Job Info for 0913-19-028

County: CALHOUN Highway: CR Date: 01/04/2017 (7 years ago) Engineer's Estimate: $473,543 Control Number: 0913-19-028
Project: BR 2012(730) District: YOAKUM Time: 60 WORKING DAYS Type: REPLACE BRIDGE AND APPROACHES

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $473,543.00
REXCO CONSTRUCTION SERVICES, INC.   $416,186.67 1
-12.11% | -$57,356.33
CONSTAR CONSTRUCTION   $421,834.00 2
-10.92% | -$51,709.00
1.36% | $5,647.33
LESTER CONTRACTING, INC.   $474,995.42 3
0.31% | $1,452.42
14.13% | $58,808.75
12.60% | $53,161.42
LISKA CONSTRUCTION COMPANY, INC.   $477,816.43 4
0.9% | $4,273.43
14.81% | $61,629.76
0.59% | $2,821.01
3LW MANAGEMENT, LLC   $496,272.00 5
4.8% | $22,729.00
19.24% | $80,085.33
3.86% | $18,455.57
TREVWAY, INC.   $529,878.13 6
11.9% | $56,335.13
27.32% | $113,691.46
6.77% | $33,606.13
SJ&J CONSTRUCTION, LLC   $694,266.00 7
46.61% | $220,723.00
66.82% | $278,079.33
31.02% | $164,387.87

