Job Info for 6359-16-001

County: CALLAHAN Highway: FM3217 Date: 12/18/2023 (11 months ago) Engineer's Estimate: $218,400 Control Number: 6359-16-001
Project: MMC - 635916001 District: ABILENE Time: 183 CALENDAR DAYS Type: ROADWAY MATERIALS_AGGREGATES
Notice
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $218,400.00
ZACK BURKETT CO.   $239,745.00 1
9.77% | $21,345.00
VULCAN CONSTRUCTION MATERIALS, LLC   $249,506.00 2
14.24% | $31,106.00
4.07% | $9,761.00

Bid Items

Items: 7, 0 filtered
CALLAHAN FM3217  |  ABILENE  |  6359-16-001  |  12/18/2023  |  $218,400  |  MMC - 635916001  |  ROADWAY MATERIALS_AGGREGATES  |  183 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate ZACK BURKETT CO. VULCAN CONSTRUCTION MATERIALS, LLC
8039 6087 AGGR (TY B GR 3) (DEL) (ST3) TON 300.000 $71.000 $62.400 $68.380
8039 6089 AGGR (TY B GR 3) (DEL) (ST5) TON 550.000 $70.000 $63.300 $62.640
8039 6091 AGGR (TY B GR 3) (DEL) (ST7) TON 500.000 $73.000 $84.000 $81.540
8039 6092 AGGR (TY B GR 3) (DEL) (ST8) TON 350.000 $76.000 $96.600 $94.000
8039 6094 AGGR (TY B GR 3) (DEL) (ST10) TON 500.000 $72.000 $74.400 $84.820
8039 6095 AGGR (TY B GR 3) (DEL) (ST11) TON 500.000 $74.000 $68.100 $74.770
8039 6124 AGGR (TY B GR 5) (DEL) (ST12) TON 500.000 $45.000 $78.300 $82.150
Totals: $218,400.00 $239,745.00 $249,506.00