CALHOUN SH0185 (6467-08-001)

Items: 15

County: CALHOUN
Length: N/A
Highway: SH0185
District: YOAKUM
Control Number: 6467-08-001
DBE Goal: 0.0%
Project: RMC - 646708001
Guaranty: N/A
Time: 75 W
Engineer's Estimate: $1,986,616.45
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: THERMOPLASTIC PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
CAMILLE MAREK
KELLY ROTHER
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,986,616.45
Over/Under Est: -36.68% -$728,675.32
Over/Under Est: -34.62% -$687,863.86
Amt Left: 3.24% $40,811.46
$1,299,356.54
Over/Under Est: -34.59% -$687,259.91
Amt Left: 3.29% $41,415.41
Delta: -0.05% -$603.95
Over/Under Est: -20.73% -$411,919.73
Amt Left: 25.18% $316,755.59
Delta: -21.19% -$275,340.18
Over/Under Est: -17.55% -$348,608.92
Amt Left: 30.21% $380,066.40
Delta: -4.02% -$63,310.81
$1,736,034.20
Over/Under Est: -12.61% -$250,582.25
Amt Left: 38.01% $478,093.07
Delta: -5.98% -$98,026.67
$1,870,629.72
Over/Under Est: -5.84% -$115,986.73
Amt Left: 48.71% $612,688.59
Delta: -7.75% -$134,595.52

Bid Items & Bid Tabulations

15 Total 0 of 15
CALHOUN  |  SH0185  |  YOAKUM  |  6467-08-001  |  08/01/2024  |  $1,986,616.45  |  RMC - 646708001  |  THERMOPLASTIC PAVMT MRK  |  75 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY BARRICADES AND SERVICES, LLC
CENTERLINE TECHNOLOGIES, LLC
STRIPE LINES, INC.
TRP INFRASTRUCTURE SERVICES, LLC
INTERSTATE BARRICADES & MARKINGS, INC.
STRIPE-A-ZONE, LLC
PAVEMENT MARKINGS INC.
MOBILIZATION
LS 1.000 $180,000.000 $5,000.000 $1.000 $5,000.000 $20,000.000 $15,000.000 $25,000.000 $45,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $2,500.000 $500.000 $1.000 $500.000 $1,000.000 $500.000 $1,200.000 $100.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 6,535.000 $1.050 $0.880 $0.950 $0.830 $1.000 $0.950 $0.900 $2.200
RE PM W/RET REQ TY I (W)6"(BRK)(060MIL)
LF 8,018.000 $0.450 $0.380 $0.330 $0.320 $0.400 $0.450 $0.550 $0.680
RE PM W/RET REQ TY I (W)6"(SLD)(060MIL)
LF 1,537,296.000 $0.450 $0.310 $0.330 $0.310 $0.380 $0.430 $0.450 $0.440
RE PM W/RET REQ TY I (Y)6"(BRK)(060MIL)
LF 299,515.000 $0.450 $0.380 $0.330 $0.320 $0.400 $0.450 $0.520 $0.550
RE PM W/RET REQ TY I (Y)6"(SLD)(060MIL)
LF 744,533.000 $0.450 $0.310 $0.330 $0.320 $0.380 $0.450 $0.450 $0.480
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 409,890.000 $0.750 $0.620 $0.640 $0.710 $0.800 $0.650 $0.760 $0.850
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 41,865.000 $0.750 $0.680 $0.640 $0.710 $0.850 $0.650 $0.840 $0.950
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 173,477.000 $0.750 $0.620 $0.640 $0.710 $0.800 $0.650 $0.760 $0.900
TMA (MOBILE OPERATION)
DAY 250.000 $500.000 $5.000 $1.000 $1.990 $100.000 $200.000 $1.000 $10.000
HPPM-RIB W/RET REQ TYI(W)6"(BRK)100MIL
LF 8,370.000 $0.600 $0.620 $0.800 $0.530 $0.550 $0.500 $0.720 $1.400
HPPM-RIB W/RET REQ TYI(W)6"(SLD)100MIL
LF 34,533.000 $0.600 $0.620 $0.800 $0.530 $0.550 $0.500 $0.710 $1.200
HPPM-RIB W/RET REQ TYI(Y)6"(BRK)100MIL
LF 800.000 $0.600 $0.620 $1.000 $1.530 $0.550 $0.500 $0.760 $2.200
HPPM-RIB W/RET REQ TYI(Y)6"(SLD)100MIL
LF 3,160.000 $0.600 $0.620 $0.800 $1.530 $0.550 $0.500 $0.710 $1.600
Totals: $1,986,616.450 $1,257,941.130 $1,298,752.590 $1,299,356.540 $1,574,696.720 $1,638,007.530 $1,736,034.200 $1,870,629.720