CAMERON IH 69E (0039-07-256)
Items: 83
County: CAMERON
Length: N/A
Highway: IH 69E
District: PHARR
Control Number: 0039-07-256
DBE Goal: N/A
Project: NH 2B20(151)
Guaranty: N/A
Time: 184 WORKING DAYS
Engineer's Estimate: $6,314,122.10
Date: 08/05/2020 (5 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,314,122.10 | |||
| $5,394,454.04 |
-14.57%
-$919,668.06
|
|||
| $5,990,608.41 |
-5.12%
-$323,513.69
|
11.05%
$596,154.37
|
||
| $6,252,016.11 |
-0.98%
-$62,105.99
|
15.9%
$857,562.07
|
-4.36%
-$261,407.70
|
|
| $8,141,516.00 |
28.94%
$1,827,393.90
|
50.92%
$2,747,061.96
|
-30.22%
-$1,889,499.89
|
|
| $8,611,857.20 |
36.39%
$2,297,735.10
|
59.64%
$3,217,403.16
|
-5.78%
-$470,341.20
|
E
Engineer's Estimate
$6,314,122.10
1
Awarded
$5,394,454.04
Over/Under Est:
-14.57%
-$919,668.06
$5,990,608.41
Over/Under Est:
-5.12%
-$323,513.69
Amt Left:
11.05%
$596,154.37
$6,252,016.11
Over/Under Est:
-0.98%
-$62,105.99
Amt Left:
15.9%
$857,562.07
Delta:
-4.36%
-$261,407.70
$8,141,516.00
Over/Under Est:
28.94%
$1,827,393.90
Amt Left:
50.92%
$2,747,061.96
Delta:
-30.22%
-$1,889,499.89
$8,611,857.20
Over/Under Est:
36.39%
$2,297,735.10
Amt Left:
59.64%
$3,217,403.16
Delta:
-5.78%
-$470,341.20
| Subcontractor | Percentage | Amount |
|---|---|---|
| GP7 CONSTRUCTION INC. | 38.57% | $2,146,271.43 |
| GO UNDERGROUND, LIMITED LIABILITY COMPANY | 12.13% | $674,987.62 |
| SOIL TECH ADVANCE INC. | 6.25% | $347,788.34 |
| ARTILLERY, LLC | 4.30% | $239,278.38 |
| PAVEMENT MARKINGS INC. | 1.34% | $74,565.82 |
| MVP INSTALLATIONS, L.P. | 0.73% | $40,621.68 |
| AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | 0.65% | $36,169.99 |
| TEXAS HIGHWAY SYSTEMS, INC. | 0.45% | $25,040.76 |
| Total: | 64.42% | $3,584,724.02 |
Bid Items & Bid Tabulations
83
Total
0 of 83