Bid Items

Items: 36, 0 filtered
CALHOUN CR  |  YOAKUM  |  0913-19-028  |  01/04/2017  |  $473,543  |  BR 2012(730)  |  REPLACE BRIDGE AND APPROACHES  |  60 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate REXCO CONSTRUCTION SERVICES, INC. CONSTAR CONSTRUCTION LESTER CONTRACTING, INC. LISKA CONSTRUCTION COMPANY, INC. 3LW MANAGEMENT, LLC TREVWAY, INC. SJ&J CONSTRUCTION, LLC
104 6009 REMOVING CONC (RIPRAP) SY 17.000 $25.000 $109.750 $31.000 $52.000 $424.530 $30.000 $88.930 $80.000
110 6001 EXCAVATION (ROADWAY) CY 313.000 $15.000 $21.500 $17.000 $26.840 $7.290 $25.000 $24.150 $15.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 277.000 $35.000 $49.380 $19.000 $54.000 $9.520 $30.000 $108.830 $30.000
150 6002 BLADING HR 10.000 $100.000 $100.000 $110.000 $205.000 $111.000 $300.000 $100.000 $100.000
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 640.000 $0.250 $3.750 $2.000 $3.250 $3.850 $3.500 $3.000 $0.500
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 160.000 $0.250 $8.560 $2.000 $11.850 $2.570 $3.500 $3.000 $0.500
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 160.000 $0.250 $8.560 $2.000 $11.850 $2.570 $3.500 $3.000 $0.500
168 6001 VEGETATIVE WATERING MG 5.800 $30.000 $69.550 $170.000 $420.000 $111.370 $85.000 $100.000 $60.000
247 6366 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) CY 299.000 $120.000 $114.900 $110.000 $108.000 $110.640 $70.000 $172.000 $80.000
310 6009 PRIME COAT (MC-30) GAL 234.000 $5.000 $11.340 $15.000 $10.400 $7.700 $5.000 $19.260 $10.000
316 6249 AGGR(TY-PE GR-4 SAC-B) CY 18.000 $70.000 $408.330 $1,100.000 $855.500 $721.500 $500.000 $1,284.210 $500.000
316 6400 ASPH (AC-15P OR AC-10-2TR OR CRS-2P) GAL 796.000 $5.000 $6.950 $12.000 $6.900 $7.700 $4.000 $15.000 $8.000
400 6005 CEM STABIL BKFL CY 134.000 $150.000 $94.550 $70.000 $120.000 $192.540 $200.000 $150.000 $180.000
403 6001 TEMPORARY SPL SHORING SF 1,260.000 $20.000 $11.750 $20.000 $12.000 $12.940 $25.000 $45.000 $20.000
432 6002 RIPRAP (CONC)(5 IN) CY 25.000 $450.000 $299.080 $320.000 $633.200 $849.360 $550.000 $300.000 $1,000.000
432 6024 RIPRAP (STONE COMMON)(DRY)(12 IN) CY 16.000 $150.000 $213.790 $120.000 $300.000 $281.810 $250.000 $200.000 $180.000
450 6006 RAIL (TY T223) LF 62.000 $135.000 $156.190 $130.000 $556.000 $351.690 $180.000 $200.000 $220.000
460 6019 CMP (GAL STL 21 IN) LF 10.000 $70.000 $144.600 $60.000 $91.000 $134.160 $60.000 $189.000 $90.000
460 6036 CMP (ALUMINUM 18") LF 51.000 $80.000 $46.840 $65.000 $57.000 $51.980 $50.000 $100.000 $300.000
460 6037 CMP (ALUMINUM 24") LF 70.000 $110.000 $48.480 $70.000 $61.000 $52.730 $60.000 $100.000 $400.000
462 6026 CONC BOX CULV (9 FT X 7 FT) LF 182.000 $1,000.000 $666.990 $600.000 $592.000 $492.230 $850.000 $475.000 $1,000.000
466 6211 WINGWALL (SW - 0) (HW=8 FT) EA 1.000 $6,500.000 $20,859.600 $25,000.000 $30,800.000 $27,513.000 $18,000.000 $15,180.470 $35,000.000
466 6212 WINGWALL (SW - 0) (HW=9 FT) EA 1.000 $7,500.000 $21,549.750 $26,000.000 $32,900.000 $28,153.300 $19,000.000 $17,330.390 $40,000.000
467 6348 SET (TY II) (18 IN) (CMP) (6: 1) (P) EA 1.000 $1,500.000 $1,262.300 $1,200.000 $1,250.000 $1,361.500 $1,100.000 $1,760.000 $2,000.000
467 6380 SET (TY II) (24 IN) (CMP) (6: 1) (P) EA 2.000 $1,500.000 $1,378.740 $1,300.000 $2,400.000 $858.250 $1,450.000 $1,000.000 $2,000.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $15,000.000 $9,150.000 $8,000.000 $6,600.000 $29,369.000 $5,000.000 $20,000.000 $25,000.000
496 6042 REMOV STR (SMALL) EA 3.000 $1,750.000 $955.000 $800.000 $1,000.000 $1,311.000 $600.000 $2,015.660 $500.000
500 6001 MOBILIZATION LS 1.000 $26,359.000 $31,300.000 $35,000.000 $27,475.000 $51,156.000 $45,000.000 $60,000.000 $160,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $3,000.000 $869.380 $1,000.000 $1,200.000 $1,764.840 $10,000.000 $800.000 $4,000.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 135.000 $50.000 $47.080 $50.000 $55.000 $36.080 $40.000 $10.000 $25.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 135.000 $15.000 $29.960 $20.000 $11.000 $15.410 $15.000 $5.000 $10.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 430.000 $4.000 $6.960 $5.000 $3.250 $6.010 $4.500 $3.000 $3.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 430.000 $2.000 $2.940 $2.000 $2.000 $1.200 $1.500 $3.000 $1.000
530 6016 DRIVEWAYS (BASE) SY 182.000 $25.000 $28.500 $30.000 $31.000 $26.110 $12.500 $25.000 $50.000
545 6001 CRASH CUSH ATTEN (INSTL) EA 4.000 $15,000.000 $11,903.750 $12,000.000 $13,500.000 $13,502.810 $11,000.000 $15,000.000 $5,000.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 6.000 $35.000 $20.330 $45.000 $35.000 $106.750 $25.000 $33.000 $60.000
Totals: $473,543.00 $416,186.67 $421,834.00 $474,995.42 $477,816.44 $496,272.00 $529,878.13 $694,266.00