Job Info for 6364-21-001

County: CALDWELL Highway: FM0020 Date: 09/02/2021 (3 years ago) Engineer's Estimate: $608,980 Control Number: 6364-21-001
Project: BPM - 636421001 District: AUSTIN Time: 32 W Type: SCOUR AND EROSION CONTROL

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $608,979.70
DEAN WORD COMPANY, LTD.   $675,857.89 1
10.98% | $66,878.19
RESTEK, INC.   $734,172.54 2
20.56% | $125,192.84
8.63% | $58,314.65
SCOTT TUCKER CONSTRUCTION COMPANY, LLC   $744,045.57 3
22.18% | $135,065.87
10.09% | $68,187.68
1.34% | $9,873.03
BECK-REIT & SONS, LTD.   $781,886.80 4
28.39% | $172,907.10
15.69% | $106,028.91
5.09% | $37,841.23
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.   $801,044.60 5
31.54% | $192,064.90
18.52% | $125,186.71
2.45% | $19,157.80
DAN WILLIAMS COMPANY   $922,718.44 6
51.52% | $313,738.74
36.53% | $246,860.55
15.19% | $121,673.84
SCR CIVIL CONSTRUCTION, LLC   $991,703.76 7
62.85% | $382,724.06
46.73% | $315,845.87
7.48% | $68,985.32
AARON CONCRETE CONTRACTORS, L.P.   $1,132,914.80 8
86.03% | $523,935.10
67.63% | $457,056.91
14.24% | $141,211.04

Bid Items

Items: 22, 0 filtered
CALDWELL FM0020  |  AUSTIN  |  6364-21-001  |  09/02/2021  |  $608,980  |  BPM - 636421001  |  SCOUR AND EROSION CONTROL  |  32 W
Item code Description Unit Quantity Engineer's Estimate DEAN WORD COMPANY, LTD. RESTEK, INC. SCOTT TUCKER CONSTRUCTION COMPANY, LLC BECK-REIT & SONS, LTD. DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC. DAN WILLIAMS COMPANY SCR CIVIL CONSTRUCTION, LLC AARON CONCRETE CONTRACTORS, L.P.
100 6002 PREPARING ROW STA 10.000 $2,000.000 $3,300.000 $1,500.000 $1,377.710 $2,000.000 $4,000.000 $5,000.000 $8,500.000 $4,400.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 612.000 $1.500 $7.018 $8.750 $9.760 $8.000 $3.000 $1.250 $11.500 $7.000
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 612.000 $0.700 $0.260 $1.750 $1.060 $1.500 $1.250 $1.400 $0.280 $0.300
168 6001 VEGETATIVE WATERING MG 91.040 $25.000 $34.100 $50.000 $121.390 $20.000 $65.000 $16.000 $130.000 $35.000
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 612.000 $5.000 $2.860 $1.870 $3.610 $5.000 $3.000 $1.500 $3.100 $3.600
401 6001 FLOWABLE BACKFILL CY 32.000 $300.000 $235.400 $350.000 $526.640 $333.000 $200.000 $450.000 $800.000 $370.000
420 6158 CL C CONC(PILE ENCASEMENT) LF 92.000 $435.000 $183.150 $500.000 $596.370 $450.000 $335.000 $400.000 $630.000 $910.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 260.000 $300.000 $344.289 $225.000 $278.750 $188.000 $650.000 $380.000 $250.000 $435.000
432 6030 RIPRAP (STONE COMMON)(GROUT)(12 IN) CY 619.000 $225.000 $176.968 $295.000 $242.660 $288.000 $220.000 $350.000 $322.000 $455.000
438 6001 CLEANING AND SEALING EXISTING JOINTS LF 1,748.000 $20.000 $16.640 $22.500 $16.570 $24.000 $20.000 $18.000 $23.000 $14.000
446 6002 CLEAN & PAINT EXIST STR (SYSTEM II) LS 1.000 $125,000.000 $193,703.900 $180,000.000 $193,711.210 $250,000.000 $200,000.000 $260,000.000 $211,000.000 $255,000.000
454 6008 HEADER TYPE EXPANSION JOINT CF 242.800 $260.000 $300.560 $372.500 $293.080 $310.000 $300.000 $325.000 $480.000 $715.000
500 6001 MOBILIZATION LS 1.000 $55,361.700 $67,254.130 $40,000.000 $74,481.900 $75,000.000 $45,000.000 $90,000.000 $99,100.000 $60,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $5,000.000 $7,230.695 $15,380.000 $5,372.020 $4,000.000 $10,000.000 $5,000.000 $16,000.000 $9,300.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 166.000 $23.000 $18.980 $28.250 $30.230 $25.000 $19.000 $24.000 $25.000 $24.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 166.000 $10.000 $5.772 $22.350 $11.570 $10.000 $6.000 $19.000 $6.200 $7.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,458.000 $3.000 $3.120 $5.000 $3.680 $2.000 $4.000 $4.000 $4.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,458.000 $0.700 $0.520 $1.250 $1.180 $1.000 $1.000 $1.000 $0.600 $0.700
770 6017 REALIGN POSTS EA 1.000 $50.000 $330.000 $1,000.000 $1,586.980 $1,000.000 $5,000.000 $140.000 $950.000 $1,100.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 74.000 $95.000 $110.000 $50.000 $78.380 $110.000 $75.000 $95.000 $100.000 $150.000
6185 6002 TMA (STATIONARY) DAY 40.000 $185.000 $203.500 $75.000 $188.560 $1.000 $245.000 $190.000 $370.000 $520.000
7000 6001 REML & DISPL DRIFTWOOD & DEBRIS CY 20.000 $80.000 $330.000 $150.000 $398.520 $120.000 $185.000 $125.000 $200.000 $604.000
Totals: $608,979.70 $675,857.91 $734,172.54 $744,045.58 $781,886.80 $801,044.60 $922,718.44 $991,703.76 $1,132,914.80