CALLAHAN IH 20 (0006-07-085)

Items: 27

County: CALLAHAN
Length: N/A
Highway: IH 20
District: ABILENE
Control Number: 0006-07-085
DBE Goal: N/A
Project: C 6-7-85
Guaranty: N/A
Time: 175 WORKING DAYS
Engineer's Estimate: $4,421,986.55
Date: 08/06/2020 (5 years ago)
Contract Number: N/A
Type: CONCRETE MEDIAN BARRIER
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$4,421,986.55
$4,097,726.75
Over/Under Est: -7.33% -$324,259.80
Over/Under Est: -0.47% -$20,725.53
Amt Left: 7.41% $303,534.27
$4,794,555.32
Over/Under Est: 8.43% $372,568.77
Amt Left: 17.01% $696,828.57
Delta: -8.94% -$393,294.30
$4,980,800.00
Over/Under Est: 12.64% $558,813.45
Amt Left: 21.55% $883,073.25
Delta: -3.88% -$186,244.68
$5,320,460.50
Over/Under Est: 20.32% $898,473.95
Amt Left: 29.84% $1,222,733.75
Delta: -6.82% -$339,660.50

Bid Items & Bid Tabulations

27 Total 0 of 27
CALLAHAN  |  IH 20  |  ABILENE  |  0006-07-085  |  08/06/2020  |  $4,421,986.55  |  C 6-7-85  |  CONC MEDIAN BARRIER  |  175 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HJC FARMS, INC.
JAMES CONSTRUCTION GROUP, L.L.C.
A. L. HELMCAMP, INC.
WEBBER, LLC
FNH CONSTRUCTION, LLC
REMOVING CONC (CURB)
LF 432.000 $15.000 $8.000 $3.840 $30.000 $10.000 $20.000
REMOVING CONCRETE(MOW STRIP)
LF 1,181.000 $15.000 $8.000 $5.260 $13.000 $12.000 $20.000
EXCAVATION (ROADWAY)
CY 17.000 $20.000 $7.000 $70.950 $55.000 $28.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 5,330.000 $20.000 $20.000 $20.940 $40.000 $40.000 $30.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 7.000 $1,500.000 $1.000 $560.000 $620.000 $1,500.000 $3,000.000
EMULS ASPH (EROSN CONT)(MS-2)
GAL 3,228.000 $4.000 $5.000 $4.000 $6.000 $10.000 $6.000
CL C CONC (RAIL FOUNDATION)
CY 76.400 $600.000 $500.000 $476.940 $900.000 $725.000 $2,000.000
RIPRAP (CONC)(5 IN)
CY 4.000 $600.000 $500.000 $667.070 $1,200.000 $1,800.000 $650.000
MOBILIZATION
LS 1.000 $403,000.000 $175,000.000 $434,500.000 $400,000.000 $500,000.000 $500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $15,000.000 $2,500.000 $10,000.000 $60,000.000 $40,000.000 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 405.000 $5.000 $5.000 $5.090 $7.000 $15.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 405.000 $2.000 $1.000 $1.000 $3.000 $5.000 $9.000
PERM CTB (SGL SLOPE) (TY 1) (54 )
LF 32,266.000 $100.000 $105.000 $100.000 $96.000 $96.750 $120.000
REMOVE METAL BEAM GUARD FENCE
LF 700.000 $3.000 $3.000 $3.000 $8.000 $15.000 $3.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 5.000 $500.000 $300.000 $250.000 $400.000 $350.000 $500.000
REMOVE CABLE BARRIER
LF 32,323.000 $4.000 $2.250 $8.800 $4.000 $8.500 $2.000
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $500.000 $300.000 $300.000 $560.000 $350.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 3.000 $200.000 $100.000 $50.000 $230.000 $258.000 $650.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 132.000 $30.000 $6.000 $18.000 $40.000 $25.250 $100.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 34,953.000 $0.350 $1.000 $0.500 $0.370 $0.500 $0.500
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 8,066.000 $0.350 $2.000 $1.440 $1.050 $3.000 $5.000
REFL PAV MRKR TY II-C-R
EA 404.000 $5.000 $10.000 $5.760 $4.200 $8.000 $8.000
ELIM EXT PAV MRK & MRKS (4")
LF 34,953.000 $0.300 $1.000 $0.500 $0.370 $1.000 $1.000
TMA (STATIONARY)
DAY 522.000 $250.000 $200.000 $142.090 $230.000 $295.000 $350.000
TMA (MOBILE OPERATION)
DAY 15.000 $250.000 $200.000 $453.980 $300.000 $755.000 $550.000
TEMP Q-DETECT SYS
EA 1.000 $130,000.000 $50,000.000 $38,374.630 $45,000.000 $72,500.000 $68,000.000
TEMP Q-DETECT SYS (RELOCATE)
EA 2.000 $2,000.000 $2,500.000 $500.000 $1,000.000 $1,449.750 $10,000.000
Totals: $4,421,986.550 $4,097,726.750 $4,401,261.026 $4,794,555.320 $4,980,800.000 $5,320,460.500