 $0.310 $0.450 $0.450 $0.800 $0.750 $0.600 $0.750 $0.700
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 27,600.000 $0.290 $0.340 $0.340 $0.700 $0.500 $0.600 $0.750 $0.700
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 6,340.000 $0.310 $0.360 $0.360 $0.700 $0.500 $0.600 $0.750 $0.700
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 15,100.000 $0.280 $0.340 $0.340 $0.700 $0.500 $0.600 $0.750 $0.700
PREFAB PAV MRK TY C (W) (ARROW)
EA 6.000 $200.000 $220.000 $220.000 $300.000 $260.000 $275.000 $350.000 $313.000
PREFAB PAV MRK TY C (W) (WORD)
EA 6.000 $225.000 $240.000 $240.000 $400.000 $300.000 $375.000 $475.000 $427.000
REFL PAV MRKR TY II-A-A
EA 500.000 $3.000 $2.800 $2.800 $3.750 $3.300 $3.500 $4.000 $4.000
REFL PAV MRKR TY II-C-R
EA 50.000 $3.000 $4.800 $4.800 $3.700 $5.700 $3.500 $4.000 $4.000
ELIM EXT PAV MRK & MRKS (4")
LF 28,800.000 $0.450 $0.800 $0.800 $1.000 $1.000 $0.750 $1.000 $0.800
ELIM EXT PAV MRK & MRKS (8")
LF 1,200.000 $0.500 $0.900 $0.900 $1.700 $1.100 $1.500 $2.000 $1.700
ELIM EXT PAV MRK & MRKS (12")
LF 1,100.000 $2.000 $2.000 $2.000 $2.350 $2.500 $2.250 $3.000 $2.550
ELIM EXT PAV MRK & MRKS (24")
LF 300.000 $2.500 $4.800 $4.800 $4.750 $5.700 $4.500 $6.000 $5.100
ELIM EXT PAV MRK & MRKS (ARROW)
EA 15.000 $40.000 $60.000 $60.000 $85.000 $70.000 $80.000 $100.000 $91.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 8.000 $50.000 $60.000 $60.000 $120.000 $70.000 $100.000 $127.000 $114.000
PAV SURF PREP FOR MRK (4")
LF 3,440.000 $0.350 $0.020 $0.020 $0.500 $0.200 $0.080 $0.500 $0.450
PAV SURF PREP FOR MRK (8")
LF 280.000 $0.600 $0.200 $0.200 $1.000 $0.250 $0.750 $1.000 $0.800
PAV SURF PREP FOR MRK (24")
LF 40.000 $1.000 $1.000 $1.000 $2.500 $1.250 $2.000 $2.500 $2.300
INSTALL HWY TRF SIG (ISOLATED)
EA 2.000 $18,000.000 $20,000.000 $24,000.000 $27,500.000 $27,500.000 $16,200.000 $29,000.000 $18,400.000
THERMOPLASTIC PIPE (18 )(HDPE)
LF 3,336.000 $48.000 $29.850 $0.000 $0.000 $0.000 $0.000 $30.000 $0.000
GEOGRID BASE REINFORCEMENT (TY II)
SY 52,345.000 $1.500 $1.850 $1.600 $3.750 $2.000 $1.350 $1.000 $1.150
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 510.000 $50.000 $16.000 $18.890 $80.000 $65.000 $40.000 $65.000 $37.500
VIVDS PROCESSOR SYSTEM
EA 2.000 $6,000.000 $5,350.000 $8,500.000 $16,500.000 $9,950.000 $4,800.000 $10,800.000 $5,460.000
VIVDS CAMERA ASSEMBLY
EA 8.000 $1,500.000 $1,890.000 $1,600.000 $5,000.000 $2,000.000 $1,650.000 $1,969.000 $1,880.000
VIVDS SET-UP SYSTEM
EA 2.000 $450.000 $610.000 $900.000 $600.000 $1,000.000 $590.000 $1,000.000 $671.000
VIVDS COMMUNICATION CABLE (COAXIAL)
LF 1,275.000 $1.850 $4.250 $3.000 $5.000 $4.000 $4.100 $4.000 $4.650
1
RC PIPE (CL III)(18 IN)
LF 3,336.000 $48.000 $0.000 $30.000 $38.000 $25.000 $40.000 $0.000 $34.000
Totals: $3,749,729.370 $3,399,954.240 $3,488,856.700 $3,527,438.610 $3,707,447.720 $3,828,310.640 $4,210,994.460 $4,544,630.440